TOWNSHIP OF BENSALEM v. LENNAR MPA, LLC

CourtDistrict Court, E.D. Pennsylvania
DecidedApril 23, 2025
Docket2:23-cv-05113
StatusUnknown

This text of TOWNSHIP OF BENSALEM v. LENNAR MPA, LLC (TOWNSHIP OF BENSALEM v. LENNAR MPA, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TOWNSHIP OF BENSALEM v. LENNAR MPA, LLC, (E.D. Pa. 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA

TOWNSHIP OF BENSALEM : Plaintiff, :

v. : CIVIL NO. 23-5113

LENNAR MPA, LLC et al., : Defendants.

Scott, J. April 22, 2025

MEMORANDUM

This dispute comes from a two-and-a-half-page contract between Plaintiff Township of Bensalem (“Bensalem”) and Defendants Lennar MPA, LLC, Lennar MPA WIP, LLC, and Lennar Corporation (collectively, “Lennar”). At its most basic level, the contract, known as the Revised Impact Fee Agreement Waterside — Phase 2 and Phase 3 (“RIFA,” ECF No. 12-4), sets out the terms under which Lennar is to construct an improvement to a segment of State Road in Bensalem, Pennsylvania (“State Road improvement project” or “SRIP”) in exchange for the Township’s assistance in funding the improvement and its waiver of certain fees related to Lennar’s development project to which the Township would otherwise be entitled. Lennar argues that it exercised its termination rights under the RIFA and, upon providing a contractually determined sum to Bensalem, no longer has any obligations regarding the SRIP. Bensalem argues that no such

termination right exists and that Lennar has materially breached the RIFA by refusing to construct the improvement to State Road promptly and expeditiously. Lennar has moved for partial judgment on the pleadings on Count I of its counterclaims, which seeks a declaratory judgment that Lennar has, among other things, “duly terminated” the RIFA. ECF No. 4 at §§ 50-61. Bensalem has moved for judgment on the pleadings on the entirety of Lennar’s counterclaims, pointing out that all of Lennar’s dominoes stand or fall together insofar as each counterclaim hinges on the propriety of Lennar’s purported termination. ECF No. 13 § 19. Because the RIFA is ambiguous and because the Court will likely benefit from discovery related to the issues discussed below, the Court denies Lennar’s motion for partial judgment on the pleadings and denies Bensalem’s motion for judgment on the pleadings. 1. Background A. Factual Background 1. The RIFA Agreement Lennar took over from a prior developer the responsibility for Waterside, a residential land development project located between State Road and the Delaware River in Bensalem, Pennsylvania. ECF No. 1-1 (“Complaint”) §§1-2; 4-9. State Road is the only street that provides access to Waterside. ECF 13-2 at3 n.1. To complete the project and to comply with various local ordinances, Lennar entered into agreements with Bensalem. One such agreement was the RIFA, which modified an earlier fee agreement between the Parties and was signed in October 2019. Comp. § 35. According to the RIFA, Lennar “agreed to construct the entire State Road Improvement Project subject to the terms of this Agreement,” RIFA § 1, and Bensalem agreed to reimburse Lennar for the cost of the completion for any amount in excess of $1,128,112.00. RIFA § 2. Paragraph 4 of the RIFA specifies that Lennar “shall act promptly in commencement and

completion” of the SRIP and that Lennar “shall comply with all PennDOT requirements, directions and procedures necessary for the expeditious completion” of the SRIP. Finally, Paragraph 5—the locus of the present dispute—states in its entirety: “In the event that this Agreement is terminated prior to the approved completion of Phase 2 and Phase 3, then all unpaid Phase 2 and Phase 3 recreation fees along with impact fees shall become due and owing.” RIFA § 5. 2. Lennar’s Alleged Termination of the Agreement and Bensalem’s Refusal to Issue Use & Occupancy Certificates On December 21, 2023—more than four years after the Parties signed the RIFA—Lennar sent Bensalem a letter, informing Bensalem that Lennar “has exercised its rights” under the RIFA and has terminated the Agreement. ECF 12-6 at 3. Additionally, Lennar’s letter calculated the amount owed to Bensalem as $720,836.80, which, when combined with the $407,275.20 already collected by the Township, purportedly equals the total financial burden for which Lennar would have been responsible in constructing the SRIP (and after which Bensalem would be financially responsible) under the RIFA. Jd. Bensalem never responded directly to the letter. ECF 49 12. Instead, Lennar alleges that Bensalem withheld issuing two Use & Occupancy Certificates that are needed for Lennar to complete agreements to sell two residences within the Waterside development. B. Procedural History Bensalem filed this action in the Pennsylvania Court of Common Pleas approximately three weeks before Lennar sent its December 21 termination letter. Lennar then removed this action to federal court pursuant to 28 U.S.C. § 1332 on December 26, 2023. Bensalem’s Complaint seeks to void past transfers and enjoin future transfers between the various Lennar entities under Pennsylvania’s Voidable Transactions Act, 12 Pa.S.C.A. § 5101(b) (Count I), to obtain relief under the theory that Lennar’s failure to build the SRIP constitutes a

breach of contract (Count ID) or, in the alternative, specific performance from Lennar for breach of contract (Count III), or, also in the alternative, promissory estoppel under the theory that Lennar has made certain promises with respect to constructing the SRIP (Count IV). On January 4, 2024, Lennar filed its answer to Bensalem’s Complaint and its own counterclaims. ECF No. 4. Lennar seeks declaratory judgment that it, among other things, has duly terminated the RIFA (Count I), declaratory judgment that Bensalem has no legal basis to withhold the Use & Occupancy Certificates and that such certificates be released immediately to Lennar (Count I), declaratory judgment that a certain Letter of Credit sent by Bensalem to Lennar be declared null and void (Count II), relief under the theory that Bensalem has tortiously interfered with Lennar’s contracts to sell certain Waterside residences (Count IV), relief under the theory that Bensalem’s Complaint and its refusal to issue the remaining Use & Occupancy certificates amounts to abuse of process (Count V), and an injunction that orders Bensalem to stop withholding the Use & Occupancy certificates (Count VI). On April 5, 2024, Lennar filed its motion for partial judgment on the pleadings, namely seeking judgment as a matter of law on Count I of its counterclaims. ECF No. 12. On the same day, Bensalem filed its own motion for judgment on the pleadings, seeking judgment as a matter of law in its favor on the entirety of Lennar’s counterclaims. ECF No. 13. Each party filed responses to the respective motions on May 3, 2024. ECF Nos. 16, 17. Both motions are fully briefed and ripe for disposition. I. Legal Standard Motions for judgment on the pleadings are “analyzed under the same standards that apply to a Rule 12(b)(6) motion.” Wolfington v. Reconstructive Orthopaedic Assocs. IT PC, 935 F.3d 187, 195 (3d Cir. 2019) (internal citations and quotation marks omitted). Accordingly, the court must “view the facts presented in the pleadings and the inferences to be drawn therefrom in the

light most favorable to the nonmoving party, and may not grant the motion unless the movant clearly establishes that no material issue of fact remains to be resolved and that he is entitled to judgment as a matter of law.” Jd. (internal citations and quotation marks omitted). “In deciding a motion for judgment on the pleadings, a court may only consider the complaint, exhibits attached to the complaint, matters of public record, as well as undisputedly authentic documents if the complainant’s claims are based upon these documents. /d. (internal citations and quotation marks omitted); Zucker v. Quasha, 891 F. Supp. 1010, 1013 (D.N.J.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bass v. Hoagland
172 F.2d 205 (Fifth Circuit, 1949)
Zucker v. Quasha
891 F. Supp. 1010 (D. New Jersey, 1995)
Z & L LUMBER OF ATLASBURG v. Nordquist
502 A.2d 697 (Supreme Court of Pennsylvania, 1985)
Kripp v. Kripp
849 A.2d 1159 (Supreme Court of Pennsylvania, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
TOWNSHIP OF BENSALEM v. LENNAR MPA, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/township-of-bensalem-v-lennar-mpa-llc-paed-2025.