Towne Realty, Inc. v. A-1 Hydro Mechanics Corp. (In Re A-1 Hydro Mechanics Corp.)

92 B.R. 451, 1988 Bankr. LEXIS 1746, 1988 WL 112280
CourtUnited States Bankruptcy Court, D. Hawaii
DecidedOctober 19, 1988
Docket16-00051
StatusPublished
Cited by2 cases

This text of 92 B.R. 451 (Towne Realty, Inc. v. A-1 Hydro Mechanics Corp. (In Re A-1 Hydro Mechanics Corp.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Hawaii primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Towne Realty, Inc. v. A-1 Hydro Mechanics Corp. (In Re A-1 Hydro Mechanics Corp.), 92 B.R. 451, 1988 Bankr. LEXIS 1746, 1988 WL 112280 (Haw. 1988).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

JON J. CHINEN, Bankruptcy Judge.

The evidentiary hearing on the ownership of certain materials turned over by A-l Hydro Mechanics Corporation (“Defendant”), the above-named Debtor, to Towne Realty, Inc. and Towne Realty of Hawaii, Inc. (collectively “Plaintiff”), pursuant to the Order Granting Motion for Temporary Restraining Order entered herein on February 18,1988, was held on March 29, April 26, and May 4, 1988. Appearances were made by Susan Tius, Esq. for Plaintiff, Colin K. Kurata, Esq., special counsel for Defendant, and Michael Chun, Esq. for the Internal Revenue Service (“IRS”). The Court, having heard the evidence, the representations and argument of counsel, makes the following Findings of Fact and Conclusions of Law:

FINDINGS OF FACT

1. Plaintiff is the General Contractor under a contract (“Prime Contract”) with the Department of Navy, as Owner, for a project for the construction of seven buildings known as the BEQ Modernization Project (“BEQ Project”).

2. On or about May 28, 1987, Plaintiff, as Contractor, entered into a Subcontract Agreement (“the Subcontract”) with Defendant, as Subcontractor, for the total Subcontract price of $1,143,100.00.

3. Under the Subcontract, the Defendant agreed to furnish the plumbing, masonry and sheet metal work, equipment, and materials for the construction of the seven buildings at the BEQ Project.

4. The Subcontract includes the following terms:

(1)Within 30 days after entering into the Subcontract, Defendant will make commitments to all material suppliers and provide copies of purchase orders to Plaintiff for approval.

(2) Each purchase order must state the Government Contract Number and the date by which the materials must be delivered “FOB jobsite”.

(3) Defendant will promptly make payments to all persons supplying labor, materials, and supplies; Plaintiff may make any payments which Defendant fails to make, the amounts thereof deducted from any monies earned or due the Defendant under the Subcontract.

(4) Defendant may submit an application for partial payment with required supporting data by the 25th of each month. Plaintiff will make the partial payments due Defendant by the 15th day of the following month.

(5) Such partial payments will equal the value of the work done by the Defendant according to the owner’s certificate, if applicable, less a retainage of 10% for labor, materials, and equipment, and less any other amounts retained or deducted under the terms of the Subcontract.

(6) If at any time there shall be any evidence or notice of any lien or claim for which it is established that the Plaintiff is liable, the Plaintiff shall have the right to retain out of any partial payment an amount sufficient to completely indemnify itself against any such claim or lien.

(7) Upon the completion of the Prime Contract and the approval by the Government of the work, the Subcontractor will be paid the remaining amount due the Subcontractor, less an adequate retainage for warranty work, provided that the Contractor shall have the same rights and conditions as before making payment.

5. The Defendant delegated the masonry portion of the Subcontract to International Masons (“IM”), a division of the Defendant.

6. On or about June 26, 1987, the Defendant commenced performance of the Subcontract. The Defendant and IM, for the period from commencement of the *453 work through September 25, 1987, submitted three initial applications for payment, which applications were paid as requested less 10% retention.

7. On these initial three applications for payment, Defendant and IM certified that Defendant had paid for the labor and material costs covered by the applications. However, they had not paid their workers and suppliers and were not able to furnish releases from the workers and suppliers against the Plaintiffs surety bond.

8. All of the completed forms of applications for payment submitted by the Defendant and IM to Plaintiff from commencement of the job until termination of the Subcontract on January 25, 1988 failed to furnish releases. Such failure of Defendant and IM to furnish releases to Plaintiff is a breach of Article XVLl.b. of the Subcontract.

9. Sometime around October of 1987, Plaintiff became aware that Defendant and IM were not paying the material suppliers and various wages and benefits owed for the work done by their employees on the BEQ Project.

10. Under the Miller Act, suppliers of materials and workers on the BEQ Project for amounts due them, but not paid, have the right to make claims against the surety bond given by Plaintiff to the Navy to secure Plaintiffs performance of the work.

11. Plaintiff, sometime in October of 1987, in order to assure that no claims were made against Plaintiff’s bond, commenced paying wages to the employees of Defendant and IM, as well as making payment to union trust funds for fringe benefits and dues, material suppliers, insurance carriers, and federal and state taxes.

12. The Defendant and IM orally or in writing authorized and instructed Plaintiff with reference to the parties and amounts to be paid.

13. Pursuant to the instructions given by Defendant, Plaintiff promptly issued checks to the creditor or joint checks to the Defendant and the creditor. Additionally, Plaintiff, at the request of the Defendant and material suppliers who were not willing to extend credit to the Defendant, entered into Joint Check Agreements with Defendant and the suppliers.

14. As required by the Subcontract, Defendant had specially ordered the materials it needed for the BEQ Project. Despite the provision of the Subcontract that the materials be delivered to the jobsite, Defendant arranged for delivery of some of the materials to its warehouse.

15. During December 1987 and January 1988, Plaintiffs General Superintendent, John Hertzberg, repeatedly contacted Ken Lucky, the Project Coordinator for the Defendant, to deliver all of the materials to the BEQ jobsite. However, Defendant failed to do as requested.

16. On or about January 15, 1988, Defendant filed a Second Motion for Approval of Rejection of Certain Executory Contracts seeking Court approval to reject the Subcontract, stating that the Subcontract “will result in losses for the Estate herein and further, are not assignable for any possible benefits to the Estate.”

17. Defendant delayed giving notice to Plaintiff of the Motion to reject the Subcontract for ten days, but Plaintiff learned of the Motion on January 25, 1988 through a creditor of the Defendant.

18. On January 25, 1988, without prior notice to Plaintiff, Defendant’s employees came to the BEQ jobsite to pick up personal belongings, and Defendant ceased work on the Subcontract. As a result, by letter dated January 25, 1988, Plaintiff terminated the Subcontract for material and/or anticipatory breach under the provisions of Article XII, Paragraph 2. In the letter, Plaintiff cites the January 15,1988 filing of the Motion to reject the contract and the January 25, 1988 withdrawal of the workers and certain equipment by Defendant as grounds of termination.

19.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Welt v. Sasson (In Re Dollar Time Group, Inc.)
223 B.R. 237 (S.D. Florida, 1998)
In Re Sluss
107 B.R. 599 (E.D. Tennessee, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
92 B.R. 451, 1988 Bankr. LEXIS 1746, 1988 WL 112280, Counsel Stack Legal Research, https://law.counselstack.com/opinion/towne-realty-inc-v-a-1-hydro-mechanics-corp-in-re-a-1-hydro-mechanics-hib-1988.