Town of Windham v. Sean Reese and Elizabeth Reese

CourtSupreme Court of Vermont
DecidedNovember 9, 2011
Docket2011-053
StatusUnpublished

This text of Town of Windham v. Sean Reese and Elizabeth Reese (Town of Windham v. Sean Reese and Elizabeth Reese) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Windham v. Sean Reese and Elizabeth Reese, (Vt. 2011).

Opinion

Note: Decisions of a three-justice panel are not to be considered as precedent before any tribunal.

ENTRY ORDER

SUPREME COURT DOCKET NO. 2011-053

NOVEMBER TERM, 2011

Town of Windham } APPEALED FROM: } v. } Superior Court, Windham Unit, } Civil Division } Sean Reese and Elizabeth Reese } DOCKET NO. 456-10-053 Wmcv

Trial Judge: John P. Wesley David A. Howard

In the above-entitled cause, the Clerk will enter:

Defendants Sean and Elizabeth Reese appeal the superior court’s denial of their requests for relief from prior orders finding them in civil contempt and imposing daily fines until they addressed the overflow from a pond on their property to a neighboring property and town highway. We affirm, except that we reduce the amount of the ultimate fine by $150.

In the fall of 2003, the Town of Windham filed suit against defendants to collect damages and obtain an injunction to halt an ongoing overflow from defendants’ pond that had flooded a town highway. The pond was created by water build-up in a talc mine previously operated on defendants’ property. In March 2004, the Byron W. McCandless Trust, which owns property downhill from the pond, moved to intervene on the side of the Town. On April 4, 2007, following a four-day trial in October 2006, the superior court issued a decision concluding that defendants’ failure to control the flow of water from the pond “caused significant present and continuing injury to each of the Plaintiffs.” The court denied compensatory damages for lack of proof but granted injunctive relief subject to a further evidentiary hearing and supplemental findings concerning the appropriate scope of the relief.

On August 14, 2007, after conclusion of the follow-up hearing during which both sides presented the testimony of expert witnesses, the superior court issued a final injunction ordering that defendants “shall take immediate steps to lower the surface of the . . . pond by at least fifteen feet from the elevation at which water commences to spill over the edge, which shall be accomplished no later than October 1, 2007 except for good cause shown,” and further “shall with all deliberate speed take steps necessary to design, obtain necessary permits and construct a permanent regulated outflow system that insures that the level of the water in the pond does not rise higher than two feet below the level at which it commences to spill” unless they obtain a regulatory permit that approves a higher elevation. With regard to the latter permanent solution, the court ordered defendants to furnish the Town and the Trust, no later than December 15, 2007, completed engineering and construction plans at least twenty days before submitting an application for regulatory approvals. The court expressly recognized that “even assuming all deliberate speed” in implementing a permanent solution to the overflow, the permitting process and construction most likely could not be completed before the coming winter. Nevertheless, because of its conclusion that the “present unregulated flows” from the pond posed “a significant danger” of creating permanent wetlands and erosion on the Trust’s property, as well as winter ice sheeting on the town highway, defendants were required “to take such steps as necessary to immediately reduce the level of the pond by at least 15 feet.”

On October 1, 2007, the same day by which defendants had been ordered to complete “immediate steps” to abate the pond’s overflow, defendants filed a motion seeking relief from the court’s judgment imposing a final injunction. Three days later, the Trust filed a motion to hold defendants in civil contempt for failure to take immediate steps to lower the pond’s water level, as ordered by the court. The court held a hearing on the two motions on October 29, 2007. Defendants did not appear at the hearing or present any evidence, but their attorney made statements regarding his attempts to satisfy the court’s injunction. The attorney acknowledged that the pond overflow had not been drawn down, but he explained that he had participated in a September 17 site visit with an employee of the Agency of Natural Resources (ANR), who informed him that there was “no way” defendants would be allowed to pump into the stream by the October 1 deadline the amount of water necessary to satisfy the court’s injunction. The attorney explained that he never received a written statement from the ANR employee to this effect, as promised, and that he was shuffled to three different departments before he was finally told that he needed to provide a proposed drawdown rate from a hydrologist, which he had done that morning.

On November 1, 2007, the court granted the Trust’s motion for contempt based on defendants’ failure to do any actual construction or work “to attempt even minimal temporary alleviation of the overflow problem.” The court accepted the attorney’s statements regarding his belated attempts to determine whether defendants would need regulatory approval to pipe water across the Trust property into a nearby stream, but concluded that there was “no reliable evidence that the [settling] ponds on defendants’ property could not have been used to give some temporary relief with or without a permit of any sort or at least investigated as a possible temporary solution.” The court found that defendants’ lack of effort was willful and that they had failed to demonstrate that they could not have complied with the court’s injunction and alleviated the overflow situation, noting that its previous order had not limited defendants’ options to pumping water over the Trust property and into the nearby stream but rather had “left open that there could be other solutions.” Based on these findings and conclusions, the court ordered defendants to pay $50 per day beginning October 31, 2007 “until such time as the level of the water is drawn down at least two feet below the level at which water commences to spill over the edge or by plaintiff and intervenor stipulation as to a higher level or until further relief is granted by the court for good cause,” and then $20 per day “until the level is drawn down to the fifteen foot level of the court’s order or by plaintiff and intervenor stipulation as to a higher level or until further relief is granted by the court for good cause.”

Over the ensuing months, defendants filed several motions seeking relief from the court’s order that they pay daily fines for any continuing noncompliance with its final injunction. In December 2008, the parties entered into a stipulation that resolved some of the compliance issues. They agreed that the level of the water reached two feet below the spill elevation by March 1, 2008. They also agreed that maintaining the water three feet, rather than fifteen feet,

2 below the spillage level would satisfy the court’s injunction, thereby effectively ending the daily fines as of October 15, 2008, when the water was reduced to that level. In a November 2010 order, the superior court rejected defendants’ arguments in support of their motion for relief from paying the daily fines it had incurred under the court’s previous order, concluding that defendants had been “dilatory in getting regulators involved, an aspect of compliance that was entirely foreseeable.” Nevertheless, the court gave the parties time to submit further memoranda concerning any further stipulation they might have and the Trust’s request that the fines be paid directly to it rather than the state’s general fund. In a January 2011 order, the court denied defendants’ motion for relief from paying the fines, which the court calculated at $10,610. The court also denied the Trust’s motions for attorney’s fees and for allocation of payment of the fines directly to it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sheehan v. Ryea
757 A.2d 467 (Supreme Court of Vermont, 2000)
Sandgate School District v. Cate
2005 VT 88 (Supreme Court of Vermont, 2005)
Socony Mobil Oil Company v. NORTHERN OIL COMPANY
225 A.2d 60 (Supreme Court of Vermont, 1966)
Vermont Women's Health Center v. Operation Rescue
617 A.2d 411 (Supreme Court of Vermont, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Town of Windham v. Sean Reese and Elizabeth Reese, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-windham-v-sean-reese-and-elizabeth-reese-vt-2011.