Town of Slidell v. Temple

155 So. 2d 681
CourtLouisiana Court of Appeal
DecidedJune 3, 1963
DocketNo. 5861
StatusPublished
Cited by6 cases

This text of 155 So. 2d 681 (Town of Slidell v. Temple) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Slidell v. Temple, 155 So. 2d 681 (La. Ct. App. 1963).

Opinion

LANDRY, Judge.

This is an appeal from a judgment in favor of plaintiff municipality and its sewerage district for damages resulting from the alleged defective installation of a sanitary sewer line manifested by failure of the line commencing nine months subsequent to acceptance of the work by the municipality and resulting in total failure thereof five weeks thereafter.

Except as hereinafter otherwise noted, the facts and circumstances giving rise to the instant lawsuit are not in dispute between the parties. By contract executed January 21, 1959, defendant, Hollis R. Temple, t/a Temple Construction Company (sometimes hereinafter referred to simply as “contractor”), undertook installation of [683]*683a certain sewer project for plaintiffs, the Town of Slidell, Louisiana, and Sewerage District No. 1 — A, Town of Slidell, Louisiana, (sometimes hereinafter collectively referred to simply as “Municipality” or “Town”), said work to he performed according to plans and specifications therefor prepared by the firm of Carnegie & Smith, Consulting Engineers.

At the point of failure the line (consisting of fifteen inch vitrified day pipe) was laid in water-bearing sand at a depth of approximately ten feet as a segment of a gravity flow sewerage system. Before the line was laid the trench was dried by means of well points thus providing a proper foundation in which the pipe was installed according to contract specifications calling for excavations to accommodate the bell joint of each length of pipe in order that full bearing was had upon the barrel of each section. All joints were sealed and the trench in which the line was laid was back-filled and tamped in accordance with contract specifications. The line was put into service in or about October, 1959, and a pre-existing 8-inch subdivision line was tied into the system at a manhole situated approximately sixty feet south of the point of failure. The municipality formally accepted the work in April, 1960. Subsequently, in or about December, 1960, (slightly longer than a year after the line was put in use, a sinking of the surface soil was noted above the point of eventual failure. Approximately five weeks thereafter the line collapsed and failed completely whereupon Contractor and his surety were promptly notified of the break but defendant refused and declined to take any action to remedy the defect on the ground he had satisfactorily performed all obligations under the construction contract and was not responsible for the condition which resulted. Pending some action by the contractor, the municipality was compelled to dispose of sewerage by dumping same into open ditches. When the municipality became convinced contractor would assume no liability for the condition of the line the services of Clifford C. Ouder, contractor, were engaged to excavate at the point of failure to determine the nature and cause of the defect. Upon excavation of the failure site, it developed that from three to five lengths of pipe had settled or sunk, the lowest point being approximately 18 inches below grade. The pipe, however, was intact excepting one or two joints at which the bell of the pipe was broken on top. South or upgrade from the break the pipe was found to be clear of sand but north or downgrade the line contained a large accumulation of sand which clogged the line for a distance of approximately 300 feet but did not completely block the line. Upon discovering the aforesaid condition, the municipality employed a Mr. Ouder to make the necessary repairs. When it developed Ouder was unable to free the line of accumulated sand, the services of Rotor Rooter Sewer Company were engaged for that purpose. The entire cost of repair amounted to a total of $5,199.53, for which sum the trial court awarded judgment in plaintiff’s favor.

The issue before the court on appeal is conceded by all 'concerned to be purely factual. Tersely stated, the question is: What caused this particular section of the sewer line to collapse?

In order that the position of the municipality may be better understood we deem it advisable to narrate in some detail certain circumstances concerning which there is no dispute between the litigants but which, nevertheless, are material to the factual issue to be resolved herein.

During the construction process, it developed that water-bearing sands were encountered in certain areas of the municipality necessitating the installation of “well points” which the record discloses constitutes in essence a system of pumps designed to free the trench of water to provide a firm sand bed on which to lay the lines. At the point of failure water bearing sand was encountered but well points were installed and the trench properly dried and prepared prior to installation of the line. Lengths of [684]*684vitrified clay sewer pipe fifteen inches in diameter were utilized in constructing the line. Each length of pipe was so constructed that one end was larger than the other. The larger end of each section of pipe was so made that it flared out in the nature of a bell consequently, in the trade the larger portion of each pipe length is known and referred to as the “bell”. The purpose of the bell is to admit the end of the adjoining length of pipe to be inserted therein a distance of approximately two inches thus providing a continuous, unbroken conduit or line. The joints thusly formed, however, do not result in a complete seal and if left in this condition would permit the escape of sewerage as well as admit into the line entry of dirt and sub-surface water, neither of which conditions may be tolerated. Each joint, therefore, is sealed with a cement mixture known as "grout” or by a procedure known as “pouring”. The pouring process consists ,of two stages, the first of which is referred to as "caulking”. According to the record, caulking is an operation wherein a twine like material known as “Oakum” is packed and compressed into the entire circumference of the interior of each bell opening by means of a blunt metal instrument or tool thus blocking and stopping up the opening otherwise existing in the joint. After the Oakum is properly packed around the entire joint circle, molten asphalt is then poured completely around the bell opening adhering to the pipe and oakum and forming an effective seal preventing leakage. It is conceded that in the case at bar although the contract specified all joints made in the trench would be sealed with grout, such closures, with the knowledge, consent and approval of the Consulting Engineer, were in fact mainly accomplished by pouring. It is conceded that if a joint is improperly or defectively sealed the action of sub-surface water will-cause dirt surrounding the leak to enter the line eventually producing a cavity or hole beneath the line in the vicinity of the leak and ultimately undermining the pipe and causing its collapse.

Succinctly put, the municipality contends the joints at the site of the break were improperly and defectively sealed thus admitting the flow of sand into the line and creating a cavity which caused the line to sink and break. Needless to say, appellants maintain the work was performed in a satisfactory manner in strict accordance with the contract terms and specifications and contractor is, therefore, not responsible for damage resulting from unknown circumstances considering, according to defendant, the cause of the break has not been shown with any degree of certainty.

We shall first dispose of appellants' complaint that the trial court erroneously based its decision on the testimony of the Honorable Homer G. Fritchie, Mayor of the Town of Slidell.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Succession of Mary Lou Thrasher
Louisiana Court of Appeal, 2018
Commonwealth v. Petrey
945 S.W.2d 417 (Kentucky Supreme Court, 1997)
Young v. All American Assurance Company
243 So. 2d 894 (Louisiana Court of Appeal, 1971)
Matthews v. All American Assurance Company
226 So. 2d 181 (Louisiana Court of Appeal, 1969)
Deposit Guaranty National Bank v. Shipp
205 So. 2d 101 (Louisiana Court of Appeal, 1968)
Bonilla v. Arrow Food Distributors, Inc.
202 So. 2d 438 (Louisiana Court of Appeal, 1967)
Town of Slidell v. Temple
156 So. 2d 232 (Supreme Court of Louisiana, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
155 So. 2d 681, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-slidell-v-temple-lactapp-1963.