Town of Sandy Creek v. East Coast Contracting, Inc.

736 S.E.2d 793, 224 N.C. App. 537, 2012 WL 6587864, 2012 N.C. App. LEXIS 1445
CourtCourt of Appeals of North Carolina
DecidedDecember 18, 2012
DocketNo. COA12-561
StatusPublished
Cited by2 cases

This text of 736 S.E.2d 793 (Town of Sandy Creek v. East Coast Contracting, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Sandy Creek v. East Coast Contracting, Inc., 736 S.E.2d 793, 224 N.C. App. 537, 2012 WL 6587864, 2012 N.C. App. LEXIS 1445 (N.C. Ct. App. 2012).

Opinion

McCullough, Judge.

The City of Northwest (“Northwest”), appeals from the trial court’s denial of its motion to dismiss East Coast Contracting, Inc.’s (“ECC”) third-party complaint. For the following reasons, we affirm the denial of Northwest’s motion on the limited basis of governmental immunity.

I. Background

This case began 9 September 2010 when The Town of Sandy Creek (“Sandy Creek”) filed suit against ECC, Engineering Services, [538]*538PA (“ES”), and individuals seeking recovery for damages to Sandy Creek roads allegedly caused by ECC while ECC was constructing a sewer system for Northwest. Sandy Creek’s complaint alleged that Sandy Creek and Northwest discussed plans for a sanitary sewer system for their respective municipalities prior to November 2007. Thereafter, Northwest contracted with ES and ECC to design and construct the sewer system. Sandy Creek, who alleges to be a third-party beneficiary to the contracts, further alleged that they incurred damages as a result of the sewer system and that the “damages were caused by deficiencies and defects in the design, drawings, engineering, supervision, specifications, final plans, planning, coordination and workmanship provided by ES” and that ECC’s “work deviated from the standard of care such that they breached their duties to [Sandy Creek].”

With Sandy Creek’s original suit pending, ECC filed a third-party complaint against Northwest on 12 November 2010 alleging breach of contract, negligence, and indemnity and contribution. Northwest then filed a Rule 12(b)(6) motion to dismiss on 14 February 2011. Northwest’s motion came on for hearing at the 9 December 2011 Civil Session of Brunswick County Superior Court, the Honorable Ola M. Lewis presiding. The trial court filed an order on 13 February 2012 denying Northwest’s motion to dismiss.

Northwest now appeals the order upon the trial court’s Rule 54(b) certification and the stay of ECC’s third-party claims.

II. Analysis

On appeal, Northwest contends that the trial court erred by denying its motion to dismiss ECC’s third-party claims. “[A] motion to dismiss under N.C. R. Civ. P. 12(b)(6) tests the legal sufficiency of the complaint.” Stanback v. Stanback, 297 N.C. 181, 185, 254 S.E.2d 611, 615 (1979). On appeal, “[t]his Court must conduct a de novo review of the pleadings to determine their legal sufficiency and to determine whether the trial court’s ruling on the motion to dismiss was correct.” Leary v. N.C. Forest Prods., Inc., 157 N.C. App. 396, 400, 580 S.E.2d 1, 4, aff’d per curiam, 357 N.C. 567, 597 S.E.2d 673 (2003). “In ruling on the motion the allegations of the complaint must be viewed as admitted, and on that basis the court must determine as a matter of law whether the allegations state a claim for which relief may be granted.” Stanback, 297 N.C. at 185, 254 S.E.2d at 615.

[539]*539Appealability

“Generally, there is no right of immediate appeal from interlocutory orders and judgments.” Goldston v. American Motors Corp., 326 N.C. 723, 725, 392 S.E.2d 735, 736 (1990). “An interlocutory order is one made during the pendency of an action, which does not dispose of the case, but leaves it for further action by the trial court in order to settle and determine the entire controversy.” Veazey v. Durham, 231 N.C. 357, 362, 57 S.E.2d 377, 381 (1950). An order denying a motion to dismiss is therefore an interlocutory order and not generally immediately appealable.

However,

immediate appeal of interlocutory orders and judgments is available in at least two instances. First, immediate review is available when the trial court enters a final judgment as to one or more, but fewer than all, claims or parties and certifies there is no just reason for delay.... Second, immediate appeal is available from an interlocutory order or judgment which affects a “substantial right.”

Sharpe v. Worland, 351 N.C. 159, 161-62, 522 S.E.2d 577, 579 (1999) (citations omitted). “ ‘[T]his Court has repeatedly held that appeals raising issues of governmental or sovereign immunity affect a substantial right sufficient to warrant immediate appellate review.’ ” Reid v. Town of Madison, 137 N.C. App. 168, 170, 527 S.E.2d 87, 89 (2000) (quoting Price v. Davis, 132 N.C. App. 556, 558-59, 512 S.E.2d 783, 785 (1999) (citations omitted)).

In the present case, ECC asserted claims for breach of contract, negligence, and indemnity and contribution against Northwest. Upon Northwest’s Rule 12(b)(6) motion to dismiss ECC’s claims, the trial court refused to dismiss the case. Yet, by the same order denying dismissal, the trial court certified the issue of immunity for appeal, stating “[ijnasmuch as the question of whether the Third-Party Complaint is barred by governmental immunity affects substantial rights of Northwest so as to present no just reason for delay, . . . this matter is certified pursuant to N.C.R.C.P. Rule 54(b) for immediate appeal.” Thus, to the extent it is alleged that governmental immunity bars ECC’s negligence claim, we review the interlocutory order denying dismissal.

[540]*540Despite conceding that ECC’s breach of contract claim is not barred by governmental immunity, Northwest requests that we review the entire case in order to prevent piecemeal litigation. We decline Northwest’s request. Where there is no substantial right at stake as a result of the trial court’s denial of Northwest’s motion to dismiss ECC’s breach of contract claim and where the trial court only certified the issue of governmental immunity for appeal, we limit our scope of review as we have done in previous cases. See, e.g., Clayton v. Branson, 153 N.C. App. 488, 570 S.E.2d 253 (2002); Dempsey v. Halford, 183 N.C. App. 637, 645 S.E.2d 201 (2007). Thus, the sole issue on appeal is whether the trial court erred in denying Northwest’s motion to dismiss ECC’s negligence claim because Northwest is entitled to governmental immunity.

Governmental Immunity

“In North Carolina the law on governmental immunity is clear. In the absence of some statute that subjects them to liability, the state and its governmental subsidiaries are immune from tort liability when discharging a duty imposed for the public benefit.” McIver v. Smith, 134 N.C. App. 583, 585, 518 S.E.2d 522, 524 (1999).

In this case, Northwest first argues that it is entitled to governmental immunity because ECC failed to plead statutory authorization to sue the city and failed to plead waiver of immunity. Thus, citing Morrison-Tiffin v. Hampton, 117 N.C. App. 494,

Related

Bynum v. Wilson County
746 S.E.2d 296 (Court of Appeals of North Carolina, 2013)
Howard v. County of Durham
748 S.E.2d 1 (Court of Appeals of North Carolina, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
736 S.E.2d 793, 224 N.C. App. 537, 2012 WL 6587864, 2012 N.C. App. LEXIS 1445, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-sandy-creek-v-east-coast-contracting-inc-ncctapp-2012.