Town of Northumberland v. Sterman

246 A.D.2d 729, 667 N.Y.S.2d 505, 1998 N.Y. App. Div. LEXIS 172
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJanuary 8, 1998
StatusPublished
Cited by1 cases

This text of 246 A.D.2d 729 (Town of Northumberland v. Sterman) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Northumberland v. Sterman, 246 A.D.2d 729, 667 N.Y.S.2d 505, 1998 N.Y. App. Div. LEXIS 172 (N.Y. Ct. App. 1998).

Opinion

Yesawich Jr., J.

Proceeding pursuant to CPLR article 78 (transferred to this Court by order of the Supreme Court, entered in Albany County) to review a determination of respondent Commissioner of Environmental Conservation which granted respondent Saratoga County a permit to construct and operate a landfill.

In this transferred CPLR article 78 proceeding, petitioner, the Town of Northumberland (hereinafter the Town) in Sara-toga County, challenges several decisions of respondent Deputy Commissioner of Environmental Conservation (hereinafter the Commissioner) leading to the eventual issuance of a permit for the construction and operation of a landfill in the Town. After the permit application was filed by respondent Saratoga County (hereinafter the County), an issues conference was held (see, 6 NYCRR 624.4 [b]), at which the Town (having been granted party status) requested permission to access the proposed landfill site to conduct soil permeability testing pursuant to 6 NYCRR 624.7 (c). The Administrative Law Judge (hereinafter ALJ), finding that the Town had demonstrated the existence of an adjudicable issue (see, 6 NYCRR 624.4 [c]), with respect to whether the County’s permeability test results were reliable—and hence whether the latter had adequately proven its entitlement to a variance from the groundwater separation [730]*730requirement (see, 6 NYCRR 360-2.13 [d]; 360-1.7 [c] [2] [iii])1 —concluded that the discovery requested by the Town would provide relevant evidence bearing on the resolution of this issue, and granted the desired access. Upon the County’s appeal, however, this decision was modified by the Commissioner, who, though he agreed that an issue had been raised regarding the safety of the groundwater, found further testing unwarranted, and denied the Town’s discovery request. The Town contends that this decision was erroneous.

Following the issues conference, the ALJ also concluded that the Town had raised several other substantive and significant issues requiring adjudication, including whether the proposed project would have a negative impact upon the Northern Harrier, a threatened wildlife species found in the area; whether the site selection process complied with the relevant criteria; whether compliance with the groundwater separation requirement would impose an unreasonable economic burden on the County and whether the noise levels at the site would exceed the applicable limits. The Commissioner, disagreeing with several of the ALJ’s rulings, concluded that no adjudicable issue had been posed with respect to the site selection study or the economic impact of satisfying the groundwater requirement. In addition, finding the noise limits set forth at 6 NYCRR 360-1.14 (p) were intended to apply to operating noise only, and not to that generated during the construction period, the Commissioner directed that appraisal of the noise levels be limited accordingly. The Town challenges these rulings.

The adjudicable issues having been identified, an adjudicatory hearing ensued, at which the Town argued that the permit application and three requested variances should be denied, and presented evidence to that end. The ALJ recommended that one of the necessary variances, an airport separation variance, and the permit, be denied. However, the Commissioner thereafter found, inter alia, that the construction and operation of the facility would not run afoul of the laws and regulations prohibiting the “taking” of a threatened species (the Northern Harrier) or destruction of its critical habitat, and that the County had met the requirements for obtaining each of the variances; consequently, he directed that each of the variances be granted and that the permit be issued. This CPLR [731]*731article 78 proceeding, in which the Town seeks annulment of the Commissioner’s determination, followed.

The Town’s first contention, that it should have been granted access to the site to conduct soil tests, has merit. Having determined that the permeability of the soil at the site was a critical factor in deciding whether the County had met the criteria for obtaining a variance from the groundwater separation requirement (see, 6 NYCRR 360-1.7 [c] [2] [iii]), and that the Town had presented sufficient evidence to call into question the reliability of the County’s permeability findings, the Commissioner properly found an adjudicable issue existed. He nevertheless held that further testing was “not necessary”, because the results of tests previously performed by the Town, on a parcel of land adjacent to the proposed landfill site, were sufficient to “raise [ ] a substantive and significant issue regarding permeability’, and that re-evaluation of the already existing data at the adjudicatory hearing would “provide [] a forum to examine conflicting information and a safety net to ensure proper engineering design”.

But if the Countys data is not accurate or reliable, repeated evaluation of that data plainly would not be sufficient to ferret out any flaws in the design of the system. Nor can one rationally conclude, merely because the limited, off-site testing carried out by the Town’s expert prior to the issues conference was adequate to raise a question as to the correctness of the Countys permeability assumptions, that further investigation would not be necessary to actually adjudicate that question. Moreover, although the Commissioner indicated that “the permeability information of both [the Town’s expert] and the County should be evaluated in the hearing”, his refusal to allow the Town’s expert to gather any such information from the proposed site effectively prevented the very analysis he directed be undertaken.

Inasmuch as there was every indication that the proposed testing would have produced relevant, probative evidence bearing on an adjudicable issue, and the Commissioner posited no reasonable basis for denying the Town the brief site access it sought for that purpose, his determination cannot be said to have had a sound basis in reason (see, Matter of County of Monroe v Kaladjian, 83 NY2d 185, 189). Accordingly, it must be annulled, along with the decision granting the groundwater separation variance (and the permit, which depended thereon), and the matter remitted for redetermination of the groundwater safety issue after the Town is afforded access to the site to perform testing.

[732]*732The Town’s remaining arguments are unpersuasive. The Commissioner essentially upheld the ALJ’s conclusion that the landfill project would not adversely affect the Northern Harrier and adequately set forth his reasoning in this respect, explaining that “the mitigation plan can be readily implemented * * * and promotes conservation” of this threatened bird species. Having adopted the ALJ’s position that the mitigation efforts would avoid any “taking” of the Harrier, or the destruction or adverse modification of its habitat, the Commissioner not improperly found that this rendered it unnecessary to consider whether the lands in question constituted “critical habitat”. Noting that his decision should not be construed as accepting the ALJ’s position with respect to the definition of that term, he concluded that its proper construction would be better left to future development on a case-by-case basis. Though petitioner suggests otherwise, we find that insofar as the Commissioner disagreed with the ALJ, his decision details sufficiently the basis for his conclusions (see, Matter of Concerned Citizens v Zagata, 231 AD2d 851, 852, lv denied 89 NY2d 814).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Rensselaer v. Duncan
266 A.D.2d 657 (Appellate Division of the Supreme Court of New York, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
246 A.D.2d 729, 667 N.Y.S.2d 505, 1998 N.Y. App. Div. LEXIS 172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-northumberland-v-sterman-nyappdiv-1998.