TOWN OF KINGSTON & Another v. HIGH PINES CORPORATION.

CourtMassachusetts Appeals Court
DecidedJanuary 9, 2025
Docket23-P-1155
StatusUnpublished

This text of TOWN OF KINGSTON & Another v. HIGH PINES CORPORATION. (TOWN OF KINGSTON & Another v. HIGH PINES CORPORATION.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TOWN OF KINGSTON & Another v. HIGH PINES CORPORATION., (Mass. Ct. App. 2025).

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

23-P-1155

TOWN OF KINGSTON & another1

vs.

HIGH PINES CORPORATION.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

High Pines Corporation (High Pines) appeals from a summary

judgment granted in the Superior Court to the town of Kingston

and its planning board (together, town) on the town's breach of

contract claims against High Pines.2 We conclude that the

parties' 2014 settlement agreement was an enforceable contract,

and summary judgment was properly granted in favor of the town.

We likewise discern no abuse of discretion or other error in the

1 Planning Board of Kingston.

2High Pines also challenges the judge's denial of its cross motion for summary judgment on the same claims. As we note below, however, its argument does not meet the requirements of Mass. R. A. P. 16 (a) (9) (A), as appearing in 481 Mass. 1628 (2019). judge's choice of limited specific performance as the remedy for

High Pines's breach. Accordingly, we affirm.

Background. The following facts are not disputed. In

1997, the town granted a special permit to High Pines, allowing

High Pines to develop a subdivision in Kingston. In 2008,

dissatisfied with High Pines's failure to complete the

subdivision's roadways and drainage systems, the town sued High

Pines in the Land Court (Land Court action) seeking injunctive

relief compelling High Pines to complete the infrastructure. In

an attempt to resolve the Land Court action, High Pines and the

town executed a settlement agreement in September 2014. That

agreement provided, in relevant part, the following:

"1. Upon the execution hereof, High Pines, by and through its qualified engineer shall prepare a comprehensive list of infrastructure work that is required to be completed in the . . . subdivision (the 'Work'). Such Work shall relate to completion of roadway and drainage infrastructure in [a given phase of the subdivision]. Such list of Work shall be subject to the peer review and approval by the Planning Board's designated engineer/inspector who may edit or amend such list of Work accordingly. The Planning Board's designed inspector/engineer shall be Webby Engineering or such other peer review engineer as may be approved by High Pines, such approval not to be unreasonably withheld. The Planning Board may utilize such funds from the Security as may be necessary to fund such peer review. High Pines' engineer and the Board's engineer shall cooperate with each other in arriving at a final list of Work which, when complete, shall describe all of the infrastructure Work that forms the basis of the parties' dispute.

"2. All of such Work shall be completed by no later than December 1, 2014, unless a request for extension of such deadline is approved, in writing, by the Kingston Planning Board[.]

2 . . . .

"6. If all the Work or any portion of the Work is not completed by December 1, 2014, the Security [$144,006.52] shall be available and discharged to the Town to complete the Work. . . . In the event that, upon December 14, 2014, the remaining Security is insufficient to complete the remaining Work, the Town may resume the Suit or bring a separate action in Contract in a Massachusetts court of competent jurisdiction to compel the completion of any remaining Work. . . .

"7. Upon the execution of this Agreement, the parties shall submit a Joint Motion to Stay the [Land Court action] so as to permit the Work to be completed in the manner set forth [in the settlement agreement].

"8. This Agreement is a Massachusetts Contract."

High Pines did not prepare the list of work or take any

other steps required under the terms of the agreement, and the

parties did not submit a joint motion to stay the Land Court

action. On the eve of trial, the town did dismiss the action,

however. Shortly thereafter, the town filed this breach of

contract action in the Superior Court.

On the parties' cross motions for summary judgment, the

judge ruled in favor of the town and against High Pines.

Judgment entered, ordering High Pines to fulfill its obligations

"under Paragraph 1 of [the] Agreement to engage in the process

of defining the subdivision work to be completed thereunder."

This appeal followed.

Discussion. 1. Summary judgment on town's contract claim.

a. Standard of review. "We review a grant of summary judgment

3 de novo," Deutsche Bank Nat'l Trust Co. v. Fitchburg Capital,

LLC, 471 Mass. 248, 252-253 (2015), to determine "whether,

viewing the evidence in the light most favorable to the

nonmoving party, all material facts have been established and

the moving party is entitled to judgment as a matter of law"

(citation omitted). Molina v. State Garden, Inc., 88 Mass. App.

Ct. 173, 177 (2015).

b. Settlement agreement as enforceable contract. The

settlement agreement at issue set forth all material terms of

the parties' agreement, and so was enforceable. See Situation

Mgt. Sys., Inc. v. Malouf, Inc., 430 Mass. 875, 878 (2000) ("to

create an enforceable contract, there must be agreement between

the parties on the material terms of that contract, and the

parties must have a present intention to be bound by that

agreement"). Significantly, the agreement described the nature

of the work to be done (completion of roadway and drainage

infrastructure in a defined phase of the subdivision), the

method by which the details of that work would be decided, the

timing for the work's completion, and how the parties could

address disputes about any costs that exceeded the security High

Pines had already posted. This was not "merely an

[unenforceable] agreement to agree." Hunneman Real Estate Corp.

v. Norwood Realty, Inc., 54 Mass. App. Ct. 416, 419 (2002).

4 High Pines contends that the agreement was unenforceable

because it "has no provision to determine the rights or

obligations of the parties if the engineers cannot agree on the

work." That the agreement did not detail how potential good-

faith disagreements between the parties' experts should be

resolved does not alter our conclusion that the agreement was

enforceable, however. See Situation Mgt. Sys., Inc., 430 Mass.

at 878 ("It is not required that all terms of the agreement be

precisely specified, and the presence of undefined or

unspecified terms will not necessarily preclude the formation of

a binding contract"). Contrast Bell v. B.F. Goodrich Co., 359

Mass. 763, 763 (1971) (no contract where defendant agreed to

negotiate "until an agreement was consummated or until both

parties mutually agreed to terminate their negotiations").

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Deposit Ins. Corp. v. Hill
434 N.E.2d 1029 (Massachusetts Appeals Court, 1982)
Commerce Insurance v. Koch
522 N.E.2d 979 (Massachusetts Appeals Court, 1988)
Deutsche Bank National Trust Co. v. Fitchburg Capital, LLC
28 N.E.3d 416 (Massachusetts Supreme Judicial Court, 2015)
Molina v. State Garden, Inc.
37 N.E.3d 39 (Massachusetts Appeals Court, 2015)
Duff v. McKay
52 N.E.3d 203 (Massachusetts Appeals Court, 2016)
Balles v. Babcock Power Inc.
70 N.E.3d 905 (Massachusetts Supreme Judicial Court, 2017)
Bell v. B. F. Goodrich Co.
270 N.E.2d 926 (Massachusetts Supreme Judicial Court, 1971)
Massachusetts Municipal Wholesale Electric Co. v. Town of Danvers
411 Mass. 39 (Massachusetts Supreme Judicial Court, 1991)
Situation Management Systems, Inc. v. Malouf, Inc.
724 N.E.2d 699 (Massachusetts Supreme Judicial Court, 2000)
Dynamic Machine Works, Inc. v. Machine & Electrical Consultants, Inc.
831 N.E.2d 875 (Massachusetts Supreme Judicial Court, 2005)
Hastings Associates, Inc. v. Local 369 Building Fund, Inc.
675 N.E.2d 403 (Massachusetts Appeals Court, 1997)
Hunneman Real Estate Corp. v. Norwood Realty, Inc.
765 N.E.2d 800 (Massachusetts Appeals Court, 2002)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)
MICHAEL A. DAVID v. JONATHAN P. KELLY & another.
100 Mass. App. Ct. 443 (Massachusetts Appeals Court, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
TOWN OF KINGSTON & Another v. HIGH PINES CORPORATION., Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-kingston-another-v-high-pines-corporation-massappct-2025.