Town of Johnston v. Pezza

723 A.2d 278, 1999 R.I. LEXIS 19, 1999 WL 30829
CourtSupreme Court of Rhode Island
DecidedJanuary 21, 1999
Docket96-408-Appeal
StatusPublished
Cited by16 cases

This text of 723 A.2d 278 (Town of Johnston v. Pezza) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Johnston v. Pezza, 723 A.2d 278, 1999 R.I. LEXIS 19, 1999 WL 30829 (R.I. 1999).

Opinion

OPINION

FLANDERS, Justice.

Revoking a building permit issued by his predecessor, a municipal building official decided that a proposed asphalt plant did not mix with applicable town ordinances. A Superior Court trial justice, however, concluded otherwise and found that, in revoking the permit, the new building official did not give the asphalt plant a fair shake. Because the asphalt-plant applicant failed to comply with applicable conditions precedent to obtaining a building permit — including without limitation, failing to submit a proper site plan to the municipality’s planning board — and because the town’s former building official had no authority to waive the applicant’s compliance with these conditions precedent to the issuance of the building permit, we reverse and uphold the successor building official’s revocation of the permit.

In November 1994, defendant, Granite Asphalt Corporation (Granite), applied for a building permit in the town of Johnston (town) to construct an asphalt batch mixing plant. Granite submitted its application to the town’s building official, Anthony Izzo (Izzo). Because the town’s longtime mayor had just suffered an electoral defeat, Izzo’s days as the town’s building official were numbered. Within days of receiving the application, Izzo issued a building permit to Granite. On February 7, 1995, a new building official assumed office and soon determined that the permit’s issuance, as well as the asphalt plant’s ongoing construction, did not comply with the town’s ordinances. Consequently, the town, through its new building official, revoked the permit and ordered Granite to cease and desist from any further plant construction. After Granite ignored this order, the town attempted to enjoin Granite, as well as other affiliated individuals and entities, from proceeding with any further plant construction. Although work at the site was temporarily halted, the Superior Court eventually denied the town’s request for injunctive relief and permitted defendants’ installation of the plant to proceed. Notwithstanding the pendency of the town’s appeal to this Court, Granite completed the construction and the plant is now operational. Nonetheless, because the plant’s owners failed to comply with applicable conditions precedent to the building official’s issuance of the permit, we reverse, enjoin defendants’ continued operation of the plant, and remand this case to the Superior Court so that it may enter a judgment consistent with this opinion.

Facts and Travel

The various individual and corporate defendants, Leonard Pezza, Constance Pezza, -Robert A. Pezza, and certain Pezza-owned companies (Granite Asphalt Corporation, C. Pezza & Son, Inc., and Material Sand and Stone Corporation) (collectively, the Pezzas) owned a large block of property in the town. Bounded by Irons Avenue to the north, the Woonasquatucket River to the east, Sheridan Street to the south, and Endicott Street to the west, the property long had served as the commercial locus of the Pezzas’ excavation and gravel-transportation businesses, as well as their crushing, screening, and separation operations.

*280 In the summer of 1993, Robert A. Pezza (Robert), testifying as the president of Material Sand and Stone Corporation (Material Sand), discussed with his father, Leonard Pezza (Leonard), the possibility of buying a parcel of property that Leonard owned which abutted Irons Avenue (the proposed site). Robert intended to purchase the proposed site in order to erect and operate an asphalt batch mixing plant. To this end, in July 1993, C. Russell Hoffman (Hoffman), an employee of Material Sand, consulted with Izzo, who was then the town’s building official, regarding the feasibility of installing an asphalt plant on the proposed site. At that meeting, Izzo apprised Hoffman that the proposed site was appropriately zoned for the Pezzas’ intended industrial use, but that the applicant first would have to procure approval for the proposed asphalt plant from the Rhode Island Department of Environmental Management (DEM). On January 6, 1994, Robert, on behalf of what would become Granite, 1 applied for the requisite DEM approval. Thereafter, on April 27, 1994, DEM authorized the construction of a “Stansteel, Inc., Model TM 60, 200 TPH portable batch mix plant” at 100 Irons Avenue. According to the testimony of Ronald S. Marcaccio, the DEM official who had handled the application, Granite only enclosed plans for a TM-40 asphalt plant with its application. 2 Nevertheless, DEM’s permit inexplicably approved a “TM 60” plant. 3

After obtaining DEM’s approval, Hoffman returned to Izzo, who instructed him to secure approval of the plans from the Johnston Fire Department Chief, an objective Hoffman accomplished during the first week of May 1994. Hoffman again returned to Izzo in late May or early June of 1994, this time armed with both DEM’s and the fire chiefs approvals. In July 1994, Hoffman, on behalf of Granite, attempted to apply for a town building permit. Because of an intervening tax-arrearage problem, however, Hoffman did not submit any formal application until November 23,1994.

On that date, the day before Thanksgiving, Hoffman conferred with Izzo at the latter’s office “right after lunch.” Hoffman brought with him the DEM approval, a self-prepared site plan, 4 and the plot plan. With Hoffman at his elbow, Izzo proceeded to fill out the building-permit application while obtaining informational input from Hoffman as needed. Hoffman testified that, with respect to the DEM permit, Izzo claimed that “[this permit] covers the world *** that’s all you need.” After Izzo filled out the application, Hoffman tendered to Izzo a $1,670 check payable to the town for a building-permit fee. Thereafter, Hoffman testified, Izzo assured him: “ ‘Leave this with me, leave everything with me, I’ll make this out.’ It’s a long weekend, Friday after Thanksgiving, I don’t know, he says, I’ll have it for you Monday morning.” Notably, Izzo did not submit nor did he require Granite to submit a site plan for the plant to the Johnston Planning Board (board). Instead, on that next Monday, November 28, 1994, Hoffman returned to Izzo’s office, whereupon Izzo issued the building permit to him for a TM-60, 200 TPH asphalt mixing plant at 100 Irons Avenue.

However, notwithstanding the permit’s reference to a TM-60, 200 TPH plant, Granite *281 began installation of a different type of asphalt plant that was three times more expensive than the one described on the permit application. Because Stansteel no longer made the TM-60, 200 TPH type of plant, Granite began to construct a stationary. RM-60 type of plant that could produce up to 20 percent more asphalt per hour than the permitted plant. Moreover, in addition to a larger production capacity, this type of plant was not trailer-mounted like the one that Granite had specified in its permit application. Granite retained another Pezza enterprise, C. Pezza & Son, Inc., to do some of the site-preparation work. This company began to install a twenty-foot-high earthen berm around portions of the surrounding residen-tially zoned area that extended along Endi-cott Street and Irons Avenue. It also erected a concrete retaining wall running parallel to Sheridan Street.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cahoon v. Shelton
647 F.3d 18 (First Circuit, 2011)
Lariviere v. Zoning Board of Review
Superior Court of Rhode Island, 2011
Woodcock v. Little Compton Zoning Bd.
Superior Court of Rhode Island, 2010
Sheehan v. Town of North Smithfield
Superior Court of Rhode Island, 2010
Burchard v. Buhrendorf
Superior Court of Rhode Island, 2009
City of Providence v. Estate of Tarro
Superior Court of Rhode Island, 2008
Martel Investment Group, LLC v. Richmond
Superior Court of Rhode Island, 2008
Town of Cumberland v. Cumberland Plan Bd
Superior Court of Rhode Island, 2006
Kulak v. Zbr, 03-6649 (r.I.super. 2005)
Superior Court of Rhode Island, 2005
Cohen v. Duncan, 2002-599 (2004)
Superior Court of Rhode Island, 2004
Mill Realty Associates v. Crowe
841 A.2d 668 (Supreme Court of Rhode Island, 2004)
Rico Corporation v. Town of Exeter, 95-0361 (2002)
Superior Court of Rhode Island, 2002
Rico Corp. v. Town of Exeter
787 A.2d 1136 (Supreme Court of Rhode Island, 2001)
Beachfront, LLC v. Petros Kyriakides, 00-110 (2000)
Superior Court of Rhode Island, 2000

Cite This Page — Counsel Stack

Bluebook (online)
723 A.2d 278, 1999 R.I. LEXIS 19, 1999 WL 30829, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-johnston-v-pezza-ri-1999.