Town of Holden v. Pineau

573 A.2d 1310, 1990 Me. LEXIS 130
CourtSupreme Judicial Court of Maine
DecidedApril 20, 1990
StatusPublished
Cited by3 cases

This text of 573 A.2d 1310 (Town of Holden v. Pineau) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Holden v. Pineau, 573 A.2d 1310, 1990 Me. LEXIS 130 (Me. 1990).

Opinion

COLLINS, Justice.

This appeal concerns the proper construction of the penalty and attorney fee award sections of a former version of Maine’s “enforcement of land use laws and ordinances” statute, 30 M.R.S.A. § 4966 (Supp. 1987) 1 and the proper interaction between section 4966 and a municipal zoning ordinance sought to be enforced by the Town of Holden against John J. Pineau, the violator of that ordinance, through a section 4966 action. We conclude that the District Court properly interpreted the penalty provisions of section 4966, and had authority to apply the penalties provided by that statute even though those penalties exceeded the maximum penalty authorized by the local ordinance. We further determine that the trial court had authority to award attorney fees under the state statute, even though the local ordinance did not authorize an attorney fee award. We therefore affirm the decision of the Superior Court (Penobscot County, Smith, J.) denying the appeal brought by Pineau from judgment entered against him by the District Court (Bangor, Kravchuk J.). Additionally, we conclude that the Town of Holden is entitled to attorney fees incurred defending the judgment of the District Court against the Pineau’s appeal to both the Superior Court and to this Court.

I.

Appellant John J. Pineau is the president and sole stockholder of Sunspot Broadcasting Company, the licensee of two radio stations in Brewer, Maine. On October 12, 1987, Pineau and Sunspot began construction of a 261 foot commercial radio tower on Pineau’s land in the Town of Holden, which Pineau leases to Sunspot. Pineau lacked a building permit required by the Holden Zoning Ordinance, art. VI, § 2 (1981) to build such a tower. On October 14, 1987, a code enforcement officer notified Pineau that he needed a building permit to erect the tower. The following day the Holden Town Manager ordered Pineau to stop construction. The Town Manager testified that she told Pineau that if construction continued, fines would be levied against him for violating the Town’s zoning ordinance. She testified, “his [Pineau’s] answer was that if fines were to be levied, fines were to be levied.” Pineau did not stop construction as ordered. He completed the tower, without ever obtaining a permit, between October 21 and October 24, 1987.

Pineau then applied twice to the Town’s Planning Board in order to obtain “a special exception and site plan approval.” The usual prerequisites for obtaining a building permit include obtaining a special exemption and site plan approval. The Planning Board rejected each of Pineau’s applications.

In an action collateral to the action presently before this Court, Sunspot appealed the Planning Board’s decision rejecting its application to the Board of Appeals. The Board of Appeals determined that Pineau is not entitled to a building permit, and rejected Sunspot’s appeal. Sunspot next appealed to Superior Court, pursuant to M.R. Civ.P. 80B. The Superior Court also rejected Sunspot’s appeal. Sunspot has recently filed an appeal to this Court, challenging the Board of Appeal’s decision. The existence of Sunspot’s collateral appeal is important to the present appeal because, as described below, the District Court in the present case conditioned a portion of its *1312 judgment upon the outcome of Sunspot’s collateral appeal.

Meanwhile, before Sunspot’s appeal of the Planning Board’s decision to the Board of Appeals, the Town of Holden filed in the District Court the Land Use Citation and Complaint, pursuant to M.R.Civ.P. 80K, giving rise to the present appeal before this Court. The Citation and Complaint charged Pineau with “[bjuilding a radio tower without a permit and refusing] to remove the radio tower after Planning Board’s rejection of the application,” in violation of municipal ordinance art. YI, §§ 2, 5 & 6. The Citation and Complaint sought both a preliminary and permanent injunction, demanded removal of the “violation,” and demanded the assessment of a $2,500 civil penalty under 30 M.R.S.A. § 4966.

After a hearing and an on-site visit, the District Court concluded that Pineau had willfully violated both the ordinance prohibiting construction of the tower without a permit and the stop-work order of October 15, 1987, and ruled in favor of the Town. The court interpreted section 4966 as authorizing the court to levy penalties and awards as provided for in the statute, without regard to the limitations on penalties and absence of comparable awards in the local ordinance. Therefore, the court ordered Pineau to remove the tower, levied a $2,500 fine against Pineau, and awarded $3,331 in attorney fees to the Town of Holden. The District Court’s order for removal of the tower was conditioned upon Pineau (Sunspot) not prevailing in the 80B collateral appeal to the Superior Court from the Board of Appeal’s decision. As noted above, Sunspot’s appeal to the Superior Court was unsuccessful but Sunspot has now appealed to the Law Court. The tower has not yet been removed.

Pineau appealed the instant District Court’s judgment to the Superior Court. The Superior Court determined that the District Court’s findings of fact were substantiated by the record, and that the District Court had applied the law without an abuse of its discretion. Therefore, the Superior Court affirmed the judgment.

II.

We determine first that the District Court did not abuse its discretion by ordering removal of the tower in the event that Pineau is unsuccessful in his 80B collateral appeal challenging the Board of Appeal’s determination that Pineau is not entitled to a building permit. We find no merit to Pineau’s argument that the District Court misconstrued the meaning of the penalty provisions of section 4966(3) or misapplied these provisions to this case. Section 4966(3) provided the following:

3. Civil Penalties. The following provisions shall apply to violations of the laws and ordinances set forth in this section, and all monetary penalties shall be civil penalties.
A. The minimum penalty for starting construction or undertaking a land use activity without a required permit shall be $100, and the maximum penalty shall be $2,500.
B. The minimum penalty for a specific violation shall be $100, and the maximum penalty shall be $2,500.
C. The violator may be ordered to correct or abate the violations. Where the court finds that the violation was wilful, the violator shall be ordered to correct or abate the violation unless the abatement or correction will:
(1) Result in a threat or hazard to public health or safety;
(2) Result in substantial environmental damage; or
(3) Result in a substantial injustice.

The District Court found as a factual matter that Pineau was an experienced businessman, and that his decision to erect the radio tower without the required permit after he had been notified by the Town that such a permit was necessary and actually ordered to cease construction constituted a “willful violation” of the Town’s ordinance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Town of Freeport v. Brickyard Cove Associates
594 A.2d 556 (Supreme Judicial Court of Maine, 1991)
City of Ellsworth v. McAlpine
590 A.2d 545 (Supreme Judicial Court of Maine, 1991)
City of Rockland v. Winchenbaugh
583 A.2d 702 (Supreme Judicial Court of Maine, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
573 A.2d 1310, 1990 Me. LEXIS 130, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-holden-v-pineau-me-1990.