TOWN OF HOLDEN v. DEPARTMENT OF CONSERVATION AND RECREATION & Another.

Massachusetts Appeals Court·Decided August 18, 2025·No. 23-P-0794·Unpublished

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

23-P-794

TOWN OF HOLDEN

vs.

DEPARTMENT OF CONSERVATION AND RECREATION & another. 1

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

In May 2013, the town of Holden (Holden) commenced this

action against the defendants, the Department of Conservation

and Recreation (DCR) and the city of Worcester (Worcester),

claiming the defendants had overcharged it for the

transportation of Holden's sewage through Worcester to its final

destination at a wastewater treatment facility in Millbury

(treatment facility). Following an eight-day trial in the

summer of 2022, the jury found against Holden on its breach of

contract claim against DCR, but in favor of Holden on its unjust

enrichment claim against Worcester. The trial judge adopted the

jury's findings of fact and their special verdict on the unjust enrichment claim. 2 See Delaney v. Chief of Police of Wareham, 27 Mass. App. Ct. 398, 401 (1989). The judge subsequently denied Worcester's motion for judgment notwithstanding the verdict (judgment n.o.v.) on the unjust enrichment claim and Holden's cross motion to set aside the verdict on the contract claim. These cross appeals from the final judgment followed. We affirm.

Background. We recite the facts the jury could have found, as supplemented by the judge's findings of fact, reserving certain details for later discussion. See Tocci v. Tocci, 490 Mass. 1, 3 (2022). In the late 1980s, the Wachusett Reservoir and its watershed -- the public water supply for over 2.5 million people -- was at risk from failing septic systems. In

1993, the Massachusetts Water Resources Authority (MWRA), DCR, 3 and the Massachusetts Department of Environmental Protection (DEP) entered into a consent order requiring the MWRA and DCR to implement a watershed protection plan for the area. The DEP imposed a series of deadlines on DCR and the MWRA for the planning and construction of treatment facilities that would bring the watershed area into compliance with State and Federal environmental laws. The facilities plan developed by MWRA and DCR called for the expansion of sewer systems in three towns located in the watershed area (Holden, West Boylston, and Rutland), the transportation of the towns' sewage to the treatment facility through neighboring Worcester, and improvements to Worcester's sewer system to accommodate the increased flow of wastewater through it. The State made significant contributions to the project.

Around 1996 negotiations over a master sewer use agreement between the three towns, Worcester, and the DCR began but broke down; at that point, DCR, aided by the Massachusetts Executive Office of Environmental Affairs, began negotiating solely with Worcester for a sewer use agreement. During the negotiations,

Worcester expressly rejected Holden's transport rate proposal that included Worcester's actual total flow in the calculus, deeming it "grossly inadequate" to what Worcester was seeking in total revenue for the use of its sewer system.

In December 1999, upon DCR's completion of the sewer expansion project in Holden, DCR and Holden entered into a contract transferring to Holden the care, custody, and control of the new sewer components (1999 Holden-DCR contract). Pursuant to the fourth paragraph of that contract, Holden agreed "to pay directly to [DCR] all proportionate applicable transport costs (as finally determined and agreed to by the Town of Holden) for the transport of sewage . . . to the [treatment facility], including the costs of sewage transport through the City of Worcester." But for this "critical" provision requiring Holden's approval of the transport rate, Holden would not have signed the agreement. Worcester was not a party to the 1999 Holden-DCR agreement.

By the spring of 2000, "time was running out" to bring the watershed area into compliance with Federal and State law, and DCR "was anxious to turn the valve on" allowing sewage to flow into Worcester. In May 2000, Worcester and DCR entered into a "Sewer Use Agreement . . . For Intermunicipal Sewer Use" (May 2000 SUA). The agreement referenced the 1993 consent order, the public interest in expanding the public sewer system, and the

financial assistance from the State. Pursuant to that contract, Worcester agreed to "receive, transport and convey [Holden's] wastewater . . . from points of connections . . . to the Treatment Plant." The agreement established a rate calculation methodology (May 2000 SUA formula) for determining the amount owed to Worcester for transporting the towns' sewage through it. The May 2000 SUA formula allowed Worcester to (1) pass along significant and unproportionate costs to Holden, including stormwater management and capital costs that had nothing to do with Holden's use of the Worcester sewer system, and (2) undercount its actual billable flow (increasing Holden's share of the costs). 4 For example, the judge found, and Worcester does not dispute, that Worcester's costs for its sewer system, consisting of forty-five percent stormwater pipes and fifty-five percent sanitary sewer pipes, are managed together; and that although Holden does not use any of Worcester's stormwater system, Worcester includes the costs for it in the fees charged to Holden. DCR had voiced objections to the fairness of the

formula but ultimately signed the agreement. 5 Both before and after the execution of the May 2000 SUA, Holden objected to DCR and to Worcester about the unfair methodology. 6 Holden declined to sign the May 2000 SUA or to execute a similar sewer use agreement with DCR or Worcester incorporating the May 2000 SUA formula.

In the spring of 2000, Holden made the necessary connections, went online, and began sending its sewage through Worcester to the treatment facility. 7 Commencing at that time,

5 The chief negotiator for DCR noted that the formula "produces a higher rate of return to the city than the actual cost to the city for the operation and maintenance of its sewer system . . . [and] represents a significant cost sharing with the city by the towns without any apparent proportional benefit to the towns." Worcester recognized that implementation of the May 2000 SUA would increase the city's revenue at a "minimal increase in cost" to Worcester's ratepayers; and that the May 2000 SUA formula, including "[a]voidance of [the] total flow methodology," would produce a "distinct economic advantage to Worcester." Worcester rejected DCR's alternative proposed methodologies that DCR explained would produce "fair and equitable compensation."

6 The judge found that Worcester was aware that Holden objected to the amount of the fees and paid them under protest.

7 DCR considered and rejected a number of possible solutions that did not require Holden to transport its sewage through Worcester, including a water filtration plant that would have cost the State approximately one billion dollars to construct. As the trial judge found, the expansion of sewage treatment and the transport of Holden's wastewater was determined to be the most cost effective alternative for the protection of the watershed area.

Free access — add to your briefcase to read the full text and ask questions with AI

TOWN OF HOLDEN v. DEPARTMENT OF CONSERVATION AND RECREATION & Another., (Mass. Ct. App. 2025).

TOWN OF HOLDEN v. DEPARTMENT OF CONSERVATION AND RECREATION & Another. (TOWN OF HOLDEN v. DEPARTMENT OF CONSERVATION AND RECREATION & Another.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Carson v. Brockton Sewerage Commission
182 U.S. 398 (Supreme Court, 1901)
County Commissioners v. J. Roland Dashiell & Sons, Inc.
747 A.2d 600 (Court of Appeals of Maryland, 2000)
Delaney v. Chief of Police of Wareham
539 N.E.2d 65 (Massachusetts Appeals Court, 1989)
Salamon v. Terra
477 N.E.2d 1029 (Massachusetts Supreme Judicial Court, 1985)
Dobos v. Driscoll
537 N.E.2d 558 (Massachusetts Supreme Judicial Court, 1989)
Biltcliffe v. CitiMortgage, Inc.
772 F.3d 925 (First Circuit, 2014)
Katz, Nannis & Solomon, P.C. v. Levine
46 N.E.3d 541 (Massachusetts Supreme Judicial Court, 2016)
Carson v. Sewerage Commissioners of Brockton
48 L.R.A. 277 (Massachusetts Supreme Judicial Court, 1900)
West Broadway Task Force v. Boston Housing Authority
608 N.E.2d 713 (Massachusetts Supreme Judicial Court, 1993)
Somerset Savings Bank v. Chicago Title Insurance
649 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1995)
Beacon Hill Civic Ass'n v. Ristorante Toscano, Inc.
662 N.E.2d 1015 (Massachusetts Supreme Judicial Court, 1996)
Merola v. Exergen Corp.
668 N.E.2d 351 (Massachusetts Supreme Judicial Court, 1996)
A.Z. v. B.Z.
725 N.E.2d 1051 (Massachusetts Supreme Judicial Court, 2000)
Anastos v. Sable
819 N.E.2d 587 (Massachusetts Supreme Judicial Court, 2004)
A.W. Chesterton Co. v. Massachusetts Insurers Insolvency Fund
838 N.E.2d 1237 (Massachusetts Supreme Judicial Court, 2005)
Metropolitan Life Insurance v. Cotter
984 N.E.2d 835 (Massachusetts Supreme Judicial Court, 2013)
Santagate v. Tower
833 N.E.2d 171 (Massachusetts Appeals Court, 2005)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)
Zabin v. Picciotto
896 N.E.2d 937 (Massachusetts Appeals Court, 2008)