Town of Gila Bend v. Walled Lake Door Company

490 P.2d 551, 107 Ariz. 545, 1971 Ariz. LEXIS 363
CourtArizona Supreme Court
DecidedNovember 12, 1971
Docket10435
StatusPublished
Cited by25 cases

This text of 490 P.2d 551 (Town of Gila Bend v. Walled Lake Door Company) is published on Counsel Stack Legal Research, covering Arizona Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Gila Bend v. Walled Lake Door Company, 490 P.2d 551, 107 Ariz. 545, 1971 Ariz. LEXIS 363 (Ark. 1971).

Opinion

UDALL, Justice:

On August 20, 1968, Walled Lake Door Company (hereinafter the "Company”j, a Michigan corporation qualified to do business in Arizona, filed suit against the Town of Gila Bend (hereinafter the “Town”), a body politic organized under the laws of this State, a number of individuals who were members of the Town Council of Gila Bend, and one A. II. Stout, dba Stout Water Works (hereinafter “Stout”), in the Superior Court for *547 Maricopa County. The complaint asserted that the Town breached a contract with the Company to construct and install a ten inch water main from the Southern Pacific Railroad Company (hereinafter “Southern Pacific”) w^fer tank in Gila Bend for approximately six thousand feet to the Company’s plant in Gila Bend. Trial before the Court, sitting without a jury, resulted in judgment for the individual defendants but against the Town for costs of suit, money damages in the sum of $24,381.00, and specific performance of the contract. Said judgment ordered the Town to:

“ * * * forthwith commence construction and installation of a ten inch water main beginning at the Southern Pacific Tanks in Gila Bend, Arizona, and proceeding a distance of approximately 6,-000 feet to the Plaintiff’s facility in Gila Bend, and the defendant Town is further ordered to complete said construction within a reasonable time; and it is further ordered that the approval of the construction plans and specifications be obtained from the defendant A. H. Stout, dba Stout Water Works, provided, however, that the said A. H. Stout, dba Stout Water Works, shall not unreasonably withhold his approval of said construction plans and specifications”.

From this judgment the Town appealed. The facts necessary for a determination of this matter are as follows: For a number of years prior to eruption of this dispute, the Company has owned and operated a processing or cut stock plant in Gila Bend. In April of 1966, the Company’s Gila Bend plant was substantially destroyed by fire, resulting in approximately $335,000.00 damage. Reconstruction of the plant was begun in March or April of 1967. At that time, Dale C. Campbell, vice-president of the Company, flew in from Michigan to attempt to “negotiate with the City for the providing of water or, in failing to do that, remain here to find a new location for the plant.” (T.R. 90). Mr. Campbell met with the Town, through its Mayor and Town Council, and demanded that the Town provide the Company with assurance that adequate fire protection would be provided for the Company. He informed the Town that the Company could not absorb the high premiums it was forced to pay for fire insurance, resulting from the lack of an adequate water supply for fire protection, and that the Company would be forced to cease reconstruction of its plant and relocate elsewhere if negotiations failed.

In May or June of 1967, the Company entered into an agreement with the Town, whereby the Town agreed to construct and install a ten inch water main from the Southern Pacific water tanks, a distance of approximately 6,000 feet, to the Company’s plant. In return, the Company agreed to rebuild the destroyed portion of its plant, replace equipment ruined by the fire, install additional equipment, and contribute $8,000.00 towards the purchase of á “pressure booster pump” to insure continued pressure even in the event of a power failure. To date, the Company has fulfilled the duties and obligations imposed upon it under the terms of the contract. 1 The Company has expended approximately $300,000.00 in rebuilding the fire-ravaged portions of its plant, it has installed new and additional equipment, it has continued its operations in Gila Bend and, as a direct result of the Town’s failure to install the water main, has incurred many thousands of dollars extra expense in the form of increased fire insurance premiums. The Town, on the other hand, has not carried out its part of the bargain. At the time *548 the contract was entered into, no funds had been budgeted for any such purpose; although approximately one month later, when the succeeding year’s budget was drawn up, $7,500.00 was budgeted for beginning construction of the water main.

In furtherance of the above-mentioned agreement the Mayor called a special meeting of the Town Council on May 19, 1967, at which council meeting Resolution No. 37 was “passed, adopted and approved” by unanimous vote. Resolution No. 37 stated that because the increased cost of fire insurance had made it impractical for the Company to continue its operations in Gila Bend, the Town would “proceed without unnecessary delay with the installation of a 6000 foot, 10 inch water main to run from the base of the water tank at the water company to the 4 inch hydrant at the Walled Lake Door Company”. It further resolved that plans and specifications for said water main be secured immediately, ordered an immediate review of available sources of financing said project and declared an emergency to exist.

Resolution No. 38, approved and adopted by unanimous vote on May 24, 1967, ordered that a special election be held on June 16, 1967, for the purpose of approving the Town’s contract. The election was held on June 16, at which time the electorate, by majority vote, authorized the Town to proceed with construction of the water line.

Subsequently, a proposed agreement between Stout and the Town was drawn up and' submitted by the Town to the Arizona Corporation Commission for approval. This agreement was approved and notice thereof was mailed to the parties on November 2, 1967. Said agreement was to allow installation and connection of the water main to Stout’s existing water lines and established the future ownership, operation and control thereof. The agreement was, however, entered into with the understanding that it was to be subject to Stout’s “right to review all plans for installation of said lines and to approve or deny such plans within reason.” (A.R. 87.) To date, Stout has approved neither of the two plans submitted.

On August 20, 1968, negotiations for construction and installation of the water main having reached an impasse, the Company filed suit. Trial before the court, sitting without a jury, resulted in judgment for the Company. From this judgment the Town appealed. The issues presented on appeal are as follows :

I. The lower court exceeded its jurisdiction when it ordered specific performance with respect to Stout Water Works, a public service corporation.

In sum and substance, the Town argues that only the Arizona Corporation Commission has the authority to supervise and regulate a public service corporation and the Superior Court, therefore, had no jurisdiction to substitute itself for the Commission in ordering Mr. Stout not to “unreasonably withhold his approval” of construction plans and specifications submitted to him. While we agree that only the Corporation Commission has the authority to supervise and regulate the activities of a public service corporation, we fail to see how the court’s action, in ordering Stout not to unreasonably withhold his approval of a project which the Corporation Commission had already approved, 2 *549 constituted an illegal attempt to regulate the public service corporation.

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phoenix Motor v. Rajabian
Court of Appeals of Arizona, 2025
Mark Gilmore v. Kate Gallego
552 P.3d 1084 (Arizona Supreme Court, 2024)
Whitt v. Meza
545 P.3d 931 (Court of Appeals of Arizona, 2024)
Darcie Schires v. Cathy Carlat
480 P.3d 639 (Arizona Supreme Court, 2021)
Stuart v. Scottsdale
Court of Appeals of Arizona, 2020
Schires v. Carlat
Court of Appeals of Arizona, 2020
Turley v. Beus
Court of Appeals of Arizona, 2017
Compassionate v. adhs/nelson
Court of Appeals of Arizona, 2015
Brewer v. State
341 P.3d 1107 (Alaska Supreme Court, 2014)
Turken v. Gordon
224 P.3d 158 (Arizona Supreme Court, 2010)
Turken v. Gordon
207 P.3d 709 (Court of Appeals of Arizona, 2009)
Copper Hills Enterprises, Ltd. v. Arizona Department of Revenue
153 P.3d 407 (Court of Appeals of Arizona, 2007)
State v. Heinze
993 P.2d 1090 (Court of Appeals of Arizona, 1999)
Leaf Co. v. Montgomery County
520 A.2d 732 (Court of Special Appeals of Maryland, 1987)
Kromko v. Arizona Board of Regents
718 P.2d 478 (Arizona Supreme Court, 1986)
Marriott Corp. v. Industrial Com'n of Arizona
708 P.2d 1307 (Arizona Supreme Court, 1985)
Elview Construction Co. v. North Scott Community School District
373 N.W.2d 138 (Supreme Court of Iowa, 1985)
Wistuber v. Paradise Valley Unified School District
687 P.2d 354 (Arizona Supreme Court, 1984)
Associated Grocers v. Industrial Commission
616 P.2d 87 (Court of Appeals of Arizona, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
490 P.2d 551, 107 Ariz. 545, 1971 Ariz. LEXIS 363, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-gila-bend-v-walled-lake-door-company-ariz-1971.