Town of Forest v. Pub. Serv. Comm'n of Wis.

2019 WI App 8, 926 N.W.2d 510, 385 Wis. 2d 848
CourtCourt of Appeals of Wisconsin
DecidedJanuary 3, 2019
DocketAppeal No. 2018AP367
StatusPublished

This text of 2019 WI App 8 (Town of Forest v. Pub. Serv. Comm'n of Wis.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Forest v. Pub. Serv. Comm'n of Wis., 2019 WI App 8, 926 N.W.2d 510, 385 Wis. 2d 848 (Wis. Ct. App. 2019).

Opinion

PER CURIAM.

¶1 The Town of Forest ("the Town") appeals an order denying its motion to hold the Public Service Commission of Wisconsin ("the PSC") in contempt of court. The Town also appeals an order dismissing its petition for judicial review of the PSC's decision granting a certificate of public convenience and necessity to Highland Wind Farm, LLC, ("Highland") for the construction of an industrial wind energy facility. We conclude the circuit court properly exercised its discretion by denying the Town's contempt motion. We further conclude the court properly dismissed the Town's petition for judicial review on the ground that it was barred by the doctrine of claim preclusion. We therefore affirm.

BACKGROUND

¶2 On December 19, 2011, Highland applied to the PSC for a certificate of public convenience and necessity permitting Highland to construct a 102.5 megawatt wind energy facility on land located, in part, within the Town. An administrative law judge subsequently granted the Town's request to intervene in the administrative proceedings pertaining to Highland's application. On March 15, 2013, the PSC issued a final decision denying Highland's application. Based on computer modeling submitted by Highland, the PSC determined that Highland's proposed facility would exceed the nighttime noise limit of 45 dBA1 set forth in WIS. ADMIN. CODE § PSC 128.14(3)(a) (Dec. 2012),2 for between twenty and forty-five nearby, nonparticipating residences.

¶3 Thereafter, Highland successfully petitioned the PSC to reopen its March 15, 2013 decision. In the reopened proceeding, Highland proposed implementing a compliance plan that would include "curtailment of certain turbines by operating them in reduced noise operation modes in order to meet applicable noise limits." Highland asserted its use of curtailment would allow the project to meet the applicable noise limits in WIS. ADMIN. CODE § PSC 128.14(3) and was, in fact, "the only way to meet the nighttime [noise] standard." In response, the Town argued curtailment "may only be used as a mitigation tool" once a project is operational and may not be relied upon in the planning phase as a way to ensure initial compliance with the applicable noise limits.

¶4 On October 25, 2013, the PSC issued a "Final Decision on Reopening," which approved Highland's application for a certificate of public convenience and necessity. The PSC found, based on Highland's sound level modeling and proposed curtailment plan, that Highland's project would meet the noise limits in WIS. ADMIN. CODE § PSC 128.14(3), including the nighttime noise limit of 45 dBA. Although the PSC appeared to agree with Highland that WIS. ADMIN. CODE ch. PSC 128 permitted the use of curtailment in the planning phase of the project, the PSC ultimately stated it was "not necessary" to address that issue because the PSC was only required to "consider" the provisions of ch. PSC 128 when evaluating Highland's application. The PSC then concluded curtailment was an "appropriate planning strategy without regard to the rules" in ch. PSC 128.

¶5 The PSC's final decision on reopening imposed two conditions on Highland's project that are relevant to this appeal. First, the PSC held that "a showing of compliance by Highland at or above 95 percent of the time" would be "adequate for the [PSC] to consider the proposed project in compliance with applicable noise limits." Second, the PSC "accept[ed] Highland's voluntary agreement to obligate itself to a lower limit of 40 dBA" during nighttime hours for six residences occupied by individuals with sensitivities to sound. However, the PSC found it was "not necessary" to extend the 40 dBA nighttime noise limit to "additional affected residences identified in the reopened proceeding."

¶6 Commissioner Ellen Nowak dissented from the PSC's decision. She concluded WIS. ADMIN. CODE ch. PSC 128 did not contemplate "the type of curtailment plan proposed by Highland as a method for permanent compliance with sound limits." She further concluded that Highland's proposed use of curtailment would "undermine[ ] the sound limits that were discussed at length and vetted by the Wind Siting Council."3

¶7 The Town petitioned for judicial review of the PSC's final decision on reopening. Among other things, the Town argued that: (1) the PSC made material errors of law and fact when it held that Highland's project needed to comply with the applicable noise limitations only 95% of the time; (2) the PSC's finding that there was no basis to apply a 40 dBA nighttime noise limit to additional sensitive residences was not supported by substantial evidence; and (3) substantial evidence did not support the PSC's finding that Highland's curtailment plan was sufficient to ensure compliance with the applicable noise limits.

¶8 The circuit court, the Honorable Edward F. Vlack III presiding, ultimately issued a 115-page decision on the Town's petition for judicial review. The parties refer to that decision as Town of Forest I . As relevant here, the court held that the record did not contain sufficient evidence to support the PSC's determination that Highland needed to comply with the applicable noise limits only 95% of the time. The court therefore set aside that portion of the PSC's decision adopting a 95% compliance standard and remanded the matter to the PSC "for the purpose [of] conducting a further hearing on the issue of adopting a percentage compliance standard."

¶9 The circuit court also concluded that the PSC's decision to apply a lower nighttime noise limit to only six sensitive residences was not supported by substantial evidence. The court therefore remanded the proceeding to the PSC with directions to explain, based on the existing record, why it had applied the lower nighttime noise limit to only six residences and not to eleven additional residences. The court further held:

If, based upon the record herein, the [PSC] is not able to state why the six residences were selected and the other eleven were not, then the matter is reopened solely for the purpose of allowing the parties to state why other sensitive residences, already identified, should be considered and the [PSC] can then decide if others, already identified, should be included with the original six residences.

¶10 Finally, the circuit court held that there was sufficient evidence in the record to support the PSC's finding that Highland's curtailment plan would ensure compliance with the applicable noise limits. The court therefore affirmed that portion of the PSC's decision approving Highland's use of a curtailment plan.

¶11 No party appealed the circuit court's decision in Town of Forest I . On March 15, 2016, the PSC issued an order reopening the proceeding "for the limited purpose" of addressing the two issues remanded by the circuit court. The PSC stated it was exercising its authority to reopen the matter under WIS. STAT. § 196.39(1) (2015-16),4 which states the PSC may "at any time, upon notice to the public utility and after opportunity to be heard, ... reopen any case following the issuance of an order in the case, for any reason."

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Menard, Inc. v. Liteway Lighting Products
2005 WI 98 (Wisconsin Supreme Court, 2005)
In RE MARRIAGE OF BENN v. Benn
602 N.W.2d 65 (Court of Appeals of Wisconsin, 1999)
Kruckenberg v. Harvey
2005 WI 43 (Wisconsin Supreme Court, 2005)
Jensen v. City of Santa Rosa
233 Cal. Rptr. 3d 278 (California Court of Appeals, 5th District, 2018)
Wisconsin Public Service Corp. v. Arby Construction, Inc.
2012 WI 87 (Wisconsin Supreme Court, 2012)
Society Insurance v. Bodart
2012 WI App 75 (Court of Appeals of Wisconsin, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
2019 WI App 8, 926 N.W.2d 510, 385 Wis. 2d 848, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-forest-v-pub-serv-commn-of-wis-wisctapp-2019.