Town of East Montpelier v. Wheelock

70 Vt. 391
CourtSupreme Court of Vermont
DecidedJanuary 15, 1898
StatusPublished
Cited by1 cases

This text of 70 Vt. 391 (Town of East Montpelier v. Wheelock) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of East Montpelier v. Wheelock, 70 Vt. 391 (Vt. 1898).

Opinion

Start, J.

It is alleged in the bill, that the complainant town is one of the corporate towns of this state, and as such owes certain duties to the public, among which is the keeping in repair and maintenance of highways and bridges within the limits of said town; that there is a certain bridge across Winooski river in said town, now known as the Fowler bridge, which it is the duty of the complainant to maintain and keep in repair; that the defendant Wheelock is the owner of a water privilege on said river and has a dam [392]*392across it at the village of East Montpelier, which, when the dam is full, obstructs the water so that it sets back under the Fowler bridge aforesaid to the depth of seven or eight feet; that the other defendants lease power of him and use water from said dam; that the abutments under said Fowler bridge are out of repair, so much so that they must be built over, and the complainant has been, and now is, repairing the same; that the soil under the abutments is a quicksand so that it is necessary to drive piles and cut the same off below low-water mark, upon which to commence to lay the stone abutments which are to support said bridge; that it is not now definitely known which rights are superior in case of conflict, those of the complainant or those of the defendants, but the complainant avers that it has superior right and that it is the duty of said J. S. Wheelock, his lessees and assigns, on proper notice from the complainant, to let the water out of the dam for a reasonable time to enable the complainant to rebuild the abutments of said bridge; that the complainant gave the said J. S. Wheelock notice to draw the water from his said dam, as it was about to commence work on the abutments of said bridge, and thereupon, the complainant’s agent and the said Wheelock did let the water out of said dam and the complainant commenced work, placing a temporary support under said bridge near its west end, building a coffer-dam and excavating preparatory to driving piles for the abutment at the west end; that the defendants, Wallace Clark and the Eureka Granite Company, are using water from said dam and claim an interest in said water-power, as the complainant is informed and believes; that the complainant is informed and believes that the said J. S. Wheelock closed up his dam and shut the water back on the 2nd day of August, 1896; that this was done without the knowledge or consent of the complainant or its agents in control of said work, and the water was, in fact, shut off so that it set back, broke in said coffer-dam and flooded the place where said abutment was [393]*393being built, stopping the work and doing great damage; that the complainant was proceeding with the repairs with all possible dispatch, employing all the men that could be used on the work to advantage; that the complainant has caused a hole to be opened in said dam so that the water is now being drawn out, and is ready to commence on the same as soon as the water is drawn, but it is informed and believes that the said J. S. Wheelock will again close up the hole in the dam and flood the work so that it will be impossible to proceed with the repairs, unless restrained by order of court. Upon the filing oí the bill, an injunction was issued, restraining the defendants from hindering or interfering with the repairing of the bridge, or from preventing the water from flowing through the dam, or from causing the water to rise in the pond so as to interfere with the work of repairing the bridge.

The master finds, that one of the selectmen of the complainant town had an interview with defendant Wheelock, in which the purpose of the complainant to repair the bridge was disclosed, and requested Wheelock to draw the water from the pond for that purpose, at such times as might be deemed necessary, saying that he expected the complainant would have to pay. what was right; that Wheelock consented to empty the pond whenever required, accompanying the promise by the statement, that, for so doing, he only wanted what was right; that, on the 31st day of July, the complainant was ready to have the water drawn that it might construct a truss under the bridge, and sent men to help take out the water-gates, which was done; that, when the truss was constructed, the defendants were allowed to retain the water in the dam until further notice; that, later, the defendants were requested to draw the water from the pond, which was done; that, on August 10th, defendant Wheelock, learning that the complainant had not worked on Sunday, the 9th, instructed his men to so far close the dam as to get a fall of eight feet upon the wheels; that this [394]*394could be done, as the water was then flowing, without increasing the depth of the water at the bridge; that, on Wednesday, the 12th of August, soon after midnight, the water in the stream suddenly rose, overflowed the walls of the pit where the pile-driver was stationed and filled the same, and the complainant’s officers, on going to defendant Wheelock’s mill, found the water flowing over the top of the dam, and that although it did not rain in that vicinity, it was afterwards discovered that there had been what was called a cloud-burst in the town of Calais, which had caused the sudden rising of the stream. The master finds, that it was not the intention of defendant Wheelock to raise the water in the stream so as to impede the work at the bridge; that, in the adjustment of the waste-gates, they had been so placed that, with only the water ordinarily flowing in said stream, it would not have risen so as to have yielded more than eight feet head upon the wheels, and would not have affected the work of the complainant at said bridge; and that, immediately after the circumstance last stated, the complainant brought its bill in equity and procured an injunction. Prom these findings, it is clear, that the cloudburst in Calais caused the pond to fill and the water to set back upon the complainant’s work ; that the cloud-burst was an unusual and unexpected occurrence; that the parties did not know of it until after the work was flooded and the complainant had brought its bill and enjoined the defend ants from obstructing the natural flow of the water; that the defendants acted in good faith, believing that if there was an increase in the flow of water which would require a further opening of their gates, they would" observe it in season to do so; that they had no intention of impeding the complainant’s work; and that, under these circumstances, there was no occasion for enjoining the defendants from obstructing the flow of the water, and the complainant’s bill must be dismissed.

The defendants insist that they are entitled to injunction [395]*395damages for the loss of the use of their mill during the time the complainant was making repairs upon the bridge. The master finds that the time selected by the complainant for doing the work was as favorable as could have been selected for its speedy and successful accomplishment; that it was at a season of the year when the defendants were less damaged than they would have been at any other time; that the plans adopted by the complainant for carrying on the work, considering the obstacles to be overcome, were feasible and reasonable; and that there was no unreasonable delay on the part of the complainant in pushing the work to completion, and the water was not drawn longer than was reasonably necessary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walker Motors, Inc. v. City of Montpelier
Vermont Superior Court, 2013

Cite This Page — Counsel Stack

Bluebook (online)
70 Vt. 391, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-east-montpelier-v-wheelock-vt-1898.