Town of Calais v. Noordsij

CourtVermont Superior Court
DecidedFebruary 9, 2009
Docket142-06-06 Vtec
StatusPublished

This text of Town of Calais v. Noordsij (Town of Calais v. Noordsij) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Calais v. Noordsij, (Vt. Ct. App. 2009).

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

} Town of Calais, } Plaintiff, } } v. } Docket No. 142-6-06 Vtec } Barbara Noordsij, } Defendant. } }

Decision and Order on Motion for Reconsideration and to Alter

The Town of Calais brought an enforcement action against Defendant Barbara

Noordsij, asserting violations of the conditions of her zoning permit for the construction

of a barn. The Town is represented by Joseph S. McLean, Esq.; Defendant is

represented by David J. Blythe, Esq.

Defendant had not appealed the Notice of Violation to the Development Review

Board, and consequently was precluded from contesting the violation, either directly or

indirectly. After this and other issues were resolved by summary judgment, an

evidentiary hearing was held on the matter of an appropriate penalty, before Merideth

Wright, Environmental Judge. The Town sought a penalty in the amount of $39,136.92

in its post-hearing memoranda. The Court issued a decision on the merits imposing a

penalty for the violation of $24,695, or $43.63 per day over 566 days of violation.

Defendant has moved for the Court to reconsider its decision and alter the amount of

the penalty.

Relief pursuant to a motion to reconsider is “an extraordinary remedy that

should be used sparingly.” In re Bouldin Camp – Noble Road, No. 278-11-06 Vtec, slip

op. at 1 (Vt. Envtl. Ct. Sept. 13, 2007) (Wright, J.) (quoting 11 Wright, Miller & Kane,

1 Federal Practice and Procedure: Civil 2d § 2810.0). A motion to reconsider should not

be used to repeat arguments that have been raised and rejected by the court in the prior

decision, id. at 1, nor should such a motion be used present evidence that could have

been presented prior to judgment. Rubin v. Sterling Enters., 164 Vt. 582, 589 (1996); In

re South Village Communities, LLC, No. 74-4-05 Vtec, slip op. at 2 (Vt. Envtl. Ct. Sept.

14, 2006) (Durkin, J.) (citing 11 Wright, Miller & Kane, supra).

The limited functions of a motion to reconsider are “’to correct manifest errors of

law or fact’ on which the decision was based, to allow the moving party to present

newly discovered or previously unavailable evidence, to prevent manifest injustice, or

to respond to an intervening change in the controlling law.” In re Vanishing Brook

Subdivision, No. 223-10-07 Vtec, slip op. at 4 (Vt. Envtl. Ct. July 10, 2008) (Wright, J.)

(quoting 11 Wright, Miller & Kane, supra). The Court has reviewed its notes made

during the trial, in connection with these motions, as the parties did not provide a

transcript.

Defendant has requested that the Court reconsider its comment on the evidence

that the $5,000 estimate provided by Defendant’s contractor at trial as the avoided cost

of storage of the partially-completed prefabricated building appeared to be low.1 First,

it is important to recognize that the Court’s actual finding regarding the avoided cost of

storage as of the time of the Notice of Violation was based on the $5,000 figure (plus

interest for the duration of the violation), despite the contested comment, as no other

evidence was presented by either party regarding the cost of storage. Town of Calais v.

Noordsij, No. 142-6-06 Vtec, slip op. at 7 (Vt. Envtl. Ct. Aug. 29, 2008) (Wright, J.).

1 The decision stated that the contractor’s $5,000 “estimate appears to the Court to be a low estimate, as it has to cover eighteen or nineteen months rental of a storage location protected from the elements, as well as the transportation of the materials in both directions, and the labor of any dismantling of the portion of the structure that had been completed as of that time.” Town of Calais v. Noordsij, No. 142-6-06 Vtec, slip op. at 5 (Vt. Envtl. Ct. Aug. 29, 2008) (Wright, J.). 2 The comment was supported by the evidence at trial, as Defendant’s contractor

referred to his estimate of $5,000 as what he had “guessed2 off the top of [his] head,” in

response to a question regarding whether the steel frame could have been disassembled

by unbolting it and taking it down. Several questions earlier, Defendant’s contractor

had testified that an alternative to continuing to construct the building after the Notice

of Violation had issued would have been to have “dug it all out and trucked it to a

warehouse somewhere, preferably heated.” The $5,000 estimate therefore covered

dismantling the partially constructed frame and may have included the time involved

in trucking it to a warehouse, but it did not include the warehouse rental costs and, as

the contractor testified on cross-examination, it did not include the equipment necessary

to load the prefabricated pieces onto a truck and unload it at the warehouse.

It is also important to note that the $5,000 estimate did not represent the cost of

installing the building in the correct, permitted location to begin with, nor the cost of

installing it in the as-built location not then yet permitted. That is, it was not the cost of

curing the violation so as to end up with the proposed building in its permitted

location. Rather, it was the cost of putting the building in storage while a permit was

applied for to place the building in the new nonconforming location.

Moreover, Defendant’s own evidence also reflected that the cost of the work and

materials necessary to have installed a slab foundation and to have moved the

prefabricated structure in its originally-permitted location was $16,870, as shown on

Defendant’s own Exhibit O. While Defendant presented this evidence to argue that it

was not practical to move the structure to its originally-permitted location, it is that

figure that was the true avoided cost of compliance as of the date of the Notice of

Violation. However, the Court did not measure this component of the penalty by this

2 All quotations are approximate as they are taken from the Court’s notes, not from a transcript. On cross-examination, the contractor also testified to the effect that he had “no confidence in that number.” 3 larger amount, even though it was from Defendant’s own evidence, because the DRB

eventually did grant the permit in the as-built location.

Therefore the Court looked to the Town’s cost of enforcement as a fairer measure

of the appropriate penalty, without adding to it Defendant’s large avoided cost of

compliance. The Court determined that, for the purposes of deterrence, it was not

necessary to impose both the avoided cost of compliance and the Town’s enforcement

costs as the Town had requested, but that essentially the two could run concurrently,

with the avoided cost of compliance being subsumed within the enforcement cost

amount.

The Court calculated the period of violation as 566 days, commencing seven days

after the Notice of Violation and continuing until the permit was issued by the DRB

authorizing the barn to remain in the location in which it was constructed. This method

of calculating the violation period is supported by the language of 24 V.S.A. § 4451(a),

which indicates that the violation period commences seven days after the Notice of

Violation issues,3 and states that “[e]ach day that a violation is continued shall

constitute a separate offense.” Defendant’s barn remained in an unpermitted location

for 566 days after the Notice of Violation’s seven-day grace period, and therefore the

period of violation was correctly calculated by the Court to be 566 days. The fact that

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of St. Albans v. Hayford
2008 VT 36 (Supreme Court of Vermont, 2008)
Rubin v. Sterling Enterprises, Inc.
674 A.2d 782 (Supreme Court of Vermont, 1996)
Town of Hinesburg v. Dunkling
711 A.2d 1163 (Supreme Court of Vermont, 1998)
Town of Sherburne v. Carpenter
582 A.2d 145 (Supreme Court of Vermont, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
Town of Calais v. Noordsij, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-calais-v-noordsij-vtsuperct-2009.