Town of Calais v. Noordsij

CourtVermont Superior Court
DecidedAugust 28, 2008
Docket142-06-06 Vtec
StatusPublished

This text of Town of Calais v. Noordsij (Town of Calais v. Noordsij) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Calais v. Noordsij, (Vt. Ct. App. 2008).

Opinion

STATE OF VERMONT

ENVIRONMENTAL COURT

} Town of Calais, } Plaintiff, } } v. } Docket No. 142-6-06 Vtec } Barbara Noordsij, } Defendant. } }

Decision and Order

The Town of Calais brought an enforcement action against Defendant Barbara

Noordsij, asserting violations of the conditions of her zoning permit for the construction of

a barn. The Town is represented by Joseph McLean, Esq.; Defendant is represented by

David Blythe, Esq.

After certain issues were resolved by summary judgment, an evidentiary hearing

was held in this matter before Merideth Wright, Environmental Judge. The parties were

given the opportunity to submit written memoranda and requests for findings. Upon

consideration of the evidence and of the written memoranda and requests for findings filed

by the parties, the Court finds and concludes as follows.

Defendant owns a 6.7-acre parcel of property at 8598 County Road in the Town of

Calais, in the Rural Residential zoning district. Prior to the construction at issue in the

present enforcement case, the property was improved with a single-family house and with

a detached garage, itself having an attached shed.

In August of 2005, Defendant applied for a zoning permit to construct a 20' x 30'

1 prefabricated metal structure for use as a horse barn, oriented diagonally to the road. The

building was designed with its vertical posts supported on concrete piers, and otherwise to

have a dirt floor, and to be furnished with sliding barn doors. The permit application

stated that the “building is engineered by Rockford Steel Building Systems” and that it was

“to be built by local builder.”

The application included a sketch plan showing the nearest corner of the barn to be

48 feet from the centerline of County Road. The Court does not find it to be credible that

the version of the document showing the number “48” as having been written over to read

“40” was the document submitted as the application and later approved by the zoning

administrator. Defendant’s signature on the application certified that “the information

submitted in this application regarding the property is true, accurate and complete” and

that she understood “that any permit will be issued in reliance on the above

representations and will be automatically void if any are untrue or incorrect.”

The then-newly-appointed Zoning Administrator issued the zoning permit

authorizing the construction of the barn as shown on the application, with a front setback

of 48 feet from the centerline of County Road.

As discussed in the summary judgment decision, the setback actually required for

Defendant’s property is 65 feet, because it is located along the County Road south of the

Maple Corner village zoning district. Land Use Regulations, Table 2.2(E). Generally within

the Town of Calais the required front setback is 40 feet,1 except along the rights-of-way of

1 Defendant asserts that she believed that the required setback was 40 feet. This belief was not reasonable and does not rise to an estoppel, as discussed in the summary judgment decision in the present case. At best, Defendant’s belief could only have resulted from an inquiry she may have made by telephone to the Town Clerk, who had formerly served also for thirty-five years as the Zoning Administrator, without specifying the location of the property as being on the County Road, because at all times material to these events, the Town Clerk believed that the required setback on the County Road was 100 feet, and was

2 three specific roadways, including along County Road (State Aid Highway #1) in the

location of Defendant=s property. Regulations, Table 2.2(E). Prior to the 2005 amended

regulations the setback along the County Road had been 100 feet from the centerline.

In mid-September of 2005, Defendant obtained an estimate of $16,763.62 from

Shelter Construction, a local building firm, for the pre-engineered steel building. The

estimate included $10,363.62 for the building=s materials, including Vermont sales tax, plus

$500 for the concrete for the footings. The estimate included $3,600 as labor costs for the

footings and erection of the building, and $300 for rental of a forklift. The estimate also

included $2,000 for leveling the area and digging five-foot-deep holes for the concrete

footings below the leveled grade. This element of the estimate noted that “this estimate is

based on working with existing soils” and specifically provided that “cost[s] for the

removal of ledge, debris, excess soil, or providing additional soils are not included.”

Defendant and the contractor had discussed the issue of ledge outcroppings, and

Defendant knew that it would be an additional cost to deal with ledge.

The prefabricated building materials were delivered to the property between

November 29 and December 1, 2005. The warranty on the building contained a condition

that the building materials must be kept dry. The excavation for the footings began on

November 30, and the concrete footings were poured on December 1, 2005. The contractor

stacked the steel framing members, beams, wall sheathing, boxes of trim, doors and

hardware on the ground on so-called bunkers or pallets, covered by tarps. The contractor

unaware that it had been reduced to 65 feet. If the Town Clerk had been asked by telephone about setbacks on the County Road, she would have responded ‘100 feet’; if she had been asked about setbacks generally she might have responded ’40 feet.’ Even if such a conversation occurred, the Court finds it not to be reasonable for an applicant to change an approved 48 foot setback on an issued permit and to proceed to build a project at a reduced setback based on such an unattributed and unrecorded conversation, without bringing the permit in to the Zoning Administrator for an amendment.

3 began the framing work around December 19, 2005.

Before the contractor started work, Defendant had staked out the barn for where she

thought it should be. Even that original staked location was closer than the permitted 48

feet from the centerline of the County Road. Before the footings were poured Defendant

and the contractor agreed to move the location of the footings a few feet from their staked

position in order to avoid ledge and avoid the need for blasting. The building’s footings

were in fact located so that the nearest corner was set back only 41½ feet from the

centerline of the County Road, in violation of the zoning permit. If Defendant had shown

the contractor her zoning permit, or had staked out the building in compliance with the

zoning permit, this enforcement action would not have been necessary.

The avoided cost of blasting at that time, prior to construction, was at least $2,500.

After the Zoning Administrator noticed construction equipment on Defendant’s

property in mid-December, she checked her records to determine whether a zoning permit

had been issued for the property. She realized that she had made a mistake in the permit;

that is, that the setback should have been 65 feet rather than the 48 feet that she had

approved in the permit. Prior rulings in this matter have established that Defendant was

entitled therefore to the benefit of the 48-foot-setback due to the error of the Zoning

Administrator.

The Zoning Administrator notified Defendant orally on December 20, 2005 that

construction appeared to be in violation of the permit and that continuing with

construction might be unwise.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of St. Albans v. Hayford
2008 VT 36 (Supreme Court of Vermont, 2008)
Agency of Natural Resources v. Deso
2003 VT 36 (Supreme Court of Vermont, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Town of Calais v. Noordsij, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-calais-v-noordsij-vtsuperct-2008.