Town of Berlin v. Nobel Insurance

758 A.2d 436, 60 Conn. App. 56, 2000 Conn. App. LEXIS 446
CourtConnecticut Appellate Court
DecidedSeptember 19, 2000
DocketAC 19444
StatusPublished
Cited by4 cases

This text of 758 A.2d 436 (Town of Berlin v. Nobel Insurance) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Berlin v. Nobel Insurance, 758 A.2d 436, 60 Conn. App. 56, 2000 Conn. App. LEXIS 446 (Colo. Ct. App. 2000).

Opinion

Opinion

HENNESSY, J.

The plaintiff, the town of Berlin, appeals from the judgment of the trial court denying its application for a permanent injunction to prohibit the defendant, the Nobel Insurance Company,1 from [58]*58proceeding to arbitration in connection with a dispute concerning a contract to build a running track at Berlin High School. The plaintiff claims that the court abused its discretion by (1) determining that an arbitration clause was contained in the parties’ “takeover agreement,” under which the defendant agreed to complete the project, which had been left unfinished by the contractor, and (2) denying the application for a permanent injunction. We affirm the judgment of the trial court.

The following facts are relevant to this appeal. The defendant, an insurance and bonding company, served as the surety for and guaranteed the performance of the Lomaglio Construction Company (Lomaglio), a contractor hired to construct the track at the school. Lomaglio, as the bond principal, provided performance bonds. In 1993, the defendant had posted the bonds, which named the plaintiff as the obligee. After Lomaglio failed to complete the work, the plaintiff, in October, 1993, terminated Lomaglio’s contract and looked to the defendant to complete the work. The defendant arranged for completion of the work. The plaintiff and the defendant then entered into a written takeover agreement in November, 1993, in which the defendant agreed to perform “all work and all other obligations of the contract [between the plaintiff and Lomaglio] called for under the said contract [not] presently completed or fulfilled, pursuant to the terms of the existing contract documents.” The takeover agreement incorporated by reference the original contract between the plaintiff and Lomaglio.

Lomaglio brought an action against the plaintiff for breach of contract while the defendant completed the work under the contract. Lomaglio never pursued its lawsuit, which was'subsequently dismissed for failure to prosecute with due diligence. The defendant eventually completed its obligations under the takeover [59]*59agreement in accordance with the terms of the agreement.

The defendant, in June, 1997, commenced arbitration proceedings against the plaintiff before the American Arbitration Association, seeking damages for the plaintiffs alleged wrongful termination of Lomaglio, and its alleged failure to compensate Lomaglio and the defendant for additional work done under the contract. Thereafter, the plaintiff commenced an action against the defendant, seeking a judgment declaring that the disputes with the defendant were not subject to arbitration and a temporary injunction staying the arbitration proceedings pending the outcome of the declaratory judgment action. The court concluded that the takeover agreement contains an arbitration clause because it incorporated the contract between the plaintiff and Lomaglio. The court also denied the plaintiffs application for a permanent injunction. The plaintiff now appeals from that decision.

As a preliminary matter, the plaintiff argues to this court that the defendant has waived its right to arbitration because it is bound by the consequences of Lomag-lio’s having filed an action against the plaintiff. We disagree.

Although it is true that arbitration is a favored procedure in this jurisdiction, it also is true that an arbitration clause can be waived by the parties or by the one entitled to its benefit. Waterbury Teachers Assn. v. Waterbury, 164 Conn. 426, 435, 324 A.2d 267 (1973). One may waive a right to arbitration by going to trial without insisting on the arbitration condition. Batter Building Materials Co. v. Kirschner, 142 Conn. 1, 11, 110 A.2d 464 (1954). The plaintiff contends that when Lomaglio brought the breach of contract action against the plaintiff, it waived its right under the contract to arbitration, and that the defendant now is bound by that waiver [60]*60because it incorporated into its takeover agreement by reference the wording of the contract between the plaintiff and Lomaglio.

The takeover agreement between the plaintiff and the defendant required the defendant to “take over and perform, or procure the performance of, all work . . . pursuant to the terms of the existing contract documents.” The defendant incorporated by reference the wording of the contract between the plaintiff and Lomaglio. The defendant did not, by doing so, become bound by the consequences of the fact that Lomaglio initiated a civil action against the plaintiff. The takeover agreement between the plaintiff and the defendant is a separate and distinct contract, and there were no actions taken by the defendant that would warrant our concluding that it waived its right to request that the dispute be placed before an arbitrator.

I

The plaintiff claims that the court improperly found that the takeover agreement incorporates the arbitration clause from the contract between the plaintiff and Lomaglio. The plaintiff claims that the takeover agreement with the defendant does not contain a written arbitration clause consistent with the requirement of General Statutes § 52-408.2 That statute requires that an agreement to settle a dispute by arbitration must be [61]*61in writing and executed by the parties. The plaintiff points out that the takeover agreement does not specifically mention an arbitration clause, and that the document in which the arbitration clause is specifically mentioned was not executed by the plaintiff and the defendant, but instead by the plaintiff and Lomaglio.

“[ W]here there is definitive contract language, the determination of what the parties intended by their contractual commitments is a question of law.” (Internal quotation marks omitted.) Gateway Co. v. DiNoia, 232 Conn. 223, 229, 654 A.2d 342 (1995). Because a question of law is presented, review of the trial court’s ruling is plenary, and this court must determine whether the trial court’s conclusions are legally and logically correct, and whether they find support in the facts appearing in the record. Id.

It is undisputed that article 4.5.1 of the contract between the plaintiff and Lomaglio contains a written agreement to arbitrate. The contract provides: “Any controversy or claim arising out of or related to the contract, or the breach thereof, shall be settled by arbitration in accordance with the construction industry arbitration rules of the American Arbitration Association, and judgment upon the award rendered by the arbitrator or arbitrators may be entered in any court having jurisdiction thereof . . . .’’It also is undisputed that the takeover agreement entered into by the plaintiff and the defendant contains language incorporating the contract between the plaintiff and Lomaglio. The takeover agreement provides: “The surety undertakes and agrees to take over and perform, or procure the performance of, all work and all other obligations of the contract called for under the said contract [not] presently completed or fulfilled, pursuant to the terms of the existing contract documents.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Developers Sur. & Indem. Co. v. Carothers Constr., Inc.
320 F. Supp. 3d 386 (D. Connecticut, 2018)
Detar v. Coast Venture XXVX, Inc.
811 A.2d 273 (Connecticut Appellate Court, 2002)
Wyatt Energy v. Motiva Enter., No. Cv 02 0467090s (Sep. 27, 2002)
2002 Conn. Super. Ct. 12303 (Connecticut Superior Court, 2002)
State Medical Society v. Oxford Hlth. P., No. X01cv0165664s (Dec. 13, 2001) Ct Page 16582
2001 Conn. Super. Ct. 16581 (Connecticut Superior Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
758 A.2d 436, 60 Conn. App. 56, 2000 Conn. App. LEXIS 446, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-berlin-v-nobel-insurance-connappct-2000.