Total Building Maintenance, Inc. v. J & J Contractors/Raines Brothers, a Joint Venture, J & J Contractors, Inc., Raines Brothers, Inc., St. Paul Fire & Marine Insurance Co., and Fidelity & Deposit Co. of Maryland

CourtCourt of Appeals of Tennessee
DecidedMarch 13, 2009
DocketE2008-00678-COA-R3-CV
StatusPublished

This text of Total Building Maintenance, Inc. v. J & J Contractors/Raines Brothers, a Joint Venture, J & J Contractors, Inc., Raines Brothers, Inc., St. Paul Fire & Marine Insurance Co., and Fidelity & Deposit Co. of Maryland (Total Building Maintenance, Inc. v. J & J Contractors/Raines Brothers, a Joint Venture, J & J Contractors, Inc., Raines Brothers, Inc., St. Paul Fire & Marine Insurance Co., and Fidelity & Deposit Co. of Maryland) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Total Building Maintenance, Inc. v. J & J Contractors/Raines Brothers, a Joint Venture, J & J Contractors, Inc., Raines Brothers, Inc., St. Paul Fire & Marine Insurance Co., and Fidelity & Deposit Co. of Maryland, (Tenn. Ct. App. 2009).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE November 6, 2008 Session

TOTAL BUILDING MAINTENANCE, INC., v. J & J CONTRACTORS/RAINES BROTHERS, a Joint Venture, J & J CONTRACTORS, IN., RAINES BROTHERS, INC., ST. PAUL FIRE & MARINE INSURANCE COMPANY, and FIDELITY & DEPOSIT CO. OF MARYLAND

Direct Appeal from the Chancery Court for Hamilton County No. 06-0227 Hon. W. Frank Brown, III, Chancellor

No. E2008-00678-COA-R3-CV - FILED MARCH 13, 2009

In this action plaintiff sued for money owed under its subcontract with the defendant contractor. The defendants’ contractor denied liability, raised as affirmative defenses, waiver/estoppel, unclean hands and breach of contract, filed a counter-claim alleging that plaintiff failed to complete its work in a timely and proper manner and permitted the roof to be harmed by others during the construction and generally failed to cooperate. Following an evidentiary hearing, the Trial Judge determined that both parties had breached the contract, that plaintiff was guilty of unclean hands, denied both parties any recovery and dismissed the case. On appeal, we affirm.

Tenn. R. App. P.3 Appeal as of Right; Judgment of the Chancery Court Affirmed.

HERSCHEL PICKENS FRANKS, P.J., delivered the opinion of the Court, in which CHARLES D. SUSANO , JR., J., and D. MICHAEL SWINEY , J., joined.

Timothy M. Gibbons, Chattanooga, Tennessee, for appellant.

Randy Wilson and Robert F. Parsley, Chattanooga, Tennessee, for appellees.

OPINION Plaintiff in this action alleged that it was owed money for work performed on the new headquarters for the Electric Power Board in Chattanooga. Further, that defendants J&J Contractors and Raines Brothers, Inc., (hereinafter “contractor”) formed a joint venture to act as general contractor for the construction project, and that unnamed defendants were the performance bond sureties.

Plaintiff averred that it entered into two contracts with contractor to work as a roofing subcontractor on this project, and attached copies of the subcontract agreements and alleged that it had a number of disputes with contractor regarding the fact that contractor sought to hold plaintiff liable for damage caused by other parties to the work performed by plaintiff.

Plaintiff charged that contractor also tried to increase the scope of the work, and refused to execute change orders for the additional work. Plaintiff asserted that it had completed all of the work, but had not been fully paid, and was owed $193,000.00, because contractor had breached the contract, interfered with the contract and breached covenants of good faith and fair dealing.

Plaintiff later amended its Complaint to add St. Paul Fire & Marine Insurance Company and Fidelity & Deposit Company of Maryland, as sureties on the bonds.

Defendants answered, denying any liability, pleading waiver/estoppel, unclean hands, breach of contract, comparative fault, laches, insufficiency of process, etc. Defendants also filed a Counterclaim asserting that plaintiff had failed to complete its work in a timely and proper manner, failed to insure that the roof was inspected by a representative of the manufacturer to obtain a warranty, permitted the roof to be harmed by others during construction, and withheld necessary lien releases. Defendants attached an Interim Agreement which the parties had executed.

Plaintiff filed a Reply to Counterclaim, denying it had breached any of its responsibilities, and the case went to trial before the Trial Judge on November 27-30, 2007.

The Trial Court filed a Memorandum Opinion, and found that plaintiff was the roofing subcontractor on the new EPB office building in downtown Chattanooga, and that the defendant joint venture was the general contractor on the project. The Court found that the parties and the architect all agreed the roof installation began too early, and that the contractor was in charge of scheduling the work, and did ask plaintiff to install the roof earlier than normal, but that the contractor contended that plaintiff was supposed to protect its work. The Court said that other parties were still working in the roof area, and that the roof was damaged by water, and part of it had to be replaced. The Court found that the roofing manufacturer, Garland Company, would not warranty the roof until a second cap sheet was installed over the initial one, and that plaintiff claimed defendants owed them for this installation. The Court found that plaintiff also claimed to be owed for all the repair work to the roof.

-2- The Court found that Marvin Cornelison, president of Raines Brothers, testified that everyone had responsibility for damaging the roof, and the company that caused the most damage was Staley Marble & Granite, Inc., the subcontractor. The Court found the contractor withheld $32,328.00 from Staley’s final payment to cover roof damages, and that the contractor explained in a letter to Staley that this was 20% of the amount invoiced for repairs by plaintiff ($161,638.00), because the contractor assessed that Staley was responsible for 20% of the roof damage. The Court found there was no evidence that any other sub was back-charged for roof damage, and there were pictures in evidence of other subs working on the roof, which could have caused damage.

The Court found that the evidence was clear that plaintiff had to share in the blame for part of the roof damage, as there was proof that it had failed to properly install an ice and water shield in one area, and water damage resulted, and there was also proof of improperly installed flashing, as well as damage caused by improper precautions by plaintiff’s employees, and that plaintiff was largely responsible for the repair work needed on the roof.

The Court found the contractor agreed to pay plaintiff for certain repair work, and asked plaintiff to identify its costs associated with the same, by providing invoices, time cards, etc., but that plaintiff never complied with this request until late in the discovery process, and did not provide a breakdown regarding which invoices were related to which work. The Court held that regarding the second cap sheet, plaintiff provided a quote for the work of $86,779.00, but the contractor got a quote from another for $47,000.00 for the same work. The Court found that plaintiff was directed to do the work pursuant to the subcontract, and to keep detailed cost records on the work, but plaintiff failed in this regard. The Court said the plaintiff was repeatedly asked by the contractor to itemize its expenses related to the second cap sheet, and the contractor referenced the contract requirements (found in the Supplementary Conditions) regarding financial information needed to consider a change order. The Court held that plaintiff never provided actual cost information, although it did provide a couple of estimates.

The Court observed that the plaintiff’s credibility was damaged by the changing nature of its position regarding the actual costs associated with the second cap sheet, and that plaintiff’s invoices appeared to be “padded”, e.g., the repair associated with one balcony roof was billed to the contractor three different times.

The Court observed that plaintiff’s claim was primarily based upon the testimony of Mr. Whitmore, and his credibility was damaged in several ways, and set forth examples.

The Court determined that it would deny recovery to plaintiff because Whitmore admitted that plaintiff received formal, written change orders for some extra work, and that it was paid for that work; plaintiff did not receive change orders for the disputed repair work nor the second cap sheet, and should not have performed the work without change orders.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Castelli v. Lien
910 S.W.2d 420 (Court of Appeals of Tennessee, 1995)
Hogue v. Kroger Company
373 S.W.2d 714 (Tennessee Supreme Court, 1963)
Bingham v. Dyersburg Fabrics Co., Inc.
567 S.W.2d 169 (Tennessee Supreme Court, 1978)
Allied Materials & Equipment Co. v. United States
569 F.2d 562 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
Total Building Maintenance, Inc. v. J & J Contractors/Raines Brothers, a Joint Venture, J & J Contractors, Inc., Raines Brothers, Inc., St. Paul Fire & Marine Insurance Co., and Fidelity & Deposit Co. of Maryland, Counsel Stack Legal Research, https://law.counselstack.com/opinion/total-building-maintenance-inc-v-j-j-contractorsraines-brothers-a-tennctapp-2009.