Filed 6/8/16 Topline Supply v. Superior Court CA4/2
NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.
IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
FOURTH APPELLATE DISTRICT
DIVISION TWO
TOPLINE SUPPLY, INC.,
Petitioner, E063391
v. (Super.Ct.No. CIVDS1302091)
THE SUPERIOR COURT OF OPINION SAN BERNARDINO COUNTY,
Respondent;
PMB SB 399-401 EAST HIGHLAND, LLC, a Delaware Limited Liability Company et al.,
Real Parties in Interest.
ORIGINAL PROCEEDINGS; petition for writ of mandate. Bryan Foster, Judge.
Petition is granted.
Marrone, Robinson, Frederick & Foster, J. Alan Frederick and Jennifer E. Traylor,
for Petitioner.
No appearance for Respondent.
1 Kuluva, Armijo & Garcia, and Lori D. Serota, for Real Parties in Interest.
Petitioner Topline Supply, Inc. (hereinafter Topline), defendant below, seeks
review by way of mandamus of the trial court’s order denying its motion for summary
judgment. We find the “accepted work” doctrine applicable and that it bars the cross-
complaint of real parties in interest. Accordingly, we will grant the petition.
I
STATEMENT OF THE CASE
The underlying action is a premises liability/slip and fall case brought by plaintiff
Connie Rogers against real parties in interest PMB SB 399-401 East Highland, LLC, and
PMB Real Estate Services, LLC (hereinafter PMB or real parties). Topline was not
named as a defendant, but PMB filed a cross-complaint for indemnity and related relief,
as to which cross-complaint Topline was added in place of “Roe 1.”
Topline moved for summary judgment on the basis of the “accepted work”
doctrine and also argued that any claim was barred by the four-year statute of limitations
set out in Code of Civil Procedure section 337.1.
The evidence presented by Topline tended to show that in 2005, Topline
contracted with PMB to provide certain renovation services on the subject premises,
including the installation of tile on a handicapped access ramp which is the subject of
plaintiff’s complaint. This contract included a provision relating to final payment, which
2 provided that “the Architect1 will inspect the Work. When the Architect finds the Work
acceptable and the Contract fully performed, the Architect will promptly issue a final
Certificate for Payment.” Topline’s declarant stated that Topline finished the work and
was fully paid, and that PMB had never contacted Topline with any complaints or
requests for repairs.
PMB did not respond to the motion, but the trial court nevertheless denied it
because it felt that the “accepted work” doctrine did not free a contractor from liability if
the hirer had been sued by a third party. The court also ruled that Topline had failed to
show that the owner had accepted the work2 and that its statute of limitations defense
failed because it had failed to properly plead the defense.3
This petition followed. We initially believed that the “accepted work” defense had
merit, and we also assumed that because PMB had failed to respond to the motion for
summary judgment, it had probably implicitly conceded that its action against Topline
must fail on some basis. We asked PMB for an informal response (see Palma v. U.S.
1 The parties’ contract incorporated a form contract created by the American Institute of Architects and captioned “General Conditions of the Contract for Construction of a Small Project.” The parties are described as “Owner” and “Architect.” PMB is listed as “Owner” and the space for “Architect” has been left blank. It is apparent that “Architect,” in the text of the document, must be construed to mean Topline, the contractor.
2PMB was apparently a property manager for St. Bernardine Medical Center. However, PMB was specifically described as the “Owner” in the contract documents. It seems beyond dispute that PMB was either the owner or the owner’s agent.
3 Topline’s answer to the cross-complaint included defenses based on Code of Civil Procedure sections 339 and 337, but not the relevant statute, section 337.1.
3 Industrial Fasteners, Inc. (1984) 36 Cal.3d 171, 178), believing that to be a mere
formality.
However, PMB did file a response in this court, which led to a partial derailment
of the case into a dispute over whether PMB should even be permitted to raise legal
arguments. PMB’s excuse, as set out in its response in this court, was that (1) upon
receiving the motion, counsel contacted a colleague for assistance, and asked that
attorney to prepare opposition and to appear at the hearing. Counsel overlooked the
colleague’s communication declining to take on the matter. “Coincidentally,” another
member of the firm was on court call at the time of the hearing on Topline’s motion, but
merely noted that the trial court denied the motion and therefore saw no need to
intervene.4 For the same reason primary counsel saw no reason to ask the court for the
opportunity to file a tardy response. (See Code Civ. Proc., § 473.)
To dispose of this issue first, we agree with PMB that we can, and should,
consider its argument on the merits. Whatever the merits of PMB’s excuses, in fact it
is correct that it could not have sought relief under Code of Civil Procedure section 473
even if it had wanted to, as there was no “judgment, dismissal, order, or other proceeding
taken against him or her . . . .” (Code Civ. Proc., § 473, italics added.) If the trial court
had granted Topline’s motion, we agree that PMB most probably would have been
required to submit its excuses to the trial court for consideration under section 473. But
4Topline’s attorney opened the hearing by noting that there was no opposition. Why this did not spur associate counsel to break in is not clear.
4 as it is, PMB had no ruling to challenge below, and it has not defaulted before this court
in these proceedings. There is the further consideration that if PMB’s arguments have
merit, we would be loath to order the trial court to enter an erroneous judgment.
Accordingly, we proceed to the merits.
II
DISCUSSION
A.
As we noted above, Topline raised the statute of limitations as a defense, but did
not specify the correct statute. We cannot say that the trial court erred in this strict
application of the rules, which is supported by recent authority. (Martin v. Van Bergen
(2012) 209 Cal.App.4th 84, 91.) More fundamentally, a claim for indemnity “ ‘does not
accrue for statute of limitations purposes when the original accident occurs, but instead
accrues at the time the tort defendant pays a judgment or settlement as to which he is
entitled to indemnity.’ ” (Valley Circle Estates v. VTN Consolidated, Inc. (1983) 33
Cal.3d 604, 611, quoted in Valley Crest Landscape Development, Inc. v. Mission Pools of
Escondido, Inc. (2015) 238 Cal.App.4th 468, 481 (Valley Crest).)5 Hence, the trial
court’s ruling on this point was correct.6
5 Valley Crest also involved an attempt to use Code of Civil Procedure section 337.1’s limitation period against the party seeking indemnification.
6 At oral argument, Topline relied on Wagner v.
Free access — add to your briefcase to read the full text and ask questions with AI
Filed 6/8/16 Topline Supply v. Superior Court CA4/2
NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.
IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
FOURTH APPELLATE DISTRICT
DIVISION TWO
TOPLINE SUPPLY, INC.,
Petitioner, E063391
v. (Super.Ct.No. CIVDS1302091)
THE SUPERIOR COURT OF OPINION SAN BERNARDINO COUNTY,
Respondent;
PMB SB 399-401 EAST HIGHLAND, LLC, a Delaware Limited Liability Company et al.,
Real Parties in Interest.
ORIGINAL PROCEEDINGS; petition for writ of mandate. Bryan Foster, Judge.
Petition is granted.
Marrone, Robinson, Frederick & Foster, J. Alan Frederick and Jennifer E. Traylor,
for Petitioner.
No appearance for Respondent.
1 Kuluva, Armijo & Garcia, and Lori D. Serota, for Real Parties in Interest.
Petitioner Topline Supply, Inc. (hereinafter Topline), defendant below, seeks
review by way of mandamus of the trial court’s order denying its motion for summary
judgment. We find the “accepted work” doctrine applicable and that it bars the cross-
complaint of real parties in interest. Accordingly, we will grant the petition.
I
STATEMENT OF THE CASE
The underlying action is a premises liability/slip and fall case brought by plaintiff
Connie Rogers against real parties in interest PMB SB 399-401 East Highland, LLC, and
PMB Real Estate Services, LLC (hereinafter PMB or real parties). Topline was not
named as a defendant, but PMB filed a cross-complaint for indemnity and related relief,
as to which cross-complaint Topline was added in place of “Roe 1.”
Topline moved for summary judgment on the basis of the “accepted work”
doctrine and also argued that any claim was barred by the four-year statute of limitations
set out in Code of Civil Procedure section 337.1.
The evidence presented by Topline tended to show that in 2005, Topline
contracted with PMB to provide certain renovation services on the subject premises,
including the installation of tile on a handicapped access ramp which is the subject of
plaintiff’s complaint. This contract included a provision relating to final payment, which
2 provided that “the Architect1 will inspect the Work. When the Architect finds the Work
acceptable and the Contract fully performed, the Architect will promptly issue a final
Certificate for Payment.” Topline’s declarant stated that Topline finished the work and
was fully paid, and that PMB had never contacted Topline with any complaints or
requests for repairs.
PMB did not respond to the motion, but the trial court nevertheless denied it
because it felt that the “accepted work” doctrine did not free a contractor from liability if
the hirer had been sued by a third party. The court also ruled that Topline had failed to
show that the owner had accepted the work2 and that its statute of limitations defense
failed because it had failed to properly plead the defense.3
This petition followed. We initially believed that the “accepted work” defense had
merit, and we also assumed that because PMB had failed to respond to the motion for
summary judgment, it had probably implicitly conceded that its action against Topline
must fail on some basis. We asked PMB for an informal response (see Palma v. U.S.
1 The parties’ contract incorporated a form contract created by the American Institute of Architects and captioned “General Conditions of the Contract for Construction of a Small Project.” The parties are described as “Owner” and “Architect.” PMB is listed as “Owner” and the space for “Architect” has been left blank. It is apparent that “Architect,” in the text of the document, must be construed to mean Topline, the contractor.
2PMB was apparently a property manager for St. Bernardine Medical Center. However, PMB was specifically described as the “Owner” in the contract documents. It seems beyond dispute that PMB was either the owner or the owner’s agent.
3 Topline’s answer to the cross-complaint included defenses based on Code of Civil Procedure sections 339 and 337, but not the relevant statute, section 337.1.
3 Industrial Fasteners, Inc. (1984) 36 Cal.3d 171, 178), believing that to be a mere
formality.
However, PMB did file a response in this court, which led to a partial derailment
of the case into a dispute over whether PMB should even be permitted to raise legal
arguments. PMB’s excuse, as set out in its response in this court, was that (1) upon
receiving the motion, counsel contacted a colleague for assistance, and asked that
attorney to prepare opposition and to appear at the hearing. Counsel overlooked the
colleague’s communication declining to take on the matter. “Coincidentally,” another
member of the firm was on court call at the time of the hearing on Topline’s motion, but
merely noted that the trial court denied the motion and therefore saw no need to
intervene.4 For the same reason primary counsel saw no reason to ask the court for the
opportunity to file a tardy response. (See Code Civ. Proc., § 473.)
To dispose of this issue first, we agree with PMB that we can, and should,
consider its argument on the merits. Whatever the merits of PMB’s excuses, in fact it
is correct that it could not have sought relief under Code of Civil Procedure section 473
even if it had wanted to, as there was no “judgment, dismissal, order, or other proceeding
taken against him or her . . . .” (Code Civ. Proc., § 473, italics added.) If the trial court
had granted Topline’s motion, we agree that PMB most probably would have been
required to submit its excuses to the trial court for consideration under section 473. But
4Topline’s attorney opened the hearing by noting that there was no opposition. Why this did not spur associate counsel to break in is not clear.
4 as it is, PMB had no ruling to challenge below, and it has not defaulted before this court
in these proceedings. There is the further consideration that if PMB’s arguments have
merit, we would be loath to order the trial court to enter an erroneous judgment.
Accordingly, we proceed to the merits.
II
DISCUSSION
A.
As we noted above, Topline raised the statute of limitations as a defense, but did
not specify the correct statute. We cannot say that the trial court erred in this strict
application of the rules, which is supported by recent authority. (Martin v. Van Bergen
(2012) 209 Cal.App.4th 84, 91.) More fundamentally, a claim for indemnity “ ‘does not
accrue for statute of limitations purposes when the original accident occurs, but instead
accrues at the time the tort defendant pays a judgment or settlement as to which he is
entitled to indemnity.’ ” (Valley Circle Estates v. VTN Consolidated, Inc. (1983) 33
Cal.3d 604, 611, quoted in Valley Crest Landscape Development, Inc. v. Mission Pools of
Escondido, Inc. (2015) 238 Cal.App.4th 468, 481 (Valley Crest).)5 Hence, the trial
court’s ruling on this point was correct.6
5 Valley Crest also involved an attempt to use Code of Civil Procedure section 337.1’s limitation period against the party seeking indemnification.
6 At oral argument, Topline relied on Wagner v. State of California (1978) 86 Cal.App.3d 922 for the principle that under Code of Civil Procedure section 337.1, a claim for equitable indemnity must also be brought within four years. Wagner has been repeatedly distinguished and criticized for its failure to apply the standard rule on accrual. [footnote continued on next page]
5 B.
The “accepted work” doctrine or rule provides that once an owner who has
contracted for the construction of an improvement has accepted the work, it is the owner
who is solely liable to third parties injured due to a defect or condition of the
improvement. The theory is that the owner, by accepting the work, implicitly approves
of its safety and takes on the responsibility towards third parties. (Boswell v. Laird
(1857) 8 Cal. 469, 498.) The rule has evolved, however, to apply only to those defects
which are patent, so that it is fair to place upon the owner the obligation of recognizing
them and requiring them to be corrected before the work is accepted. (Sanchez v.
Swinerton & Walberg Co. (1996) 47 Cal.App.4th 1461, 1466-1470 (Sanchez), and cases
cited.)
In this case, the alleged defect is that the tiles were too slippery when wet. PMB’s
building manager testified at his deposition that he knew the tiles were slippery when wet
and instructed employees to put mats down to improve the footing well before plaintiff
fell.7 PMB had also purchased a slip-resistant material in 2009 and admitted that it had
applied slip-resistant epoxy to the tiles.
[footnote continued from previous page] (See Valley Crest, supra, 238 Cal.App.4th at p. 480; Crouse v. Brobeck, Phleger & Harrison (1998) 67 Cal.App.4th 1509, 1542.) We also note that Code of Civil Procedure section 337.15, which applies to suits involving latent defects, expressly includes actions for indemnity within its scope, whereas section 337.1 does not. We therefore believe our analysis is correct.
7 The complaint does not expressly allege that the tiles were wet when plaintiff fell. However, Topline served requests for admission on PMB which asked it to admit [footnote continued on next page]
6 Sanchez, supra, 47 Cal.App.4th 1461 was also a slip and fall case. An upstairs
landing of a building had been constructed so that it sloped slightly towards the entrance,
which caused water to pool on the landing during rainy periods. The owner and the
owner’s employees had noticed the problem in the past and had attempted to rectify it by
placing sandbags to divert the water. (Id. at p. 1464.) The appellate court had no
difficulty in concluding that any defect in the construction was patent, relying both on the
fact of the pooling and the evidence that the problem had actually been observed by the
owner. (Id. at pp. 1470-1471) It is similarly plain here that PMB was aware that the tiles
became slippery when wet and in fact attempted on its own to improve the situation.
For the purpose of applying the “accepted work” doctrine, Topline carried its
burden, if we consider both the specific evidence presented and reasonable inferences to
be drawn therefrom. (See Carlsen v. Koivumaki (2014) 227 Cal.App.4th 879, 891-892.)
Topline was fully paid for its work and the contract provides that final payment is to be
made only after the “Architect” inspected the work and found it “acceptable.” This is
another way of saying that final payment is to be made after the work is “accepted.” That
the tiles became slippery when wet became obvious to PMB and its agents well before
plaintiff’s alleged fall. Hence, Topline was relieved of liability for any injury suffered by
a third party.
[footnote continued from previous page] that “Plaintiff alleges that she slipped on the tile . . . because the tile had become slippery when wet.” PMB admitted this.
7 The trial court apparently believed that the “accepted work” doctrine only applies
to bar actions by the injured party, and not actions for indemnity by a joint tortfeasor.
But the “shorthand” rule is that there can be no duty to indemnify without liability to the
injured party. (See Prince v. Pacific Gas & Electric Co. (2009) 45 Cal.4th 1151, 1159.)
In Children’s Hospital v. Sedgwick (1996) 45 Cal.App.4th 1780, a doctor defendant
prevailed at the trial of a malpractice action. The hospital at which the plaintiff had been
treated settled with the plaintiff, and then sought indemnification from the doctor. (Id. at
pp. 1783-1984.) The court rejected the hospital’s suit, commenting that “an action for
equitable indemnity is ‘wholly derivative and subject to whatever immunities or other
limitations on liability [that] would otherwise be available.’ ” (Id. at p. 1787.)
We conclude that the trial court erred in not granting summary judgment to
Topline.
However, as we have noted above, this case is procedurally more than peculiar.
Possibly through no fault of its own (or through an excusable fault), real parties in
interest have not had the opportunity to factually dispute Topline’s contentions.
Accordingly, we asked PMB whether it could represent in good faith that, if permitted to
do so, it could introduce evidence which would tend to show a triable issue of material
fact.
PMB fails to do so. Its response largely argues against application of the
acceptance rule but it provides no concrete basis on which to conclude, or even suspect,
that the project was not completed and accepted. PMB’s primary argument is that the
8 subject tile was selected by Topline and that the authorities which we have discussed
above do not preclude liability for a defective product.
The theory that the tile was selected by Topline would be inconsistent with the
evidence, specifically the declaration by Topline’s representative and contract documents
containing communications by Topline such as “[w]e need tile and grout selection, and
pattern selection.” However, even assuming that PMB could raise a triable issue as to
selection, nothing in the record suggests that the tile was in fact defective. Like many
surfaces, it had a tendency to become slippery when wet. But PMB was fully aware of
this. Just as the acceptance rule places sole responsibility upon an owner who accepts
work which constitutes a patent risk to the public, it should place the same sole
responsibility upon an owner who accepts work which contains a product which
constitutes a patent risk to the public. After the point of acceptance, it was the owner
who had the sole power to correct any known problems and protect the public.8
III
DISPOSITION
We therefore conclude that remand is unnecessary. Even if PMB persuaded the
trial court that its failure to file opposition was excusable, it has pointed to no factual
evidence in its possession which could alter the result we reach.
8 In this context it is informative, but not dispositive, that PMB never asked Topline to install new tiles or otherwise make the area safer.
9 The petition for writ of mandate is granted. Let a peremptory writ of mandate
issue, directing the Superior Court of San Bernardino Superior County to vacate its order
denying petitioner’s motion for summary judgment, and to enter a new order granting
said motion.
Petitioner is directed to prepare and have the peremptory writ of mandate issued,
copies served, and the original filed with the clerk of this court, together with proof of
service on all parties. Petitioner to recover its costs.
NOT TO BE PUBLISHED IN OFFICIAL REPORTS
RAMIREZ P. J. We concur:
HOLLENHORST J.
McKINSTER J.