Tony�s Construction v. Kraus-Anderson Construction Company, St. Louis County Schools - ISD 2142

CourtCourt of Appeals of Minnesota
DecidedJuly 5, 2016
DocketA16-75
StatusUnpublished

This text of Tony�s Construction v. Kraus-Anderson Construction Company, St. Louis County Schools - ISD 2142 (Tony�s Construction v. Kraus-Anderson Construction Company, St. Louis County Schools - ISD 2142) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tony�s Construction v. Kraus-Anderson Construction Company, St. Louis County Schools - ISD 2142, (Mich. Ct. App. 2016).

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA IN COURT OF APPEALS A16-0075

Tony’s Construction, Appellant,

vs.

Kraus-Anderson Construction Company, Defendant,

St. Louis County Schools - ISD #2142, Respondent.

Filed July 5, 2016 Affirmed Kirk, Judge

St. Louis County District Court File No. 69VI-CV-14-740

Gordon C. Pineo, Deal & Pineo, P.A., Virginia, Minnesota (for appellant)

John M. Colosimo, Bonnie A. Thayer, Colosimo, Patchin & Kearney, Ltd., Virginia, Minnesota (for respondent)

Considered and decided by Kirk, Presiding Judge; Stauber, Judge; and Bjorkman,

Judge.

UNPUBLISHED OPINION

KIRK, Judge

Appellant-subcontractor challenges the district court’s grant of summary judgment

to respondent-owner, a school district, on appellant’s claims of quantum meruit, unjust enrichment, quasi or implied contract, and promissory estoppel. Appellant argues that

genuine issues of material fact preclude summary judgment and that the district court erred

by failing to address whether the general contractor served as respondent’s agent. We

affirm because appellant’s release of the general contractor from liability released

respondent from liability as well.

FACTS

This appeal centers on the alleged nonpayment of a subcontractor who worked on

the Cherry School renovation project. The relationship between the parties is as follows:

in August 2010, respondent St. Louis County Schools - ISD #2142 (ISD) hired Johnson

Controls, Inc. (JCI) to act as the program manager for the renovation project. JCI hired

defendant Kraus-Anderson Construction Company to serve as the construction manager of

the project. Other contracts described Kraus-Anderson as a “subconsultant” to the

renovation project. Hammerlund Construction, a general contractor, accepted appellant

Tony’s Construction’s bid to perform subcontracting work including excavation, backfill

footings, and installation of erosion control and storm ponds.

In December 2014, Tony’s filed a complaint against Kraus-Anderson and ISD under

the theory of quantum meruit, alleging that it had not been paid for change-order work

performed under the direction of Kraus-Anderson and with Hammerlund’s knowledge.

Tony’s later amended its complaint to include claims of unjust enrichment, quasi or implied

contract, and promissory estoppel.

In a deposition, Anthony Lastovich, owner of Tony’s, testified that he and three of

his employees worked at the Cherry School renovation site. During the renovation, Tony’s

2 executed several change orders. A change order was a new or different task that Tony’s

was asked to perform. Before Tony’s would begin work on a change order, Lastovich

would determine the cost of labor and materials to complete the task and provide

Hammerlund with this information. Hammerlund would then authorize Tony’s to perform

the task, and Tony’s would complete the change order. The contractual agreement between

Hammerlund and Tony’s stated that Tony’s agreed to secure Hammerlund’s consent and

written authorization before performing any change-order work.

During the early stages of the renovation, Hammerlund and Tony’s followed the

change-order process as outlined in their contractual agreement. But as the workers faced

a looming project deadline, Lastovich and his employees began taking directions on change

orders from Kraus-Anderson’s onsite project manager despite the fact that Tony’s did not

have a direct contractual relationship with Kraus-Anderson. Zachary Preble,

Hammerlund’s project manager for the renovation, testified in a deposition that the project

was plagued with problems and did not run smoothly. Lastovich testified that Kraus-

Anderson’s project manager ordered that any problems “be dealt with almost

immediately.” He also told Lastovich to keep track of his work and hours and that Kraus-

Anderson would pay for the change-order work at the end of the project. Lastovich

expected that payment for the completed change-order work would be funneled from

Kraus-Anderson to Hammerlund, who would then pay Tony’s.

At the end of the project, Lastovich submitted 19 invoices for unpaid change orders

totaling $76,579.62. Prior to initiating this action, Lastovich settled his dispute with

3 Hammerlund through a Pierringer release for $15,366.29. In 2015, Tony’s dismissed its

claim against Kraus-Anderson with prejudice.

Tony’s sued ISD under the theory of quantum meruit, quasi or implied contract, and

unjust enrichment, arguing that ISD was unjustly enriched by its work on the renovation

project, citing unusual circumstances including a poorly run renovation project, the large

number of change orders, and the fact that the parties did not always follow the prescribed

change-order process as outlined in the contract. Tony’s also asserted a promissory-

estoppel claim, arguing that Tony’s had detrimentally relied on Kraus-Anderson’s promise

that Tony’s would be paid for the change-order work.

ISD moved for summary judgment on the ground that Tony’s did not have a contract

with ISD and that ISD did not know, direct, or communicate with Lastovich or any of his

employees about Tony’s change-order work. After a hearing, the district court granted

summary judgment in favor of ISD. It dismissed Tony’s quantum meruit, quasi contract,

and unjust-enrichment claims, concluding that Tony’s failed to demonstrate that ISD

benefitted from its work through illegal, unlawful, or unjust means. Citing Lundstrom

Constr. Co. v. Dygert, it recognized that Tony’s could potentially recover if unusual

circumstances were present, such as direct contact between Tony’s and ISD, but there was

no evidence in the record that ISD knew about the change orders as they happened. 254

Minn. 224, 232, 94 N.W.2d 527, 533 (1959). It also denied Tony’s promissory-estoppel

claim, as there was no evidence of a promise between the parties. It pointed to Tony’s

admission that ISD never directed a change order or promised to pay for a change order.

Tony’s appeals.

4 DECISION

“On appeal from summary judgment, we review whether there are any genuine

issues of material fact and whether the district court erred in its application of the law.”

STAR Ctrs., Inc. v. Faegre & Benson, L.L.P., 644 N.W.2d 72, 76 (Minn. 2002). “We view

the evidence in the light most favorable to the party against whom summary judgment was

granted . . . [and] review de novo whether a genuine issue of material fact exists.” Id. at

76-77. “We also review de novo whether the district court erred in its application of the

law.” Id. at 77. “Once the moving party has made a prima facie case that entitles it to

summary judgment, the burden shifts to the nonmoving party to produce specific facts that

raise a genuine issue for trial.” Bebo v. Delander, 632 N.W.2d 732, 737 (Minn. App. 2001),

review denied (Minn. Oct. 16, 2001).

“Unjust enrichment is an equitable doctrine that allows a plaintiff to recover a

benefit conferred upon a defendant when retention of the benefit is not legally justifiable.”

Caldas v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Urban Ex Rel. Urban v. American Legion Post 184
695 N.W.2d 153 (Court of Appeals of Minnesota, 2005)
Busch v. Model Corp.
708 N.W.2d 546 (Court of Appeals of Minnesota, 2006)
Sharp v. Laubersheimer
347 N.W.2d 268 (Supreme Court of Minnesota, 1984)
Skjod v. Hofstede
402 N.W.2d 839 (Court of Appeals of Minnesota, 1987)
Hommerding v. Peterson
376 N.W.2d 456 (Court of Appeals of Minnesota, 1985)
Bedow v. Watkins
552 N.W.2d 543 (Supreme Court of Minnesota, 1996)
Star Centers, Inc. v. Faegre & Benson, L.L.P.
644 N.W.2d 72 (Supreme Court of Minnesota, 2002)
Duluth Lumber & Plywood Co. v. Delta Development, Inc.
281 N.W.2d 377 (Supreme Court of Minnesota, 1979)
Booth v. Gades
788 N.W.2d 701 (Supreme Court of Minnesota, 2010)
Urban v. American Legion Department of Minnesota
723 N.W.2d 1 (Supreme Court of Minnesota, 2006)
Lundstrom Construction Co. v. Dygert
94 N.W.2d 527 (Supreme Court of Minnesota, 1959)
GME Consultants, Inc. v. Oak Grove Development, Inc.
515 N.W.2d 74 (Court of Appeals of Minnesota, 1994)
Schumacher v. Schumacher
627 N.W.2d 725 (Court of Appeals of Minnesota, 2001)
Johnson & Peterson, Inc. v. Toohey
172 N.W.2d 326 (Supreme Court of Minnesota, 1969)
Bebo v. Delander
632 N.W.2d 732 (Court of Appeals of Minnesota, 2001)
Cityscapes Development, LLC v. Larry Scheffler
866 N.W.2d 66 (Court of Appeals of Minnesota, 2015)
Serr v. Biwabik Concrete Aggregate Co.
278 N.W. 355 (Supreme Court of Minnesota, 1938)
State v. Ernest
278 N.W.2d 355 (Nebraska Supreme Court, 1979)
Zinter v. University of Minnesota
799 N.W.2d 243 (Court of Appeals of Minnesota, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Tony�s Construction v. Kraus-Anderson Construction Company, St. Louis County Schools - ISD 2142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tonys-construction-v-kraus-anderson-construction-company-st-louis-minnctapp-2016.