Toney v. Fauhiva

123 P.3d 691, 109 Haw. 96, 2005 Haw. App. LEXIS 455
CourtHawaii Intermediate Court of Appeals
DecidedOctober 28, 2005
DocketNo. 26693
StatusPublished
Cited by1 cases

This text of 123 P.3d 691 (Toney v. Fauhiva) is published on Counsel Stack Legal Research, covering Hawaii Intermediate Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Toney v. Fauhiva, 123 P.3d 691, 109 Haw. 96, 2005 Haw. App. LEXIS 455 (hawapp 2005).

Opinion

Opinion of the Court by

BURNS, C.J.

Plaintiffs-Appellants Bryan Toney (Bryan) and Lilibeth Toney (collectively, the Toneys) appeal from the June 16, 2004 Final Judgment in favor of Defendant-Appellee Lemoto “Ray” Fauhiva (Fauhiva), and the July 14, 2004 Judgment awarding Fauhiva $8,245.25 for costs and $5,745.00 for attorney fees.1 We affirm.

BACKGROUND

The Toneys were owners of residential land located in the District of North Kona, Hawai'i, identified as Tax Map Key (3) 7-3-059:022 Lot 7-Q. During March 2002, the Toneys were in the process of constructing a residence on their property. They were operating pursuant to the “owner-builder” exception stated in Hawaii Revised Statutes (HRS) § 444-2(7) (Supp.2004). During this time, the Toneys entered into a contract with Fauhiva, a licensed masonry contractor. In the contract, Fauhiva agreed to construct a retaining wall on the Toneys’ property. Fau-hiva completed construction of the retaining wall in April 2002. Later that year, on August 20 or 21, the retaining wall collapsed.2

[98]*98On December 10, 2002, the Toneys filed a Complaint, in the Circuit Court of the Third Circuit, seeking damages “including but not limited to the cost to [the Toneys] of clearing of collapsed wall(s) and rubble and excavation for replacement wall(s); labor and materials for the failed and replaced wall(s); payment for damages to adjoining residential property upon which the walls collapsed; costs and attorneys fees, for all of which [Fauhiva] is liable.”

By leave of the circuit court, the Toneys, on July 16, 2003, filed their First Amended Complaint for Damages. In their First Amended Complaint, the Toneys contended inter alia that Fauhiva had failed to comply with the disclosure requirements imposed by HRS § 444-25.5 (Supp.2003). Specifically, they alleged:

9. The contracted matter and [Fauhiva] and [the Toneys’] relationship and activities referred to above are subject to and governed by Chapter 444 of the Hawaii Revised Statutes and particularly Section 444-25.5 thereof.
10. [Fauhiva] failed to comply with and violated Section 444-25.5 of the Hawaii Revised Statutes and is entitled to the relief provided thereby and by Chapter 480 of the Hawaii Revised Statutes.
11. Because of [Fauhiva’s] violation of an [sic] failure to comply with Chapter 441[sic] and Section 444-25.5 thereof, [Fauhiva] has violated Chapter 480 of the Hawaii Revised Statutes, thereby entitling [the Toneys] to the relief provided by that Chapter.

A jury trial was held on February 24 and 25, and on March 2 and 3, 2004. At trial, at the conclusion of the Toneys’ evidence, both parties moved for a directed verdict on the issue of the applicability of HRS § 444-25.5. The parties stipulated to the following: (1) the applicability of HRS Chapter 444 is solely a question of law; (2) the Toneys were owner-builders when they hired Fauhiva; (3) Fauhiva was a licensed contractor; and (4) HRS § 444-25.5 was not followed. Concluding that HRS Chapter 444 was not applicable, the circuit court orally granted Fauhiva’s motion for directed verdict. The written order was filed on March 30, 2004.

On a special verdict form, the jury determined that Fauhiva was negligent in constructing the retaining wall, Bryan was negligent in connection with the construction of the retaining wall, Fauhiva’s negligence was a 30 percent cause of the damages, and Bryan’s negligence was a 70 percent cause of the damages. On June 16, 2004, the circuit court entered a Final Judgment that stated, in relevant part:

Pursuant to the March 30, 2004 Order granting [Fauhiva’s] Motion for Directed Verdict with Respect to [the Toneys’] Hawaii Revised Statues [sic] § 444-25.5 Claims, the jury special verdict entered on [99]*99March 3, 2004 and good cause appearing therefor;
IT IS HEREBY ORDERED, ADJUDGED AND DECREED as follows:
1. Final Judgment is entered in favor of [Fauhiva] with respect to all of [the Toneys’] claims and that [the Toneys] recover nothing herein.
2. All other claims asserted in Civil No. 02-1-0229K not specifically identified above are dismissed with prejudice.
3. There are no further claims or parties in Civil No. 02-1-0229K.

On April 7, 2004, Fauhiva filed a motion for an award of attorneys fees and costs. On June 10, 2004, the circuit court entered its Order Granting in Part [Fauhiva’s] Motion for Costs and Attorneys’ Fees awarding Fau-hiva $8,245.25 for costs and $5,745.00 for attorney fees. A Judgment to this effect was entered on July 14, 2004.

The Toneys filed a notice of appeal on July 16, 2004. An amended notice of appeal was subsequently filed on July 20, 2004. The appeal was assigned to this court on December 20,2004.

POINTS ON APPEAL

In their opening brief, the Toneys contend:
A. The Circuit Court below erred in granting [Fauhiva’s] motion for a directed verdict by its ORDER GRANTING DEFENDANT LEMOTO “RAY” FAUHIVA dba HAWAIIAN ISLE MASONRY’S MOTION FOR DIRECTED VERDICT WITH RESPECT TO PLAINTIFFS’ HAWAII REVISED STATUES [sic] § 444-25.5 CLAIMS entered on March 3[0], 2004....
B. The Circuit Court below erred in denying PLAINTIFFS BRYAN TONEY AND LILIBETH TONEY’S MOTION FOR DIRECTED VERDICT, ... which was by implication denied by ORDER GRANTING DEFENDANT LEMOTO “RAY” FAUHIVA dba HAWAIIAN ISLE MASONRY’S MOTION FOR DIRECTED VERDICT WITH RESPECT TO PLAINTIFFS’ HAWAII REVISED STATUES [sic] § 444-25.5 CLAIMS entered on March 3[0], 2004,....
C.The Circuit Court below erred in entering its Final Judgment entered on June 16, 2004, and its Judgment entered on July 14, 2004, by not including awards in [the Toneys’] favor as provided for by H.R.S § 444-25.5 and particularly subsection d) thereof, and H.R.S. Chapter 480.

STANDARDS OF REVIEW

Directed Verdict

Hawaii appellate courts review, de novo, a trial court’s rulings on directed verdict or judgment notwithstanding the verdict (JNOV) motions. In re Estate of Herbert, 90 Hawai'i 443, 454, 979 P.2d 39, 50 (1999).

The test of the validity of a directed verdict is whether the evidence is such that, after giving to plaintiffs’ evidence all value to which it is legally entitled, and indulging every legitimate inference which may be drawn from the evidence in plaintiffs’ favor, it can be said that there is no evidence to support a jury verdict in plaintiff’s favor.

Lang v. Beech Aircraft Corp., 4 Haw.App. 237, 244, 663 P.2d 640, 644-45 (1983).

Verdicts based on conflicting evidence will not be set aside where there is substantial evidence to support the jury’s findings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scherer v. CONTRACTORS LICENSE BOARD
222 P.3d 466 (Hawaii Intermediate Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
123 P.3d 691, 109 Haw. 96, 2005 Haw. App. LEXIS 455, Counsel Stack Legal Research, https://law.counselstack.com/opinion/toney-v-fauhiva-hawapp-2005.