Tommy Hilfiger v. N. Conway Outlets

CourtDistrict Court, D. New Hampshire
DecidedFebruary 14, 2000
DocketCV-99-147-B
StatusPublished

This text of Tommy Hilfiger v. N. Conway Outlets (Tommy Hilfiger v. N. Conway Outlets) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tommy Hilfiger v. N. Conway Outlets, (D.N.H. 2000).

Opinion

Tommy Hilfiger v. N. Conway Outlets CV-99-147-B 2/14/00

UNITED STATE DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

Tommy Hilfiger Retail. Inc,

v. Civil No. 99-C-147-B Opinion No. 2000 DNH 03S North Conway Outlets LLC

MEMORANDUM AND ORDER

Tommy Hilfiger Retail, Inc. ("Hilfiger") entered into a

long-term commercial lease with North Conway Outlets ("NCO") , a

developer that planned to build a retail outlet shopping center

in North Conway, New Hampshire. NCO failed to complete

construction of the shopping center by the deadline specified in

the lease. The issue presented by this declaratory judgment

action is whether NCO is entitled to invoke a clause in the lease

excusing any delay in completing construction caused by

"governmental restrictions."

I. BACKGROUND On January 16, 1997, after a period of negotiation, Hilfiger

and NCO entered into a seven year commercial lease for retail

- 2 - space in a shopping center NCO planned to build in North Conway,

New Hampshire. See Aff. of Steven R. Gursky, Esq. I 2

[hereinafter Gursky Aff.]; Aff. of Jordan D. Warshaw 5 2

[hereinafter Warshaw Aff.]. Under Section 6.2 of the lease, NCO

agreed that

construction of the demised premises to the extent required of [NCO] shall be substantially completed by not later than twelve (12) months following October 1, 1997 unless [NCO's] failure so to complete is caused by governmental restrictions, strikes, walkouts, shortages of material or labor, act of God, enemy actions, civil commotion, fire or casualty, or any other causes beyond the reasonable control of [NC01, in which event the aforesaid date shall be extended for such period as [NCO] is so prevented from completing such construction. If such substantial completion has not been achieved by the aforesaid date, as extended as aforesaid, [Hilfiger] and [NCO] shall have the right to terminate this lease by giving written notice of such termination to the other within thirty (30) days thereafter.

Gursky Aff. Ex. A § 6.2 (emphasis added).

On March 20, 1997, the Conway Planning Board ("Planning

Board") granted final site plan approval for NCO's project.

See Warshaw Aff. SI 4. Mountain Valley Mall Associates ("MVMA") ,

a shopping mall located across the street from NCO's proposed

- 3 - development, appealed the Planning Board's grant of final

approval to both the Conway Zoning Board of Adjustment ("ZBA")

and the New Hampshire Superior Court. See id. 5 5 3, 5, 6. The

ZBA refused to hear the matter and MVMA appealed the ZBA's

decision to superior court. See id. I I S , 6. The Superior

Court affirmed both the Planning Board's grant of final site plan

approval and the ZBA's refusal to consider MVMA's appeal. See

id. I 7.1 MVMA then appealed both decisions. The New Hampshire

Supreme Court affirmed both decisions on February 3, 2000. See

id. 5 8.

NCO did not begin construction of the planned shopping

center by the October 1, 1998 substantial completion date

specified in the lease. Shortly after the deadline expired,

Hilfiger notified NCO that it had breached the lease and that

1 The Superior Court dismissed MVMA's ZBA appeal because MVMA's "planning board claims [had] already been adjudicated and [its] ZBA appeal was not preserved through proper exhaustion of administrative remedies." Mountain Valley Mall Assocs. v. Municipality of Conway and Conway Zoning Bd. of Adjustment, N o . 97-E-125, slip op. at 6 (N.H. Super. C t ., Carroll County Feb. 11, 1998) .

- 4 - Hilfiger was exercising its right to terminate. See id. Ex. C.

NCO responded by claiming that it could not build the shopping

center because MVMA had appealed the land use approvals NCO

needed to begin construction. See id. Ex. D. NCO argued,

therefore, that the time for completing construction was extended

because its inability to build was due to a cause beyond its

reasonable control. See id. It has since also argued that its

inability to meet the substantial completion deadline must be

excused because its inability to build was the result of

governmental restrictions. Hilfiger commenced this declaratory

judgment action to resolve the dispute. It now seeks summary

judgment.

II. STANDARD OF REVIEW

Summary judgment is appropriate if the record, viewed in the

light most favorable to the non-moving party, shows that no

genuine issues of material fact exist and that the moving party

is entitled to judgment as a matter of law. See Fed R. Civ. P.

- 5 - 56(c); Commercial Union Ins. Co. v. Walbrook Ins. Co., 7 F.3d

1047, 1050 (1st Cir. 1993). A material fact is one "that might

affect the outcome of the suit under the governing law."

Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). A

genuine factual issue exists if "the evidence is such that a

reasonable jury could return a verdict for the nonmoving party."

Id.

Summary judgment is appropriate to resolve a question of

contract interpretation "only if the meaning of the language is

clear," in light of the surrounding circumstances and the

undisputed evidence of the parties' intent. See Rodriquez-Abreu

v. Chase Manhattan Bank, N.A., 986 F.2d 580, 586 (1st Cir. 1993)

(noting that there must be "no genuine issue as to the inferences

which might reasonably be drawn from the language"). A dispute

over the proper interpretation of the pertinent contract

provision does not necessarily give rise to a "genuine issue."

See Boston Five Cents Sav. Bank v. Secretary of Dep't of Hous.

and Urban Dev., 768 F.2d 5, 8 (1st Cir. 1985) . If the words of

- 6 - the contract are so clear that "reasonable people could not

differ over their meaning," the contract language is unambiguous

and the court decides the issue of proper interpretation. Id.;

see also United States Liab. Ins. Co. v. Selman, 70 F.3d 684, 687

(1st Cir. 1995). To prevail under these circumstances, the

moving party must demonstrate that its interpretation of the

unambiguous language is correct. See Allen v. Adage, Inc., 967

F .2d 695, 701 n. 5 (1st Cir. 1992).

- 7 - In contrast, summary judgment generally is inappropriate if

the meaning of contract language is ambiguous and the extrinsic

evidence bearing on the meaning of the ambiguous language is

contested. See id. at 698 n. 3. In such circumstances, summary

judgment is appropriate only if the extrinsic evidence of the

parties' "intended meaning is so one-sided that no reasonable

person could decide to the contrary." Bank v. International Bus.

Machs. Corp., 145 F.3d 420, 424 (1st Cir. 1998) (internal

quotation marks and citations omitted); Allen, 967 F.2d at 698

(same).

Applying the summary judgment standard in the context of the

present case, Hilfiger will not be entitled to judgment if the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
United States Liability Insurance v. Selman
70 F.3d 684 (First Circuit, 1995)
Bank v. International Business MacHines Corp.
145 F.3d 420 (First Circuit, 1998)
W.P. Associates v. Forcier, Inc.
637 A.2d 353 (Supreme Court of Rhode Island, 1994)
Rollins v. Rollins
440 A.2d 438 (Supreme Court of New Hampshire, 1982)
Anderson v. Century Products Co.
943 F. Supp. 137 (D. New Hampshire, 1996)
Restaurant Operators, Inc. v. Jenney
519 A.2d 256 (Supreme Court of New Hampshire, 1986)
Woodstock Soapstone Co. v. Carleton
585 A.2d 312 (Supreme Court of New Hampshire, 1991)
Gamble v. University System
610 A.2d 357 (Supreme Court of New Hampshire, 1992)
Butler v. Walker Power, Inc.
629 A.2d 91 (Supreme Court of New Hampshire, 1993)
Appeal of Dell
668 A.2d 1024 (Supreme Court of New Hampshire, 1995)
Echo Consulting Services, Inc. v. North Conway Bank
669 A.2d 227 (Supreme Court of New Hampshire, 1995)
Hampton Beach Casino, Inc. v. Town of Hampton
674 A.2d 979 (Supreme Court of New Hampshire, 1996)
Alexander v. Blackstone Realty Associates
684 A.2d 60 (Supreme Court of New Hampshire, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Tommy Hilfiger v. N. Conway Outlets, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tommy-hilfiger-v-n-conway-outlets-nhd-2000.