Tom Shaw, Inc. v. Robert E. Derecktor of Rhode Island, Inc.

639 F. Supp. 1064, 1986 U.S. Dist. LEXIS 23054
CourtDistrict Court, D. Rhode Island
DecidedJuly 9, 1986
DocketCiv. A. 85-402
StatusPublished
Cited by2 cases

This text of 639 F. Supp. 1064 (Tom Shaw, Inc. v. Robert E. Derecktor of Rhode Island, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tom Shaw, Inc. v. Robert E. Derecktor of Rhode Island, Inc., 639 F. Supp. 1064, 1986 U.S. Dist. LEXIS 23054 (D.R.I. 1986).

Opinion

OPINION

FRANCIS J. BOYLE, Chief Judge.

Car Float # 12 is a barge owned by Plaintiff. It was built in 1923. 1 The barge is approximately 210 feet long and 34 feet wide, has a draft of 4 to 5 feet with 4 to 6 feet freeboard. It was built of 24 compartments each with a hatch, arranged three across and in eight rows. On March 27, 1985, the barge overturned while being towed to Point Judith, Rhode Island from Davisville, Rhode Island. It was carrying a cargo of boulders to be used in the restoration of a sea wall. The stone was in the order of 12 to 15 ton boulders. At the time that the barge tipped over, the Plaintiff was in a state of “demobilization” on its contract. There remained seven loads of stone to be delivered. The normal turnaround time was three days per load. The Plaintiff had contracted with the Army Corps of Engineers to perform the work at Point Judith.

After it overturned, the barge was towed to Galilee, Rhode Island where the Plaintiff’s employees sought to right it by attaching lines to its opposite side and pulling on the lines with a tug. Temporary hatch *1066 covers were applied. This effort was not successful. The barge was then taken to Davisville, Rhode Island and on Monday, May 20, 1985 to Defendant Derecktor’s Shipyard in Middletown, Rhode Island. There it sank in another unsuccessful attempt to right it. The barge was flipped over but it sank alongside Defendant’s bulkhead. In the process of flipping the barge and in an effort to minimize the effect of its sinking, Defendant’s crane was damaged.

Before car float # 12 was brought to the Defendant’s shipyard it had been towed to the Harbor of Refuge where the first attempt to right it was made by the Plaintiff. A single steel pad eye 2 was welded to the side of the barge and a cable attached to the pad eye was carried up the side and across the upturned bottom of the barge to a tug on the side of the barge opposite the pad eye. The effort was made to pull the side of the barge to which the pad eye was attached up and over thereby righting the barge. The attempt was made after the hatches were secured with plywood covers, using sealing material around the edges and held in place with a bolt attached to a 2 by 4 across the interior part of the hatch. Some repairs were also made to the bottom of the barge to make it more watertight. Some weeks later two additional pad eyes were welded to the side of the barge equidistant from the ends of the barge and 106 feet apart. The pad eyes were described as being a little better than an inch thick, flat-stock plain hot rolled carbon steel, 8 to 10 inches long, with a hole to receive an attachment, and with a hardness of 81.3 on the Rockwell B schedule and a tensile strength of 73,400 lbs. per square inch. These pad eyes were used in the attempt to flip the barge at Defendant’s yard.

After the May 20, 1985 effort to right the barge at the Derecktor Shipyard, Plaintiff’s employees made an effort to keep the barge afloat, but it failed. They then left the barge, never thereafter to return. Two efforts by the Defendant’s employees were subsequently made to raise the barge, one by pumping up the center line tanks, which was not successful, and the other by lifting and pumping, using a number of pumps. The first effort of Defendant to raise the barge was made in the first week of June, 1985 and Derecktor’s people worked for three days. The barge had been raised by the 21st or 22nd of June and placed in a small dry dock where work was done to make it watertight. The barge was removed from the Derecktor Shipyard on August 12, 1985.

The Plaintiff corporation completed its contract with the Army Corps of Engineers on May 13, 1985. The Army Corps of Engineers cancelled its contract with Plaintiff on May 20, 1985. On October 3, 1985 Plaintiff’s tug and two other barges left Rhode Island to return to Cheboygan, Michigan with heavy equipment which had been used in performing the contract. Some equipment was left behind in Rhode Island. The Plaintiff had a substantial quantity of large equipment in Rhode Island which had been acquired to perform the contract, including substantial quarry equipment and loading equipment and which under the contract could be moved to Cheboygan, Michigan at the expense of the government. The Plaintiff estimated this cost at $266,465.

The Plaintiff contended that it intended to transport the equipment on car float # 12 and that it was prevented from doing so because of the failure of the Defendant to successfully right the barge in May of 1985. At the time of trial, it was the government’s position that it would not make the payment to Plaintiff. Plaintiff was, however, pursuing a claim against the government for the payment in an action entitled Tom Shaw, Inc. v. The United States of America, # 668-85c, in the United States Court of Claims. The Plaintiff completed its obligations under the con *1067 tract with the Army Corps of Engineers, using another smaller barge which it owned, and proceeded to ship some of the construction equipment to Cheboygan on that barge and another owned by the company, and towed by its tug, the Robert Charles. At the time of trial, because of delays in transit, the tug and barges had not reached Cheboygan.

Estimates of the fair market value of Car Float # 12 after it had been successfully righted varied from $10,000 maximum by Plaintiffs expert to $33,000 by two of Defendant’s experts.

The Plaintiff contends that the Defendant was negligent in the manner in which it sought to right the barge, and the Defendant contends that the Plaintiff was negligent in its failure to make the barge watertight and to attach pad eyes of adequate strength. The underlying relationship between the parties is contractual. There is however no written contract. Plaintiff first contacted the Defendant employees because of information that the Defendant had a crane which was adequate to flip the barge over. The Plaintiff claims that during the effort to right the barge, the barge was damaged and that it lost the difference between the purchase price of the barge, $35,000, and the price at which it was sold, $11,000. It also claims consequential damages. Plaintiff seeks reimbursement of monies which would have been paid to it for transporting its equipment to Cheboygan, Michigan under its contract with the Army Corp. of Engineers. Defendant seeks reimbursement for damages sustained by its crane in an unsuccessful attempt to right the barge and the cost of raising, repair and dockage of the barge.

Addressing first the claim of the Plaintiff against the Defendant, apart from the issue of liability, in order to recover in a negligence action, it is axiomatic that Plaintiff has the burden of proving damages by a fair preponderance of the evidence. Damages must be proved. They are not to be presumed. Blake v. Robertson, 4 Otto 728, 94 U.S. 728, 733, 24 L.Ed. 245 (1876). The Plaintiff has completely failed to prove damages. The credible evidence is that the car float was worth as much on the market after the Defendant salvaged it as it was before the sinking; in the area of $33,000.

The so-called consequential damages which the Plaintiff seeks in the amount of $266,465 are wholly unsubstantiated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erinakes v. Zahreddine
Superior Court of Rhode Island, 2009

Cite This Page — Counsel Stack

Bluebook (online)
639 F. Supp. 1064, 1986 U.S. Dist. LEXIS 23054, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tom-shaw-inc-v-robert-e-derecktor-of-rhode-island-inc-rid-1986.