Toltest, Inc. v. North American Specialty Insurance

362 F. App'x 514
CourtCourt of Appeals for the Sixth Circuit
DecidedJanuary 27, 2010
Docket09-1544
StatusUnpublished
Cited by4 cases

This text of 362 F. App'x 514 (Toltest, Inc. v. North American Specialty Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Toltest, Inc. v. North American Specialty Insurance, 362 F. App'x 514 (6th Cir. 2010).

Opinion

OPINION

CLAY, Cii-cuit Judge.

Plaintiff TolTest, Inc. (“TolTest”) appeals from the grant of summary judgment to Defendant North American Specialty Insurance Company (“NASIC”) on the grounds of res judicata. TolTest sued NASIC as the surety for Acme Contracting, Ltd. (“Acme”), a subcontractor who successfully bid for a contract but then failed to perform. TolTest argues that NASIC owes a 5% bid bond for Acme’s failure to perform. The district judge determined that TolTest’s failure to litigate this issue in previous litigation between Acme and TolTest barred them from pursuing it here. TolTest also appeals the denial of their motion to add Acme as a defendant. For the following reasons, the judgment of the district court is AFFIRMED.

FACTUAL HISTORY

The resolution of this case is inextricably related to separate litigation between TolTest and Acme currently pending before this Court as Case No. 08-2072 (the “Acme-TolTest litigation”). The Acme-TolTest litigation deals with a contract dispute stemming from an agreement to demolish two buildings at Georgia Tech University. The full factual history of that case, as found by a district judge following a bench trial, can be found at Acme Contracting, Ltd. v. TolTest, Inc., No. 07-10950, 2008 WL 1990780 (E.D.Mich. May 5, 2008). A brief recitation of the facts most relevant to this appeal is provided here.

TolTest and Acme were contractor and subcontractor on a construction demolition project at Georgia Tech University. The contract that the parties entered into is called the 01-contract. While the parties were operating under the 01-contract, the project manager, Whiting-Turner, offered the 04-contract for bid. Acme submitted a bid as subcontractor to TolTest, who successfully used the bid to secure the contract. Following TolTest’s receipt of the contract, Acme refused to enter into an agreement with TolTest on the 04-con-tract. Acme had secured a 5% bid bond in connection with the 04-contraet, and Tol-Test, in this suit, hopes to receive those funds from Acme’s surety, NASIC.

The Acme-TolTest litigation does not focus on the 04-Contract. The heart of the suit was Acme’s allegations that Tol- *516 Test breached the 01-eontract. Additionally, however, Acme pursued a claim for quantum meruit based on its contention that it performed work that would have been part of the 04-contract and was not compensated for it. TolTest currently does not contest that Acme performed this work or that it is entitled to some compensation for it. In the course of reaching its decision in the Acme-TolTest litigation, the district court made the following findings about the 04-Contract:

Meanwhile, on or about April 6, 2006, Whiting-Turner invited TolTest to bid on a separate groundwork, grading, and shoring phase of the Georgia Tech Project (Subcontract Number 11000-04). (Stipulated Facts at ¶ 24). TolTest and Acme again collaborated on bidding this second phase. (Stipulated Facts at ¶ 25). On or about May 22, 2006, Acme submitted a bid to TolTest for $1,517,349 to perform the work under this second phase. (Stipulated Facts at ¶ 26). Whiting-Turner awarded TolTest Subcontract Number 11000-04 for “Grading and Site Utilities”. (Stipulated Facts at ¶ 27).
TolTest sent a purchase order to Acme for work to be performed under Subcontract Number 11000-04. (Stipulated Facts at ¶ 28). Acme did not sign that purchase order, however, because the ultimate contract that TolTest signed with Whiting-Turner, the “04-Con-tract,” had expanded the work that Acme would perform but did not provide for any increased compensation to Acme for that work. It is undisputed that TolTest and Acme were never able to arrive at an Agreement for work under Subcontract Number 11000-04 for “Grading and Site Utilities” and Acme never signed the purchase order. (Stipulated Facts at ¶ 31).

DISCUSSION

The district court granted summary judgment on behalf of NASIC based both on principles of res judicata and based on a determination that TolTest’s claim was a compulsory counter-claim in the AcmeTolTest litigation. The district court should be affirmed if either ground is independently satisfied. Traditional res judicata principles are broader and incorporate more activity, so we rest our holding on that basis. 1

This Court reviews de novo a district court’s application of the doctrine of res judicata. Bragg v. Flint Bd. of Educ. 570 F.3d 775, 776 (6th Cir.2009). The party asserting the defense of res judicata bears the burden of proof. Winget v. JP Morgan Chase Bank, 537 F.3d 565, 572 (6th Cir.2008). For res judicata to apply, the following elements must be present: (1) a final decision on the merits by a court of competent jurisdiction; (2) a subsequent action between the same parties or their “privies.”; (3) an issue in the subsequent action which was litigated or which should have been litigated in the prior action; and (4) an identity of the causes of action. Bragg, 570 F.3d at 776 (quoting Bittinger v. Tecumseh Products Co., 123 F.3d 877, *517 880 (6th Cir.1997)). Before the district court, and also on appeal, TolTest only contests the third element.

In order to make a finding of res judicata in this case, the Court must determine that TolTest should have brought a counter-claim in the Acme-TolTest litigation. The issue of the bid bond was assuredly not litigated in the previous action, but NASIC’s contention is that it “should have been litigated.” TolTest argues in reply that “the law is clear — res judicata applies only to claims that TolTest was required to bring at that time, not those that it could have.” (Pl. Reply Br. at 7). TolTest’s assertion is simply not correct. The Sixth Circuit has rejected an argument that only compulsory counter-claims apply to res judicata, finding that “what is important is not whether a particular claim is compulsory, but whether the claim should have been considered during the prior action.” Sanders Confectionery Prods., Inc. v. Heller Fin., Inc., 973 F.2d 474, 484 (6th Cir. 1992). The purpose of res judicata is to compel “litigants to bring all related claims in one suit.” Wilkins v. Jakeway, 183 F.3d 528, 532 n. 4 (6th Cir.1999).

The contested issue in this suit by Tol-Test is the negotiations over the 04-con-tract. The district court crucially remarked that “to litigate the bid bond claim in this action, TolTest would present the testimony of the very same witnesses who testified in [the Acme-TolTest litigation] and would present the very same documents that were presented in that action.” TolTest, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
362 F. App'x 514, Counsel Stack Legal Research, https://law.counselstack.com/opinion/toltest-inc-v-north-american-specialty-insurance-ca6-2010.