Toledo Plate & Window Glass Co. v. Smoger Lumber

195 N.E. 577, 100 Ind. App. 620, 1935 Ind. App. LEXIS 77
CourtIndiana Court of Appeals
DecidedMay 7, 1935
DocketNo. 14,808.
StatusPublished

This text of 195 N.E. 577 (Toledo Plate & Window Glass Co. v. Smoger Lumber) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Toledo Plate & Window Glass Co. v. Smoger Lumber, 195 N.E. 577, 100 Ind. App. 620, 1935 Ind. App. LEXIS 77 (Ind. Ct. App. 1935).

Opinion

Appellee, Kosciusko Building and Loan Association entered into a contract with appellee, Smoger Lumber Company, whereby the lumber company agreed to construct a building for the loan association on real estate belonging to it. While the building was in progress of *622 construction the lumber company entered into a contract with appellant whereby it was to furnish at an agreed price of $537.00, plate and mirror glass of various descriptions for use in the construction of said building.

All plate glass and mirrors were delivered by appellant in boxes upon the premises where the building was in process of construction by the 11th day of July, 1929.

On or about the 1st day of August, 1929, the mirrors were unpacked from the boxes and installed by the lumber company, as contractor, in the building. The installation consisted of introducing the mirrors into false window framing recesses in the brick walls, having been left for that purpose, and framing around the mirrors. In all there were 84 mirrors which required two men three or four days to install- and none of which mirrors, prior to their installation, were inspected by either the contractor or architect.

A few days after the installation of the mirrors which, at the time of the installation, had dirty and dusty surfaces, the architect and secretary of the loan association observed what appeared to be murkiness in the mirrors and brush and stencil marks.

On the 21st day of September, 1929, the contractor communicated to the appellant the complaint of the loan association that the mirrors were defective. The contractor had already paid on account to the appellant $337.00 leaving a balance of $200.00 which was being held back by the loan association because of the defective mirrors. The appellant then examined these mirrors, offered to resilver them, and pay the freight to and from Toledo, Ohio, if the contractor would take them out of their recesses and replace them therein at the contractor’s expense, on their return from appellant’s factory. The contractor refused to pay for the *623 removal and replacement so as to this proposition nothing' more was done.

In January, 1930, the contractor demanded of appellant that it remove all the mirrors and replace the same, standing the cost of removal and replacement. Appellant then removed one mirror which, according to its agent, contained defective glass, as distinct from defective silvering of which appellee complained, and replaced the same, but declined to remove and replace the remainder but again offered to stand the cost of resilvering and the freight both ways to and from its place of business in Toledo.- This proposition was again refused.

On February 18, 1930, appellant filed a notice, directed to the loan association and the contractor, of its intent to hold a mechanic’s lien against the property of the loan association to secure the payment of the balance of $200.00 and interest. Suit was brought to foreclose this lien on the 24th day of June, 1930.

To the complaint the contractor filed a cross-complaint alleging the defects in the mirrors; that the mirrors were sold to the contractor by the appellant pursuant to certain specifications; that the loan association declined and refused to pay for the construction of said building because of the defective mirrors; that the value of the mirrors in good condition would have been $312.80; that it will cost the contractor $120.00 to replace and remove them to its damage in the sum of $432.80 for which it asked judgment.

A general denial was filed by appellant together with a second paragraph of answer to the cross-complaint alleging that the contractor waived any and all grounds for rejecting the mirrors or for any action on account of defects, by accepting the mirrors and incorporating them in the building, after it had ample opportunity for inspection and rejection thereof for the defects *624 claimed. The issues were closed by a general denial to this second paragraph of answer.

Trial was had by court and he found that appellant take nothing by its complaint and that the contractor recover on its cross-complaint and entered judgment for the contractor against the appellant for $405.00 together with the costs of this action.

Appellant’s motion for new trial contained the following grounds: (1) that the decision of the court is not sustained by sufficient evidence; (2) that the decision of the court is contrary to law; (3) that the court awarded excessive damages ’against the plaintiff; and (4) that there was error in the assessment of the amount of recovery against plaintiff, the same being too large. The overruling of this motion is assigned as error on appeal.

After stating the facts, KIME, J., rendered the following opinion.

Appellant contends that the contractor waived the defects observable in the mirrors by accepting and incorporating them in the building and cites the case of Pottlitzer et al. v. Wesson et al. (1893), 8 Ind. App. 472, 35 N. E. 1030. This case is not applicable to the case at bar for the reason that when the merchandise in the Pottlitzer case arrived at the purchasers’ place of business, after examination of said merchandise the purchasers communicated with the seller notifying him that the merchandise was not the quality ordered. The seller wired to the purchaser that the merchandise was the quality ordered and that the purchaser must accept it as such. The purchasers then took the merchandise into their possession and sold it.

It can be seen that the purchasers, regardless of the fact that they knew the merchandise to be defective, accepted it as the quality ordered and, consequently, were in no position to object to its imperfections. In *625 the case at bar the statement for the mirrors is as follows:

“THE TOLEDO PLATE &. WINDOW GLASS CO.
Toledo, Ohio
Cutomer’s Name Smoger Lbr. Co.
City, South Bend, State, Ind.
Street County
Estimate No. Date Price
Shipping Instructions.
Terms: One per cent discount ten days fro date of invoice; thirty days net. All agreements are contingent upon strikes, accidents or other causes beyond our control.
Glass for Kosciusko Bldg. & Loan Co. as per plans & spec, except that 4 mitred mirrors are changed to small mirrors not mitred. No skylight or ceiling lights or fixture glass. (Our italics.)
$515.
F. A.
Customer’s signature ROY HAYS
Salesman C. L. Lowry, Date 5/1/29.”

and an officer of appellant testified that he was familiar with the terms of the contract of construction between the contractor and the loan association.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. F. Darmody Co. v. Moss
158 N.E. 489 (Indiana Court of Appeals, 1927)
First National Bank v. Grindstaff
45 Ind. 158 (Indiana Supreme Court, 1873)
Conant v. National State Bank
22 N.E. 250 (Indiana Supreme Court, 1889)
Michigan Pipe Co. v. Sullivan County Water Co.
127 N.E. 768 (Indiana Supreme Court, 1920)
Pottlitzer v. Wesson
35 N.E. 1030 (Indiana Court of Appeals, 1893)
Zimmerman v. Druecker
44 N.E. 557 (Indiana Court of Appeals, 1896)
Edwards Manufacturing Co. v. Stoops
102 N.E. 980 (Indiana Supreme Court, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
195 N.E. 577, 100 Ind. App. 620, 1935 Ind. App. LEXIS 77, Counsel Stack Legal Research, https://law.counselstack.com/opinion/toledo-plate-window-glass-co-v-smoger-lumber-indctapp-1935.