Toledo Bridge and Crane Co. v. Oil Belt Traction Co.

173 Ill. App. 298, 1912 Ill. App. LEXIS 414
CourtAppellate Court of Illinois
DecidedJune 5, 1912
StatusPublished

This text of 173 Ill. App. 298 (Toledo Bridge and Crane Co. v. Oil Belt Traction Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Toledo Bridge and Crane Co. v. Oil Belt Traction Co., 173 Ill. App. 298, 1912 Ill. App. LEXIS 414 (Ill. Ct. App. 1912).

Opinion

Mr. Justice McBride

delivered the opinion of the court.

In this case the jury was waived and trial had by the judge of the Circuit Court of Crawford county, by consent, which resulted in a finding and judgment in favor of the plaintiff for $303.67, from which judgment the plaintiff prosecutes his appeal and insists that the judgment should have been for $1,831.33.

During the fall of 1900, the defendant in error, hereinafter called the defendant, was engaged in building a railroad near Oblong, Illinois, and was contemplating the building of three bridges along this railroad. The plaintiff in error, hereinafter called the plaintiff, had submitted to the defendant on September • 18th a bid with certain specifications for the building of these bridges and on September 28th, submitted to it a revised proposition. The Empire Railway Supply Company, hereinafter called the Supply Company, was a broker having its office in Chicago, and was instrumental in having the plaintiff bid upon the building of these bridges, for which the plaintiff had prior to that time agreed to pay the Supply Company two hundred dollars. After receiving the bid, or proposition, of September 28th, Mr. Murran and Mr. Upson, president, secretary and general manager of the defendant went to Chicago for the purpose of seeing W. W. Curtis, representative of the plaintiff, and through a communication from a Mr. Kadish, a representative of the Supply Company, met Curtis at a hotel in Chicago and talked over the proposition that had been made by the plaintiff to the defendant for the building of these bridges, and in that conversation the president and secretary of the defendant told Mr. Curtis that the proposition made by the plaintiff was satisfactory but they preferred to have the plaintiff make the contract with the Supply Company, without explaining why, and Mr. Curtis told them that this would be satisfactory to him if they would guarantee the payment, that he did not think the Supply Company financially responsible. On October 4, 1909, the plaintiff submitted to the Supply Company a proposition for the building of these three bridges, giving the specifications and the details with reference to the work to be done by the plaintiff, for which the Supply Company was to pay plaintiff eighty-six hundred dollars ($8,600.00), fifty per cent of the contract price of each span to be paid on the delivery of the material at Oblong, Illinois, and the balance on the completion of the work, and this proposition contained this clause: “We are to be given satisfactory assurance of your ability to pay for this work in accordance with the contract.” On October 15, 1909, the Supply Company forwarded to plaintiff an acceptance of its proposition, which acceptance contained the following clause, among others, “We take pleasure in handing you herewith the guaranty of the Oil Belt Traction Company of Oblong, Illinois, for the payments as provided in the agreement above referred to.” “Payments for this work will be made direct from this office upon advice of the Oil Belt Traction Company that such material has been delivered at Oblong, Illinois;” and this acceptance was signed Empire Railway Supply Company, J. W. Kadish, treasurer; and in this acceptance of the Supply Company was inclosed the following letter:

“Oblong, Ill., Oct. 6, 1909.
The Toledo-Massillon Bridge Co.,
Chicago, Ill..
Gentlemen :—With reference to the contract for the one 78½ ft. through plate girder bridge and the two 80 ft. through plate girder spans, made between your Company and the Empire Railway Supply Company, and in conformity with our verbal agreement with your Mr. Curtis a few days since in Chicago, we beg to advise that the Oil Belt Traction Company hereby guarantees the payment for the same. We understand this to be fifty per cent upon delivery of material at this point and the remaining fifty per cent upon completion of the work.
Trusting this will be satisfactory and that you will proceed at once with the work, we beg to remain,
Very truly yours,
Geo. P. Murrin,
President.
N. L. Upson,
Secretary.
Oil Belt Traction Company Seal.”

It also appears from the evidence that afterward the name of the Toledo-Massillon Bridge Company was changed to Toledo Bridge and Crane Company. This contract was accepted by the plaintiff in Toledo, Ohio, and in pursuance thereof the plaintiff proceeded to. furnish the material and deliver it at Oblong, in accordance with the contract and actually constructed one of the bridges. The plaintiff employed the Ferro Construction Company to erect these bridges at a cost of $1,640.00. After the erection of the first bridge there was much difficulty encountered in putting up the other two bridges, in consequence of the "defendant not being ready to have them constructed. Repeated demands were made by the plaintiff to build the bridges which resulted in a proposition to deduct two-thirds of the $1,640 from the contract price and allow the Supply Company, or defendant, to build the other two bridges. This, however, is not very clear from the testimony but has been treated by counsel for appellant and appellee in their argument, statements and computations as having been agreed to, and in their statements the amount of $1,093.33 is presented as having been deducted from the contract price. The defendant also demands $77.00 as demurrage that it claims to have paid for the plaintiff and should be deducted. There was also $58.00 that plaintiff claims as extra work in unloading cars on account of the fault of the defendant. Counsel for defendant in his argument insists that the court allowed plaintiff this $58.00 and that was all that it could ask for.

It further appears from the evidence that the defendant entered into a contract with the Supply Company for the building of these bridges at the price of $10,500.00. Counsel for defendant in his brief states the account as follows:

For three bridges as per contract...........$8,600.00

For unloading two bridges (extra).......... 58.00

Total ................................$8,658.00

Cash paid for bridges..............$7,183.34

Demurrage....................... 77.00

Relief from erecting two bridges... 1,093.33

Total........................$8,353.67 $8,658.00

8,353.67

$ 304.33

This includes a payment made by defendant to the plaintiff of $1,383.34 and the remainder of it was paid by the defendant to the Supply Company but the Supply Company has not paid the plaintiff the amount due it upon this contract by about fourteen hundred dollars.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John A. Tolman Co. v. Rice
45 N.E. 496 (Illinois Supreme Court, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
173 Ill. App. 298, 1912 Ill. App. LEXIS 414, Counsel Stack Legal Research, https://law.counselstack.com/opinion/toledo-bridge-and-crane-co-v-oil-belt-traction-co-illappct-1912.