Tolbert v. Ohio Department of Transportation

172 F.3d 934
CourtCourt of Appeals for the Sixth Circuit
DecidedApril 16, 1999
DocketNo. 98-3299
StatusPublished
Cited by29 cases

This text of 172 F.3d 934 (Tolbert v. Ohio Department of Transportation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tolbert v. Ohio Department of Transportation, 172 F.3d 934 (6th Cir. 1999).

Opinion

GILMAN, Circuit Judge.

Plaintiffs, who are residents of the Cher-rywood apartment complex in Toledo, Ohio and predominantly African-American (the “Cherrywood residents”), claim that the Ohio Department of Transportation (“ODOT”), its director Jerry Wray, and the City of Toledo discriminated against them on the basis of race in allocating sound barriers along highways in Toledo. The district court ruled that their claims were barred by the applicable two-year statutes of limitation, finding that the Cherrywood residents’ cause of action had accrued in 1984 when ODOT approved a highway-construction plan that did not include sound barriers near Cherrywood.

The complaint, however, challenges the discriminatory allocation of sound barriers, not the initial failure of ODOT to provide such barriers near Cherrywood. As a result, the Cherrywood residents’ cause of action did not accrue until (1) the request for sound barriers in their largely African-American neighborhood had been denied, and (2) they knew or had reason to know that ODOT was in the process of providing sound barriers in a similarly-situated white neighborhood. We therefore REVERSE the judgment of the district court and REMAND the case for further proceedings consistent with this opinion.

I. BACKGROUND

A. The Plaintiffs

The Plaintiffs are residents of Cherry-wood. According to a 1990 census, 84% of the Cherrywood residents are African-American. Over 71% of the households in Cherrywood’s census tract had annual incomes of less than $10,000.

B. The Parkway

The Buckeye Basin Greenbelt Parkway (the “Parkway”) is a federally-funded highway currently under construction in Toledo, Ohio. The northbound lanes of the Parkway are located approximately 75 to 100 feet from Cherrywood. Planning for the Parkway began in the 1970s. ODOT claims that it conducted 17 public meetings to discuss the Parkway project between 1979 and 1982, but the record is devoid of information about the notification procedures except for one of the public meetings in 1982. The Cherrywood residents allege that ODOT did not conduct any meetings specifically with them.

In the late 1970s and early 1980s, the Federal Highway Administration (“FHWA”) conducted an initial noise analysis for the Parkway project. One such analysis indicated that the existing noise level at Cherrywood was approximately 79 decibels. The Cherrywood residents allege that the current specifications for the Parkway will elevate that noise level to 90 decibels, an increase of over 10 decibels. In 1982, the FHWA incorporated its noise analysis into an Environmental Impact Statement (“EIS”). The EIS recommended against building sound barriers around the Parkway because that would be impractical “due to the influence of traffic generating noise from Cherry Street and to the industrial background noise from the adjacent area.” In 1984, the FHWA approved the EIS. Between 1984 and 1995, the FHWA made various changes to the Parkway plans. On January 19, 1995, the FWHA determined that because the changes were not “substantial,” no supplemental EIS was necessary.

Construction of the Parkway began in 1996, and is ongoing. In 1996, the Cherry-wood residents requested that ODOT reopen the question of whether to provide noise-mitigation measures on the Parkway project. ODOT officials refused to do so, [937]*937stating that the Cherrywood residents could have attended the various public meetings in the 1980s.

C. The 1-75 Expansion

ODOT also made plans to widen Interstate 75 in Toledo in the 1980s. • According to the 1990 census, 86% of the residents in the 18 census blocks immediately adjacent to the 1-75 widening project (known as “Point Place”) are Caucasian. Sixty percent of the households in the five adjacent census tracts had annual incomes of over $25,000.

According to a 1983 ODOT noise analysis, the widening of 1-75 would result in noise levels between 70 and 82 decibels in the adjacent neighborhoods, creating an increase of no more than three decibels above the original sound level. The noise analysis recommended against the construction of sound barriers for the 1-75 widening.

ODOT has nonetheless since decided to construct sound barriers adjacent to 1-75. The Cherrywood residents allege that the City of Toledo was involved in this decision. Construction commenced in the summer of 1996.

D. Procedural Background

The Cherrywood residents filed a six-count complaint in the United States District Court for the Northern District of Ohio on August 26, 1997. It named ODOT, its director Jerry Wray, and the City of Toledo as defendants. The complaint states in pertinent part as follows:

Discrimination Against Plaintiff Class
19.In analyzing the noise impact of the Parkway, defendants, inter alia, incorrectly measured existing noise levels, failed to evaluate meaningfully noise abatement measures, and failed to take into consideration the views of the impacted residents in violation of 23 C.F.R. § 772.
20. In designing, approving, and constructing the Parkway, defendants failed to assess whether the allocation of sound mitigation measures and consideration of alternative Parkway alignments complied with Title VI, Title VIII, and other civil rights requirements.
21. Defendants failed to provide plaintiffs, the African-American population residing in the Cherrywood apartments and nearby residential properties, with sound mitigation measures or other design alternatives to lessen the noise impact of the Parkway. Plaintiffs allege that defendants’ discriminatory refusal to approve sound mitigation measures or other design alternatives and defendants’ discriminatory allocation of mitigation measures between Point Place and Cherrywood disproportionately imposes environmental and health burdens of freeway construction on the basis of race.
22. Defendants do not advance any reason rising to the level of necessity, to justify: (1) the absence of noise mitigation measures or other design alternatives at the southwestern terminus of the Parkway or (2) the disparity in the allocation of mitigation measures between predominantly white areas along 1-75 and predominantly African-American area surrounding Cherrywood apartments.

The complaint then alleges that the above facts constitute violations of (1) Title VI of the Civil Rights Act of 1964, 42 U.S.C. § 2000d; (2) U.S. Department of Transportation regulations implementing Title VI; (3) The Fair Housing Act, 42 U.S.C. § 3601; (4) The Civil Rights Act of 1870, 42 U.S.C. § 1981; (5) The Civil Rights Act of 1866, 42 U.S.C. § 1982; and (6) The Civil Rights Act of 1871, 42 U.S.C. § 1983.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
172 F.3d 934, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tolbert-v-ohio-department-of-transportation-ca6-1999.