Tocci Building Corp. v. Commonwealth Insurance

22 Mass. L. Rptr. 522
CourtMassachusetts Superior Court
DecidedApril 23, 2007
DocketNo. 0202261
StatusPublished

This text of 22 Mass. L. Rptr. 522 (Tocci Building Corp. v. Commonwealth Insurance) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tocci Building Corp. v. Commonwealth Insurance, 22 Mass. L. Rptr. 522 (Mass. Ct. App. 2007).

Opinion

Hopkins, Merita A., J.

INTRODUCTION

This is an insurance policy coverage dispute between plaintiffs Tocci Building Corporation (“Tocci”) and Candlewood Hotel Company (“Candlewood”) and defendant Commonwealth Insurance Company (“Commonwealth”). The plaintiffs bring counts for breach of contract (Count I), declaratory judgment (Count II), and damages under G.L.c. 93A (Count III). Both parties move for summary judgment. For the reasons set forth below, defendant Commonwealth’s motion for summary judgment is ALLOWED, and the plaintiffs Tocci and Candlewood’s cross motion for summary judgment is DENIED.

BACKGROUND

I. Damage to Retaining Wall

Plaintiff Candlewood Hotel Company (“Candle-wood”) had engaged plaintiff Tocci Building Corporation (“Tocci”) to constuct a hotel in Burlington, Massachusetts. The contract required that Tocci construct a 1,200-foot-long retaining wall separating elevated portions of the site from the hotel’s parking lot. Tocci hired subcontractors to design and construct the wall. On June 6, 2000, after the completion of the retaining wall but before completion of the hotel, a rainstorm occurred wherein more than four inches of rain fell on the property. Rainwater flowed from the parking lot (where storm drains had yet to be built) into the earth behind the retaining wall. This weakened the retaining wall, causing a 100-foot portion of it to collapse. The remainder of the retaining wall did not sustain any physical loss or damage.

On June 8, 2000, an inspector from the Town of Burlington (“Town”) deemed the retaining wall unsafe due to its failure two days prior and issued a stop work order. Thereafter, the Town hired structural and geotechnical engineers to assess whether the retaining wall’s design and construction were structurally adequate. In early August 2000, the Town gave Tocci permission to repair the 100-foot portion damaged in the storm. Those repairs were substantially completed by August 14, 2000; however, Tocci had to await Town approval before it could complete grouting. Tocci did not receive such approval until November. On August 15, 2000, the Town informed Tocci that the undamaged portion of the retaining wall, as constructed, was unsafe and did not conform to the plan submitted to and approved by the Town. It ordered Tocci to rebuild accordingly. Tocci completed work on the rest of the retaining wall in November 2000. The hotel opened shortly thereafter, 110 days behind schedule.

[523]*523II. Candlewood’s Insurance Claim2

Candlewood insured the Burlington property under a policy with Commonwealth (“the policy”), and following the storm, it submitted a claim for its losses arising from the flood. Commonwealth retained an independent adjuster, who investigated the claim with the assistance of an engineer. By letter dated April 25, 2001, Commonwealth informed Candlewood that it would cover the costs of repairing the damaged portion of the retaining wall ($11,950.00), cleanup and public safety expenses ($56,500), and two weeks of business interruption ($14,375.00). The subtotal was $82,825.00. After subtracting the $25,000.00 deductible, Commonwealth paid Candlewood $57,825.00. It tendered payment on June 24, 2003, along with a letter, which stated, in part;

It is Commonwealth’s position that the sum tendered herewith constitutes the maximum amount recoverable under the policy, and that no coverage exists for any and all other claims or portions of claims against the policy in respect of the Incident . . . With respect to claims for insurance coverage under the Commonwealth policy and arising out of the Incident other than those claims addressed by this payment, whether asserted in the Litigation or not, Commonwealth reserves all of its rights under the policy and otherwise.

(Exhibit F to Commonwealth’s Motion for Summary Judgment.) Commonwealth asserts that its letter memorializes a reservation of rights agreed upon by the parties. The plaintiffs not only dispute the existence of such an agreement, but also contend that Commonwealth’s letter constituted an admission of coverage.

The plaintiffs filed the present action against Commonwealth on May 30, 2002.3 They claim that Commonwealth failed to comply with the terms of the policy by (1) failing to cover the costs incurred in bringing the retaining wall into compliance with the Town’s building code, and (2) compensating the plaintiffs for only two weeks of business interruption rather than the entire 110-day delay in opening the hotel.

DISCUSSION

I. Insurance Policy’s Terms

The policy covered the time period of August 1, 1999, through November 1, 2000. Candlewood had coverage through Commonwealth’s basic policy, entitled the “Difference in Conditions” form, and through additional coverage provided in attached Endorsements. Portions of the policy relevant to the present dispute are as follows:

a. Interests Insured

The Differences in Conditions form, paragraph 3(a), provides coverage for:

... all buildings and other structures as described in forms and or endorsements attached hereto and business personal property, owned by the Insured usual to the occupancy of the Insured, all while on premises, owned, leased or occupied by the Insured and including interests in improvements and betterments in buildings occupied but not owned by the Insured. Coverage is extended to newly acquired property and property under the course of construction. (Page 0025.)4

Candlewood opted to insure additional property described in attached Endorsements. Relevant to the present dispute is Endorsement 1, which provides, “As respects the Differences in Conditions form, Item 3.a is deleted in its entirety and amended to read as follows.” It then enumerates categories of items insured under the policy, such as outdoor furniture, drains, foundations, and parking lots. It also lists “retaining walls.” (Page 0019A.)

b. Perils Insured Against

Paragraph 1 of the Difference in Conditions form provides, “This Policy insures against all risk of direct physical loss or damage to the insured property from any external cause during the period of this policy except as hereinafter excluded.” (Page 0025.)

An attached Endorsement specifically includes flood damage as an insured-against peril. (Page 0042.) The liability is limited to $5,000,000.00 per year, with a deductible of $25,000.00.

The policy also contains a Building Laws Endorsement, which provides coverage for “loss occasioned by the enforcement of any state or municipal law or ordinance regulating the construction or repair of buildings and in force at the time such loss occurs, which necessitates the demolition of any portion of the insured building(s) not damaged by the peril(s) insured against.” (Page 0050.) This Endorsement is subject to liability limits, none of which are relevant to the present dispute.

An endorsement entitled “Contingent Liability from Operation of Building Laws Endorsement — Demolition and Increased Time to Rebuild” (“the Cost of Construction Endorsement”),5 provides, in relevant part:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hanover New England Insurance v. Smith
621 N.E.2d 382 (Massachusetts Appeals Court, 1993)
Boston Symphony Orchestra, Inc. v. Commercial Union Insurance
545 N.E.2d 1156 (Massachusetts Supreme Judicial Court, 1989)
Hakim v. Massachusetts Insurers' Insolvency Fund
424 Mass. 275 (Massachusetts Supreme Judicial Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
22 Mass. L. Rptr. 522, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tocci-building-corp-v-commonwealth-insurance-masssuperct-2007.