Ætna Indemnity Co. v. Ladd

135 F. 636, 68 C.C.A. 274, 1905 U.S. App. LEXIS 4354
CourtCourt of Appeals for the Ninth Circuit
DecidedFebruary 6, 1905
DocketNo. 1,106
StatusPublished
Cited by6 cases

This text of 135 F. 636 (Ætna Indemnity Co. v. Ladd) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ætna Indemnity Co. v. Ladd, 135 F. 636, 68 C.C.A. 274, 1905 U.S. App. LEXIS 4354 (9th Cir. 1905).

Opinion

GILBERT, Circuit Judge,

after stating the case as above, delivered the opinion of the court.

It is assigned as, ejror that the trial, court permitted the witness Clemens to testify that the money received from the defendants in error was- paid out for the benefit of the plaintiff in error on contracts for which it had become surety, and which had been assigned to it. It is urged that the contracts had been assigned merely as security- for an advancement of $6,000 by Sudden & Christensen to thé Hardy Shipbuilding Company, and for no other purpose. It is true that the assignment, in its terms, recites that it was made as security for the payment of said sum, of $6,,000. But from and after its date, the evidence shows, it was, in fact treated by both the parties thereto as an absolute assignment for the benefit and protection of the plaintiff in error. Clemens & O’Bryan, the general agents, of the plaintiff in error, had general authority to require any contractor for which it became surety to transfer to, it his plant whenever he became unable to carry on the contract, in order that the surety company might use the same in the prosecution of the contract to. completion. On March 6, 1902, the plaintiff in. error had written to its general agents, as follows:

“When executing bonds of this character, you must always bear in mind that the Surety Company signing such a bond becomes a co-contractor, and in the event the contractor defaults on any part of the work, the company must step in and complete it or else stand the loss.”

On April 25, 1902, it had written its general agents in reference to another bond as follows:

■ “At any time should you perceive indication that the work is not progressing in a satisfactory manner, we shall rely on you to take immediate steps to protect our interests.”

[643]*643On the same date, in reference to another bond, it had written:

“If, at any time, there should be an indication that the work Is not progressing to the satisfaction of the obligee, kindly take immediate steps to safeguard our interest.”

On June 16, 1902, it had directed its agents to take whatever action may be necessary in the premises “to save us from any ultimate loss.” There were other communications of a similar nature, all tending to show that the plaintiff in error at all times had in contemplation the contingency of assuming the completion of any of the contracts upon which it was surety, whenever it became necessary to do so for its own protection, and that it looked to its general agents to act for it in that capacity. Evidence went to the jury tending to show that the home office was advised of the actions of its general agents in •carrying on and completing the contracts. Thus on May 27th the agents wrote, notifying the company of the advance made by Sudden & Christensen and the assignment of the contracts. They added:

“Until these contracts are finished, all money of the firm is deposited in the name of the Hardy Shipbuilding Company and the BStna Indemnity Company, and all checks are signed by Mr. Hardy, president of the Shipbuilding Company, and countersigned by our Tacoma agent”

On July 7th they wrote:

“We now have the record title to the whole plant, and have practically made arrangements to sell the plant, together with our contracts. * * * In order to get the Kingsford Foundry & Machine Works to release some of the machinery to us, which had been shipped the Hardy Shipbuilding Company, we told them we would pay the freight as we had taken over the contracts and moneys on hand.”

On August 4th they wrote:

“What we meant to say in our last letter was that we would complete this contract to the best of our ability.”

On August 5th they wrote:

“But the thing that troubles us is that we will have to put up some more money in order to carry the work along as everything we buy we seem to have to pay cash for, and of course we have to keep the labor paid up.”

During all this time no answer was made by the plaintiff in error disaffirming any of the acts of its general agents. It is true that on or about August 21st it protested its general agent’s draft of $5,000 to be used on the contracts, but on August 23d it explained its action in so doing by telegraphing to its agents as follows:

“Sufficient money appears to be left to complete Hardy contracts. You must arrange for advances from the owners.”

This answer, so far from repudiating the action of the general agents in assuming the contract, was clearly a ratification thereof, since the only reason assigned for not advancing the money was that it was unnecessary to do so. On August 25th the agents telegraphed to the plaintiff in error as follows:

“Ladds Bank advanced money for material and labor. Owners scared, won’t pay anything. Bank insists immediate payment Must shut down works.”

[644]*644To this the plaintiff in error replied:

“Prorate payment due among materialmen, authorizing owners to pay them direct.”

On August 26th the plaintiff in error wrote the general agents as follows:

“We will be pleased to have you forward a report showing just what portion of the work has been completed, together with the payments made, also the date of the letter and advice as to whether such payments have been properly applied in settlement of bills for labor and materials.”

Further correspondence followed, but in none of it did the plaintiff in error deny the authority of its agents to assume the completion of the contracts. We find no error, therefore, in the ruling of the court admitting in evidence the testimony so objected to.

It is contended that the court erred in permitting the witness-Clemens to answer the question, “By whom was the boat Georgia completed?” to which he answered, “The boat was completed by Mr. Seeley, trustee for the ¿Etna Indemnity Company, as we believe.” It is urged that, in so answering, the witness stated a legal conclusion, and that the court should have sustained the motion of defendant in error to strike out the answer. The question so propounded did not necessarily call for an answer stating a legal conclusion. The witness had previously testified that Clemens & O’Bryan had been carrying on the work on these contracts, and that “Mr. Seeley, trustee, had been in charge of the plant at Tacoma.” In answering that the work was completed “by Mr. Seeley, trustee for the ¿Etna Indemnity Company, as we believe,” he was but stating his understanding of the capacity in which he and his partners had acted in completing the contract. If it was error to deny the motion to exclude the testimony, it was harmless error,, which could not have prejudiced the plaintiff in error.

Of similar import is the assignment that the court erred in permitting the witness Clemens to testify in answer to the question on whose behalf the additional sum of $3,000 was obtained from the defendants in error, to answer, “¿Etna Indemnity Company.” It was proper for the witness to testify in what capacity he was acting in obtaining this money, for whom he acted when he borrowed it, and his understanding of the relation he bore to the transaction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lamb v. General Associates, Inc.
374 P.2d 677 (Washington Supreme Court, 1962)
Lyons Milling Co. v. Goffe & Carkener, Inc.
46 F.2d 241 (Tenth Circuit, 1931)
Daniel v. Pappas
16 F.2d 880 (Eighth Circuit, 1926)
Burch v. Southern Pacific Co.
32 Nev. 75 (Nevada Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
135 F. 636, 68 C.C.A. 274, 1905 U.S. App. LEXIS 4354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tna-indemnity-co-v-ladd-ca9-1905.