Titan Trucking v. American Home Assurance & Beers Construction

CourtCourt of Appeals of Tennessee
DecidedMarch 18, 2003
DocketM2002-01747-COA-R3-CV
StatusPublished

This text of Titan Trucking v. American Home Assurance & Beers Construction (Titan Trucking v. American Home Assurance & Beers Construction) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Titan Trucking v. American Home Assurance & Beers Construction, (Tenn. Ct. App. 2003).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE March 18, 2003 Session

TITAN TRUCKING, LLC V. AMERICAN HOME ASSURANCE COMPANY AND BEERS CONSTRUCTION COMPANY, INC.

Appeal from the Chancery Court for Rutherford County No. 01-2279CV Robert E. Corlew, III, Chancellor

No. M2002-01747-COA-R3-CV - Filed September 11, 2003

This case involves the interpretation of a performance payment bond. The city contracted with a construction company to make improvements to a public project. The construction company entered into a performance payment bond with the surety to protect the city. The public project required excavation of soil, and the contract allowed the construction company to either relocate the dirt or remove it. A third party purchased the dirt. The purchaser’s subcontractor hired a trucking company to move the dirt for the purchaser. The trucking company was never paid for its services. The trucking company sued the construction company and the surety under the terms of the performance payment bond. The trial court granted summary judgment in favor of the construction company and the surety. The trucking company appeals. We affirm, finding that the services provided by the trucking company were not covered under the terms of the performance payment bond because the construction company was not obligated to pay the third party purchaser for removal of the dirt.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed

HOLLY M. KIRBY, J., delivered the opinion of the court, in which W. FRANK CRAWFORD , P.J., W.S., and ALAN E. HIGHERS, J., joined.

David M. Smythe, Nashville, Tennessee, for appellant, Titan Trucking, LLC.

John P. Branham, John D. Wood, and Samuel L. Jackson, Brentwood, Tennessee, and Calvin T. Vick, Jr., Atlanta, Georgia, for appellants, American Home Assurance Company and Beers Construction Company, Inc. OPINION

In July 1997, Defendant/Appellee Beers Construction Company, Inc. (“Beers”) entered into a contract (“General Contract”) with the City of Murfreesboro to make improvements at the Sinking Creek Wastewater Project (“Project”) in Rutherford County, Tennessee. The General Contract required Beers to “furnish a performance bond . . . as security for the payment of all persons performing labor on the project under [the General Contract] and furnishing materials in connection with [the General Contract]. . . .” Beers, the principal, and Defendant/Appellee American Home Assurance Company (“American”),1 the surety, entered into a performance payment bond (“Bond”) on July 28, 1997 for $32,721,692. The Bond guaranteed “payment to all persons, firms, subcontractors, and corporations furnishing materials for or performing labor in the prosecution of the work [under the General Contract] . . . .”

Work on the Project required excavation of soil. Under the General Contract, Beers was permitted to either relocate the excavated material (dirt) to another area on the Project site, or remove the dirt from the site. A representative of Ed Boyd Excavating, Inc. (“Ed Boyd”) approached Beers’s Project manager, who agreed to sell some of the excavated materials to Ed Boyd at $10 per load. Beers invoiced Ed Boyd for $15,450 for dirt removed from the Project site. Ed Boyd contracted with Little Joe’s Construction Company (“Little Joe’s”) to transport the dirt from the Project site. Plaintiff/Appellant Titan Trucking, LLC (“Titan Trucking”) contracted with Little Joe’s to provide the trucking services. Titan Trucking was not paid for $37,415.25 of the services it provided.

Titan Trucking filed a notice of claim with Beers under the Bond, pursuant to the requirements of section 12-4-205 of the Tennessee Code Annotated. Beers’s servicing agent requested a proof of claim, which Titan Trucking provided. The monies owed to Titan Trucking remained unpaid. Titan Trucking then filed a “Verified Complaint to Enforce Bond Claim” in the Chancery Court of Rutherford County. Titan Trucking asserted that it had a contract with Little Joe’s, that Little Joe’s was a subcontractor to Ed Boyd, and that Ed Boyd “had a direct contract with the Defendant Beers to provide the trucks for removal of soil and other materials from this public project.” On this basis, Titan Trucking sought a judgment against Beers for the monies owed, pursuant to the performance bond.

Titan Trucking moved for summary judgment, arguing that Titan Trucking was entitled to judgment as a matter of law because Ed Boyd was Beers’s subcontractor, and because Titan Trucking provided labor to discharge Beers’s obligations under the General Contract. Consequently, Titan Trucking argued that it was entitled to payment under the Bond, which guaranteed payment to entities performing labor in prosecution of the General Contract. Beers opposed Titan Trucking’s motion for summary judgment and filed a cross-motion for summary judgment. Beers asserted that Titan Trucking essentially alleged that it was a third-party beneficiary to the Bond, and as such, Titan Trucking had the burden of proving that the parties to the Bond intended to have the Bond operate in favor of Titan Trucking. Beers maintained that Titan Trucking was not a third-party beneficiary

1 Beers and American will be referred to collectively as “Beers,” unless the facts necessitate otherwise.

-2- under the Bond because it did not perform work under the General Contract, but rather, merely moved dirt that Ed Boyd purchased from Beers for use on Ed Boyd’s unrelated project. Titan Trucking’s response to Beers’s cross-motion for summary judgment insisted that Titan Trucking had performed labor and provided machinery to complete work that Beers was obligated to perform under the General Contract. Thus, Titan Trucking argued, it was covered under the Bond. Titan Trucking argued that whether it was a third-party beneficiary to the Bond was irrelevant because the plain terms of the Bond were controlling.

After a hearing,2 the trial court issued its ruling in the form of a letter addressed to all parties involved. Analyzing the facts under a theory of unjust enrichment, the trial court found that Beers was not unjustly enriched, and therefore held that “Beers had no contractual obligation with Titan [Trucking], and thus owed nothing to Titan [Trucking]. Because Beers owed nothing, the insurance company employed to guarantee payments owed by Beers . . . owes nothing.” The trial judge further found that “the obligation of the insurance carrier is only to pay those obligations which Beers incurred and for which it did not pay to those sub-contractors who reasonably anticipated payment from Beers.” Because Beers did not agree to pay Titan Trucking, and because “Titan [Trucking] could not justifiably look to Beers for payment,” the trial court found that American had no obligation to remunerate Titan Trucking. Finally, the trial court found that the language of the Bond was substantially similar to a Tennessee statute permitting a lien on non-governmental construction projects. Because Titan Trucking would not have been entitled to a statutory lien under the circumstances, the trial judge held that Titan Trucking was likewise precluded from seeking compensation from Beers under the Bond. The trial court issued an order reflecting the rulings in its letter. From this order, Titan Trucking appeals.

On appeal, Titan Trucking argues that the trial court erred in granting Beers’s cross-motion for summary judgment because the trial judge had found that Titan Trucking’s services satisfied a portion of Beers’s obligations under the General Contract. Titan Trucking asserts that the trial court improperly limited coverage under the Bond, and it erred in finding that Titan Trucking was required to establish that it would be entitled to a statutory lien in order to recover under the Bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carvell v. Bottoms
900 S.W.2d 23 (Tennessee Supreme Court, 1995)
Planters Gin Co. v. Federal Compress & Warehouse Co.
78 S.W.3d 885 (Tennessee Supreme Court, 2002)
Johnson v. Johnson
37 S.W.3d 892 (Tennessee Supreme Court, 2001)
Bain v. Wells
936 S.W.2d 618 (Tennessee Supreme Court, 1997)
Warren v. Estate of Kirk
954 S.W.2d 722 (Tennessee Supreme Court, 1997)
Guiliano v. Cleo, Inc.
995 S.W.2d 88 (Tennessee Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Titan Trucking v. American Home Assurance & Beers Construction, Counsel Stack Legal Research, https://law.counselstack.com/opinion/titan-trucking-v-american-home-assurance-beers-con-tennctapp-2003.