Titan Stone, Tile & Masonry, Inc. v. Hunt Construction Group, Inc.

394 F. App'x 862
CourtCourt of Appeals for the Third Circuit
DecidedSeptember 20, 2010
Docket08-2046, 08-2850, 08-3103
StatusUnpublished

This text of 394 F. App'x 862 (Titan Stone, Tile & Masonry, Inc. v. Hunt Construction Group, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Titan Stone, Tile & Masonry, Inc. v. Hunt Construction Group, Inc., 394 F. App'x 862 (3d Cir. 2010).

Opinion

OPINION OF THE COURT

RENDELL, Circuit Judge.

Titan Stone, Tile and Masonry, Inc. (“Titan”) and International Fidelity Insurance Company (“IFIC”) appeal the District Court’s Judgment in favor of Hunt Construction Group, Inc. (“Hunt”), in this breach of contract action. We will affirm.

BACKGROUND

Because we write for the parties who are familiar with the factual context and procedural history of this case, we recite only the facts that are relevant to our analysis. In 2003, the College of New Jersey awarded Hunt a general contract to build a new library. Hunt subcontracted with Titan to manufacture and install the wall system for the project (the “Agreement”) and IFIC issued a performance bond to cover Titan’s work under the subcontract. After a series of project delays, Hunt terminated its contract with Titan. In response, Titan brought claims alleging that Hunt materially breached the Agreement by terminating Titan without cause and by failing to pay Titan for the work performed. Hunt counterclaimed for the cost of correcting and completing Titan’s unfinished work, and for the cost of delays. Hunt also filed a third party complaint against IFIC based on its issuance of the surety bond to Titan. On the basis of extensive submissions by the parties and evidence introduced at trial, the District Court found Titan and IFIC jointly and severally liable for breach of the contract and awarded Hunt attorneys’ fees against Titan. The Court denied Hunt’s motion for attorneys’ fees and costs against IFIC, however, and dismissed Titan’s additional claims.

On appeal, Titan and IFIC assert several claims: (1) the District Court erred in finding that Hunt’s termination of Titan for cause was appropriate; (2) the District Court erred in finding IFIC liable to Hunt under the performance bond for damages beyond the cost of completing Titan’s work; (3) the District Court erred in failing to strike the testimony of Hunt’s experts and in relying upon said testimony to support its findings; (4) if the District *864 Court’s finding that Titan was terminated for cause is reversed, the termination was one for convenience and Titan is entitled to damages; (5) if the District Court’s finding is affirmed, the damage calculation must be modified. Concurrently, IFIC filed an appeal alleging that (1) Hunt failed to introduce evidence of attorneys’ fees and costs at trial; (2) the award of attorneys’ fees was unreasonable, unnecessary, and excessive; (3) the attorneys’ fees were disproportionate to the damages recovered; and (4) the costs and expenses awarded were unreasonable, unnecessary and excessive. Finally, Hunt cross-appealed, alleging that IFIC’s performance bond incorporated Titan’s subcontract by reference and the District Court erred by not assessing attorneys’ fees against IFIC. We will affirm the District Court’s Judgment.

DISCUSSION

The District Court exercised diversity jurisdiction pursuant to 28 U.S.C. § 1332(a)(3) and we have jurisdiction pursuant to 28 U.S.C. § 1291 1

I. Titan and IFIC’s Appeal

We review the District Court’s factual findings for clear error. Fed.R.Civ.P. 52(a)(6). The District Court ruled that Hunt properly terminated Titan for cause because Titan bore responsibility for the project delays. The District Court concluded that Titan’s diversion of a shipment to its facility instead of to the project site — and failure to respond to Hunt’s requests to release the material — warranted termination under § 30 of the Agreement. 2 Further, the District Court found that Hunt’s decision not to notify Titan of its intent to replace Titan’s mason did not breach the implied covenant of good faith and fair dealing as Hunt had no obligation under the Agreement to inform Titan of its considerations. We will find that the District Court did not clearly err in determining that terminating Titan for cause was warranted. Accordingly, we need not address Titan’s assertion that the termination was for convenience and it is entitled to damages.

*865 The District Court also found that, under § 30.1(5) of the Agreement, Hunt was entitled to mitigation costs stemming from delays caused by Titan, plus an additional 20% of costs to cover overhead and profit. The District Court conducted a detailed review of the backcharges detailed in the parties’ submissions and introduced at trial, and found that the markup for backc-harges directly resulted from Titan’s delayed and failed performance. At the same time, the court disallowed those backcharges not supported by credible evidence in the record. The court further modified the markup calculation used by Hunt, finding that the requested 21% markup was unsupported by the language of the agreement. We conclude that there is sufficient evidence in the record to support the District Court’s damage calculation against Titan.

In the same vein, the District Court found IFIC liable to Hunt pursuant to the surety bond for damages beyond the cost of completion owed by Titan to Hunt. On appeal, Titan and IFIC claim that the language of the Agreement does not expose IFIC to liability for delay damages, acceleration costs, or other damages beyond the cost of completing the subcontract work. We exercise plenary review over questions of contract law. See In re Cendant Corp. Prides Litig., 233 F.3d 188, 193 (3d Cir.2000). Under controlling New Jersey law, when a surety bond incorporates a subcontract by reference, “the bond and the contract must be considered as one integrated document.” See Eagle Fire Prot. Corp. v. First Indem. Of Am. Ins. Co., 145 N.J. 345, 678 A.2d 699, 705 (1996). The District Court concluded that the clear language of the surety bond, which incorporated the subcontract agreement between Hunt and Titan by reference, provided that IFIC was liable for Titan’s default once provided with reasonable notice. Accordingly, the District Court did not err as a matter of law.

Finally, Titan and IFIC aver error by the District Court in declining to set aside damages and liability findings that were based on Hunt’s allegedly manufactured expert testimony. We review a district court’s finding that there was no fraud on the court for abuse of discretion. In re Prudential Ins. Co. Am. Sales Practice Litig. Agent Actions, 278 F.3d 175, 181 (3d Cir.2002). After the trial, Titan learned of Hunt’s billings for developing and revising the expert reports, and claimed that Hunt’s lawyers had substantive input into Hunt’s expert’s testimony. Titan contends that Hunt’s time allocation demonstrates that the District Court’s findings relied heavily on unreliable or biased evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
394 F. App'x 862, Counsel Stack Legal Research, https://law.counselstack.com/opinion/titan-stone-tile-masonry-inc-v-hunt-construction-group-inc-ca3-2010.