Titan Custom Cabinet, Inc. v. Advance Contracting, Inc.

941 A.2d 547, 178 Md. App. 209, 2008 Md. App. LEXIS 11
CourtCourt of Special Appeals of Maryland
DecidedFebruary 7, 2008
Docket1957, Sept. Term, 2006
StatusPublished
Cited by5 cases

This text of 941 A.2d 547 (Titan Custom Cabinet, Inc. v. Advance Contracting, Inc.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Titan Custom Cabinet, Inc. v. Advance Contracting, Inc., 941 A.2d 547, 178 Md. App. 209, 2008 Md. App. LEXIS 11 (Md. Ct. App. 2008).

Opinion

*213 DAVIS, J.

Appellants, Titan Custom Cabinet and Johansson Corporation, appeal from the denial of a Motion for New Trial entered by the Circuit Court for Baltimore City (Ross, J.) on September 23, 2006. This appeal arises out of a tort claim, in which appellants allege that appellees, Advance Contracting, Inc. and Timothy Nickels, negligently repaired the roof of appellants’ premises, thereby clogging a roof drain that ultimately resulted in a flood of their premises.

On March 18, 2005, appellants filed suit against appellees in the Circuit Court for Baltimore City; appellees answered the Complaint on May 6, 2005. Appellees then filed a Third Party Complaint on August 9, 2005 against Crown Industrial Park (Crown), the owner of the property where appellants’ premises are located. Crown, however, was never served with the Third Party Complaint. On September 21, 2005, the Third Party Complaint was amended to add Wayne Kirchner, the property manager of Crown, as a defendant/third-party plaintiff. The Amended Third Party Complaint alleged that Kirchner’s negligence caused or contributed to the flood and, thus, he should be liable for any damages awarded to appellants. Kirchner filed his Answer on December 19, 2005.

Prior to the commencement of trial, appellants and appellees agreed to a jury trial on the issue of liability only. On August 30, 2006, a three-day trial began. At the conclusion of the third day, the jury returned a judgment in favor of appellees. Thereafter, appellants filed a timely Motion for New Trial and for Judgment Notwithstanding the Verdict. The Motion was denied on September 23, 2006. This timely appeal followed, presenting for this Court three questions, which we have rephrased as follows: 1

*214 1. Did the trial court err in permitting cross-examination of appellants’ witnesses with prior inconsistent statements made to their property insurance carrier and regarding their relationship with their property insurance carrier?
2. Did the trial court err in admitting certified copies of weather reports from Baltimore-Washington International Airport to show rain accumulations?
3. Did the trial court err in denying appellants’ Motion for New Trial?

We answer the questions presented in the negative and, accordingly, affirm the judgment of the trial judge.

FACTUAL BACKGROUND

Since 1997, appellants have occupied a commercial leasehold space at 56N of the Crown Industrial Park located on Eastern Avenue in Baltimore, Maryland. Crown is the owner and landlord of this property located within the Crown Industrial Park.

The building at 56N has an “A” frame roof, in which the center line of the roof runs parallel to the front of the building. There are other buildings in the industrial park which adjoin appellants’ premises on both sides and in the back. Consequently, when water falls on the back part of the roof, the water flows downward, until it accumulates at the bottom of the roof. As a result, two drains were installed in the low area of the back portion of the roof to allow any accumulated water to drain.

During the winter of 2001 to 2002, appellants’ premises, located below the low point on the back of the roof, began to leak. For the thirty years preceding this leak, Crown had not *215 experienced any roofing problems. After being notified of the leak, Kirchner told Anders Johansson, the president and principal of both appellants, that permanent repair work would need to be completed during the spring. In the meantime, a temporary system of troughs was put into place to catch the leaking water.

By mid-April of 2002, Crown had contracted with appellees to repair the roof. Thereafter, appellees installed an asphalt roof on the 56N building including the area near the drains. George Harris, one of appellees’ employees, supervised the job and performed much of the work. He testified that the drains on the roof were protected during the repair work with the use of “microsopic/KWRAPD,” a roofing industry product, commonly referred to as a “mop head or yard.” These protective products were placed over the drains to prevent clogging. One of the drains, however, was clogged prior to appellees beginning work. Appellees notified Crown of this clogged drain and were told by Crown that it would take care of the problem. On April 15, 2002, appellees completed the job without incident.

On May 2, 2002, after a heavy rainfall, Preston Fulk, one of appellants’ employees, reported water leaking along the back wall of the premises that had formed into a pool of water approximately eight inches deep. The employee began moving equipment and materials away from the water and called Johansson to inform him of the leak. Johansson instructed the employee to contact Kirchner. Kirchner went onto the roof of the building to inspect the leak. Near the back wall of the roof, Kirchner found water that was in areas eighteen inches deep. He also noticed that one of the drains was clogged and subsequently removed approximately two handfuls of debris, including one or two bottles from the drain. When the drain still would not allow water to flow, Kirchner used a piece of wooden molding in an attempt to free the drain. Shortly thereafter, the drain gave way and thousands of gallons of water poured into appellants’ premises.

*216 Kirehner helped remove the water from appellants’ premises. Afterward, he testified that he found a broken piece of pipe filled with gravel and a mixture of old and new tar. The following day, Johansson conducted his own investigation of the water damage. Johansson testified that, during his investigation, he observed an elbow joint pipe filled with a mixture of old and new tar lying on the floor below the roof drain in the ceiling. All testimony at trial indicated that the distinction between old and new tar is its color—old tar is gray and oxidized, while new tar is dark black on the outside.

During Johansson’s investigation, he took thirty to forty photographs of the scene of the damage and made important notes. Johansson, however, did not take a photograph of the elbow pipe. The elbow pipe and the notes regarding the elbow pipe were subsequently discarded during clean-up.

Three days after the flood, Johansson composed a letter to appellants’ insurer, The Hartford Fire Insurance Company (Hartford), regarding the loss and, in relevant part, wrote: In discussing this claim with ... (our agent) he noted that it is not up for subrogation.

You know as well as I know that the landlord’s appointed manager (Wayne) [Kirehner] poked the hole in the pipe that caused the damage.
I like that you subrogate this claim, since it will otherwise stay on my “insurability profile.”

A provision in the lease between Crown and appellants, however, barred a direct claim against Crown.

During the year following the flood, appellants made a claim under the property damage portion of their Commercial & Comprehensive General Liability (CGL) policy with Hartford.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Steamfitters Local Union No. 602 v. Erie Ins. Exch.
209 A.3d 158 (Court of Special Appeals of Maryland, 2019)
Shih Ping Li v. Tzu Lee
62 A.3d 212 (Court of Special Appeals of Maryland, 2013)
B-Line Medical, LLC v. Interactive Digital Solutions, Inc.
57 A.3d 1041 (Court of Special Appeals of Maryland, 2012)
Maryland State Board of Dental Examiners v. Tabb
22 A.3d 921 (Court of Special Appeals of Maryland, 2011)
Abrishamian v. Barbely
981 A.2d 797 (Court of Special Appeals of Maryland, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
941 A.2d 547, 178 Md. App. 209, 2008 Md. App. LEXIS 11, Counsel Stack Legal Research, https://law.counselstack.com/opinion/titan-custom-cabinet-inc-v-advance-contracting-inc-mdctspecapp-2008.