Titan Construction Co. v. Mark Twain Kansas City Bank

887 S.W.2d 454, 1994 Mo. App. LEXIS 1812
CourtMissouri Court of Appeals
DecidedNovember 22, 1994
DocketWD 48841
StatusPublished
Cited by8 cases

This text of 887 S.W.2d 454 (Titan Construction Co. v. Mark Twain Kansas City Bank) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Titan Construction Co. v. Mark Twain Kansas City Bank, 887 S.W.2d 454, 1994 Mo. App. LEXIS 1812 (Mo. Ct. App. 1994).

Opinion

SPINDEN, Presiding Judge.

This breach of contract dispute involves construction of a Kansas City apartment complex financed by Mark Twain Kansas City Bank. The bank took over the project and finished it when the developers, Bridgeport Ventures, defaulted. Mark Twain found the work of the general contractor, Titan Construction Company, to be unacceptable and fired it.

Titan claims that Mark Twain made fraudulent misrepresentations and breached its contract. Mark Twain countersued, charging Titan with breach of contract. The jury ruled for Mark Twain on Titan’s breach of contract claim and against Titan on Mark Twain’s counterclaim for breach of contract. The trial court entered summary judgment for Mark Twain on Titan’s claim of fraud against the bank. Titan appeals, and we affirm.

The apartment complex’s original developer was a six-person partnership known as Bridgeport Ventures. Thomas Saul, Titan’s principal owner and president, was one of Bridgeport Ventures’ partners. Mark Twain loaned Bridgeport Ventures $7.5 million for the project. The partners executed a note payable to the bank and secured it with a deed of trust on the property and each partner’s personal guarantee. Each partner agreed to assign the construction contract to Mark Twain if Bridgeport Ventures defaulted on the loan.

Bridgeport Ventures and Titan agreed on August 14,1986, that Titan would be general contractor for the project, and Titan began constructing the apartments. Bridgeport Ventures negotiated a new construction contract with Titan on March 23, 1987, raising the construction cost. In February 1988, Mark Twain agreed to increase its loan to Bridgeport Ventures to $8.2 million. Two days later, Saul withdrew as a partner of Bridgeport Ventures.

In 1987 and 1988, several subcontractors filed mechanic’s hens against the project because Titan had not paid them. This placed Bridgeport Ventures in default under its loan agreement with Mark Twain. Although Titan provided a bond against the mechanic’s hen claims, it did not pay the subcontractors.

On March 18, 1988, Bridgeport Ventures’ remaining partners told Mark Twain that the partnership could not continue the project unless Mark Twain restructured the loan and forgave the interest. They also said that if the bank refused to do this, they would assign the construction contract to it.

Mark Twain did refuse and became actively involved in the project. It discharged the architects and hired Peckham, Guton, Albers & Viets, Inc., (PGAV) to replace them. Discussions between Mark Twain and Bridgeport Ventures continued, and Mark Twain warned that it might foreclose on the property-

On July 22, 1988, Mark Twain accepted a deed in heu of foreclosure from the partners of Bridgeport Ventures. In exchange for the property and additional collateral pledged by individual partners, Mark Twain released Bridgeport Ventures from its obligations under the loan agreements. On the same day, Mark Twain and Titan entered into a separate contract in which they agreed to proceed under the terms of Titan's March 23, 1987, contract with Bridgeport Ventures. Mark Twain agreed to be responsible as the successor owner of the project, and Titan agreed to complete the project on or before December 1, 1988. Mark Twain retained McCor-mack, Baron & Associates, Inc., as its representative for the project. After discovering that critical as-built drawings were missing *457 and that much of the completed work was unacceptable, McCormack Baron decided the project was not progressing satisfactorily. Some of the subcontractors had walked off the job, and Titan lost its bonding. A structural engineer hired by Mark Twain concluded that the buildings were not structurally sound because of concealed defects.

From July 22,1988, to September 19,1988, Mark Twain and Titan negotiated problems with schedules, payments, defective and incomplete work and deviations from the plans and specifications. After concluding that the deficient work was extensive and that Titan was not going to correct it, Mark Twain obtained certification from PGAY that good cause existed for terminating Titan’s contract. On September 9, 1988, Mark Twain notified Titan of termination of their contract for default. Mark Twain sent Titan a second notice of termination on September 19, 1988.

After terminating Titan’s services, Mark Twain formed a limited partnership with McCormack Baron called Bridgeport Apartments Associates. Mark Twain conveyed the property to Bridgeport Apartments Associates but retained a 99 percent ownership interest. McCormack Baron agreed to manage the property for Mark Twain. Mark Twain transferred the property to Bridgeport Apartments Associates on September 28,1988, and recorded the action on September 30, 1988. Mark Twain hired Neighbors Construction Company to complete the project.

On November 18, 1988, Titan sued Mark Twain City Bank for declaratory judgment, breach of contract and fraud. Titan also sued McCormack Baron, Mark Twain Bank of St. Louis and PGAV for fraud. Mark Twain counterclaimed for breach of contract and filed a third-party claim against Titan’s surety, Travelers Indemnity Company, for its refusal to honor a performance bond issued for the project. The circuit court granted summary judgment in favor of all defendants on Titan’s fraud claim. Mark Twain and the other defendants settled with Travelers before trial. The breach of contract claims were tried to a jury in September 1993. The jury returned a verdict in favor of Mark Twain on Titan’s claim and against Titan on Mark Twain’s counterclaim. The trial court entered judgment on those verdicts and overruled all post-trial motions filed by Titan. This appeal followed.

In its first of four points on appeal, Titan contends that the trial court erred in overruling its motion for directed verdict, motion for new trial and motion for judgment notwithstanding the verdict because Mark Twain did not name McCormack Baron as a party to its counterclaim against Titan for breach of contract. Titan argues that because McCormack Baron was the general partner of the Bridgeport Apartments Associates which owned the Bridgeport Apartments project, Mark Twain had to include it as a necessary party.

“Contractual obligations ‘can only be enforced by one who is a party to the contract or in privity with it.’ ” County Asphalt Paving Company v. 1861 Group, LTD., 851 S.W.2d 577, 582 (Mo.App.1993) (citation omitted). McCormack Baron was not a party to Titan’s and Mark Twain’s contract. After Bridgeport Ventures defaulted, Mark Twain succeeded to all of the rights of Bridgeport Ventures as project owner. Titan and Mark Twain entered into a separate agreement for Titan’s completing the project. On September 9,1988, Mark Twain notified Titan that it was in default. Titan ceased work on September 20,1988, and, on September 28,1988, Mark Twain conveyed the property to Bridgeport Apartments Associates without assigning its contract with Titan to the limited partnership. McCormack Baron was not a party to Mark Twain’s contract with Titan and had no interest in the property when the contract was executed. McCormack Baron was not a necessary party to Mark Twain’s counterclaim against Titan.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ENG v. CUMMINGS, McCLOREY, DAVIS & ACHO, PLC
611 F.3d 428 (Eighth Circuit, 2010)
Wages v. Young
261 S.W.3d 711 (Missouri Court of Appeals, 2008)
Woods v. Wills
400 F. Supp. 2d 1145 (E.D. Missouri, 2005)
Information Technologies, Inc. v. Cybertel Corp.
66 S.W.3d 126 (Missouri Court of Appeals, 2001)
Arnold v. Erkmann
934 S.W.2d 621 (Missouri Court of Appeals, 1996)
Trotter's Corp. v. Ringleader Restaurants, Inc.
929 S.W.2d 935 (Missouri Court of Appeals, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
887 S.W.2d 454, 1994 Mo. App. LEXIS 1812, Counsel Stack Legal Research, https://law.counselstack.com/opinion/titan-construction-co-v-mark-twain-kansas-city-bank-moctapp-1994.