Titan Constr. Servs., LLC v Board of Mgrs. of PS 90 Condominium 2025 NY Slip Op 32286(U) June 23, 2025 Supreme Court, New York County Docket Number: Index No. 652243/2021 Judge: Melissa A. Crane Cases posted with a "30000" identifier, i.e., 2013 NY Slip Op 30001(U), are republished from various New York State and local government sources, including the New York State Unified Court System's eCourts Service. This opinion is uncorrected and not selected for official publication. [FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021 NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025
SUPREME COURT OF THE STATE OF NEW YORK NEW YORK COUNTY PRESENT: HON. MELISSA A. CRANE PART ----~----'----- 60M Justice ---------------------------------------------------X
TITAN CONSTRUCTION SERVICES, LLC INDEX NO. 652243/2021
Plaintiff, Decision After Bench Trial - V -
BOARD OF MANAGERS OF PS 90 CONDOMINIUM D/B/A PS90 CONDOMINIUM ASSOCIATION,
Defendant. ________ ,___x
Melissa A. Crane, JSC
This case concerns a construction project. On September 29, 2023, this court denied
summary judgment to plaintiff, Titan, finding issues of fact about whether there was a mutual
mistake and, if so, whether plaintiff should receive $2.06 a square inch for its terracotta work, as
defendant contends, or whether it should receive what plaintiff would consider a reasonable
price. Thus, the main issue for trial was: (1) whether the parties agreed to a particular price, and,
(2) if not, what a reasonable price would be. There are also issues concerning other work Titan
performed on the site. Defendant contends that the parties agreed to $2.06 per square inch and
that price is reasonable. Plaintiff contends that the parties did not agree to that price which
plaintiff postures is umeasonably low. The following is the court's decision after a bench trial.
I. The Price for the TRC 02 Work
On July 11, 2016, plaintiff Titan and defendant PS90, the property owner, entered into a
contract for Titan to perform work on PS90's condominium building (Ex. C) Part of the work
was for "TRC 02" repair, a type ofrepair to terracotta (id at§ 3.2.3). At§ 6.1.5, the contract
OTHER ORDER - NON-MOTION 1 of 8 Paae 1 of 9 [* 1] [FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021 NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025
lists as an "Addenda" a certain "Revised Bid Form" signed APRIL 13, 2016. Plaintiff attached
that bid form to the contract. It reads $285.00 per square inch as the unit price for the TRC 02
Terra Cotta Spall Repair (id at bates stamp 000053; see also Ex Eat 000063).
It is clear there was a mistake on that April bid form and that plaintiff meant to bid
$285/sq foot in that April bid. Although plaintiff claims in its post-trial brief that "There is no
evidence of a mutual mistake in the within action," this contradicts plaintiffs position elsewhere,
including, strangely, in the same post trial brief (see EDOC 115 pg. 2 "TITAN does not dispute
that the intended result was not what the parties' contract specifically contemplated"). The
position Plaintiffs counsel took on the record at trial also confirmed the presence of a mutual
mistake. At trial plaintiffs counsel conceded that "There was a bid submission of $2.06 that was
changed later that day to $285 a square inch. In our view it should have been $285 a square foot,
not a square inch." (Trial Transcript (TT) 106-107). Moreover, this on-the-record admission was
in keeping with plaintiffs position throughout the case. In its pretrial statement, plaintiff again
admitted that:
"TITAN does not dispute that the intended result was not what the parties' contract specifically contemplated. That is because the quantity should have been square feet by location, not the number of square inches multiplied by $285.00 per square inch, which is what the contract actually states."
(EDOC 108 pg. 2) Having conceded the existence of a mutual mistake in the contract
previously, plaintiff cannot now take a contrary position. Thus, it would appear no party
disputes that it was a mistake to append the April bid form containing the bid of $285 per square
inch to the contract.
Plaintiff does not argue that a court will reform the instrument to do what is reasonable in
the face of evidence of actual intent. Rather, PLAINTIFF ADMITS that "Where a written
instrument fails to conform to the intended agreement between the parties whether caused by the
2 of 8 Paae 2 of 9 [* 2] [FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021 NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025
mutual mistake of the parties, however induced, or of the mistake of one party and fraud of the
other, or for some other reason a court will reform the instrument so as to make it conform to
the actual agreement between the parties" (Pl Post Trial Br. [EDOC 115] at pg 17). This
position comports with the law. "Where there is no mistake about the agreement and the only mistake
alleged is in the reduction of that agreement to writing, such mistake of the scrivener, or of either party,
no matter how it occurred, may be corrected." (Nash v. Kornblum, 12 N.Y.2d 42, 47 [1962] (quoting I Born v. Schrenkeisen, 110 N.Y. 55, 59 [1888]).
Unfortunately for plaintiff, the evidence shows that the parties had meant to agree to
$2.06 a square inch. First, there is the May 16, 2016 bid submission (Ex Fat 000072). This Bid
Submission, which post dates the April bid submission, and is Titan's final bid, lists a square
inch price of $2.06 for the TRC 02 work (id. at 000072). Moreover, an email from Eric Mercado
at Titan to Mathew Cronin, dated May 17, 2016 (Ex 00), reflects that the May bid submission
was sent and included a change for TRC 02 work to "Square inch." It was after the final May
bid submission that defendant awarded the contract to Titan.
It was Titan who assembled the contract (see Testimony of Mr. Garcia (Titan) at pg 40:
"And in terms of putting together the paper documents with the signatures and the final version,
someone at Titan did that, right, and sent the whole thing back to SuperStructures? A: Yes."
Therefore, it is highly likely that someone at Titan incorrectly attached the April bid document to
the contract containing $285 per square inch, when they were supposed to have attached the May
bid document containing $2.06 per square inch.
There is more. The field reports, upon which Titan was always cc' d, all list the TRC 02
work in square inches at $2.06 per Unit Price (see Ex 000 spreadsheet at bates no 001660,
001691, and 001710). Titan's own exhibit ZZZ (Field Report 13) also lists $2.06 for TRC 02
3 of 8 Paqe 3 of 9 [* 3] [FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021 NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025
work. There is nothing in the record to suggest that Titan challenged this designation. In fact,
Titan submitted payment applications and accepted payment at $2.06 per square inch for the
terra cotta work. Joint Exhibit JJJ is an application and certificate for payment. At the point JJJ
was created, 100% of the original work was complete and Titan accepted $1, 710 for
approximately 832 square inches of work. Mathematically, this works out, rounded up by half a
cent, to $2.06 a square inch, just like the May bid called for. During the trial, in relation to Ex
JJJ, Mr.
Free access — add to your briefcase to read the full text and ask questions with AI
Titan Constr. Servs., LLC v Board of Mgrs. of PS 90 Condominium 2025 NY Slip Op 32286(U) June 23, 2025 Supreme Court, New York County Docket Number: Index No. 652243/2021 Judge: Melissa A. Crane Cases posted with a "30000" identifier, i.e., 2013 NY Slip Op 30001(U), are republished from various New York State and local government sources, including the New York State Unified Court System's eCourts Service. This opinion is uncorrected and not selected for official publication. [FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021 NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025
SUPREME COURT OF THE STATE OF NEW YORK NEW YORK COUNTY PRESENT: HON. MELISSA A. CRANE PART ----~----'----- 60M Justice ---------------------------------------------------X
TITAN CONSTRUCTION SERVICES, LLC INDEX NO. 652243/2021
Plaintiff, Decision After Bench Trial - V -
BOARD OF MANAGERS OF PS 90 CONDOMINIUM D/B/A PS90 CONDOMINIUM ASSOCIATION,
Defendant. ________ ,___x
Melissa A. Crane, JSC
This case concerns a construction project. On September 29, 2023, this court denied
summary judgment to plaintiff, Titan, finding issues of fact about whether there was a mutual
mistake and, if so, whether plaintiff should receive $2.06 a square inch for its terracotta work, as
defendant contends, or whether it should receive what plaintiff would consider a reasonable
price. Thus, the main issue for trial was: (1) whether the parties agreed to a particular price, and,
(2) if not, what a reasonable price would be. There are also issues concerning other work Titan
performed on the site. Defendant contends that the parties agreed to $2.06 per square inch and
that price is reasonable. Plaintiff contends that the parties did not agree to that price which
plaintiff postures is umeasonably low. The following is the court's decision after a bench trial.
I. The Price for the TRC 02 Work
On July 11, 2016, plaintiff Titan and defendant PS90, the property owner, entered into a
contract for Titan to perform work on PS90's condominium building (Ex. C) Part of the work
was for "TRC 02" repair, a type ofrepair to terracotta (id at§ 3.2.3). At§ 6.1.5, the contract
OTHER ORDER - NON-MOTION 1 of 8 Paae 1 of 9 [* 1] [FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021 NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025
lists as an "Addenda" a certain "Revised Bid Form" signed APRIL 13, 2016. Plaintiff attached
that bid form to the contract. It reads $285.00 per square inch as the unit price for the TRC 02
Terra Cotta Spall Repair (id at bates stamp 000053; see also Ex Eat 000063).
It is clear there was a mistake on that April bid form and that plaintiff meant to bid
$285/sq foot in that April bid. Although plaintiff claims in its post-trial brief that "There is no
evidence of a mutual mistake in the within action," this contradicts plaintiffs position elsewhere,
including, strangely, in the same post trial brief (see EDOC 115 pg. 2 "TITAN does not dispute
that the intended result was not what the parties' contract specifically contemplated"). The
position Plaintiffs counsel took on the record at trial also confirmed the presence of a mutual
mistake. At trial plaintiffs counsel conceded that "There was a bid submission of $2.06 that was
changed later that day to $285 a square inch. In our view it should have been $285 a square foot,
not a square inch." (Trial Transcript (TT) 106-107). Moreover, this on-the-record admission was
in keeping with plaintiffs position throughout the case. In its pretrial statement, plaintiff again
admitted that:
"TITAN does not dispute that the intended result was not what the parties' contract specifically contemplated. That is because the quantity should have been square feet by location, not the number of square inches multiplied by $285.00 per square inch, which is what the contract actually states."
(EDOC 108 pg. 2) Having conceded the existence of a mutual mistake in the contract
previously, plaintiff cannot now take a contrary position. Thus, it would appear no party
disputes that it was a mistake to append the April bid form containing the bid of $285 per square
inch to the contract.
Plaintiff does not argue that a court will reform the instrument to do what is reasonable in
the face of evidence of actual intent. Rather, PLAINTIFF ADMITS that "Where a written
instrument fails to conform to the intended agreement between the parties whether caused by the
2 of 8 Paae 2 of 9 [* 2] [FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021 NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025
mutual mistake of the parties, however induced, or of the mistake of one party and fraud of the
other, or for some other reason a court will reform the instrument so as to make it conform to
the actual agreement between the parties" (Pl Post Trial Br. [EDOC 115] at pg 17). This
position comports with the law. "Where there is no mistake about the agreement and the only mistake
alleged is in the reduction of that agreement to writing, such mistake of the scrivener, or of either party,
no matter how it occurred, may be corrected." (Nash v. Kornblum, 12 N.Y.2d 42, 47 [1962] (quoting I Born v. Schrenkeisen, 110 N.Y. 55, 59 [1888]).
Unfortunately for plaintiff, the evidence shows that the parties had meant to agree to
$2.06 a square inch. First, there is the May 16, 2016 bid submission (Ex Fat 000072). This Bid
Submission, which post dates the April bid submission, and is Titan's final bid, lists a square
inch price of $2.06 for the TRC 02 work (id. at 000072). Moreover, an email from Eric Mercado
at Titan to Mathew Cronin, dated May 17, 2016 (Ex 00), reflects that the May bid submission
was sent and included a change for TRC 02 work to "Square inch." It was after the final May
bid submission that defendant awarded the contract to Titan.
It was Titan who assembled the contract (see Testimony of Mr. Garcia (Titan) at pg 40:
"And in terms of putting together the paper documents with the signatures and the final version,
someone at Titan did that, right, and sent the whole thing back to SuperStructures? A: Yes."
Therefore, it is highly likely that someone at Titan incorrectly attached the April bid document to
the contract containing $285 per square inch, when they were supposed to have attached the May
bid document containing $2.06 per square inch.
There is more. The field reports, upon which Titan was always cc' d, all list the TRC 02
work in square inches at $2.06 per Unit Price (see Ex 000 spreadsheet at bates no 001660,
001691, and 001710). Titan's own exhibit ZZZ (Field Report 13) also lists $2.06 for TRC 02
3 of 8 Paqe 3 of 9 [* 3] [FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021 NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025
work. There is nothing in the record to suggest that Titan challenged this designation. In fact,
Titan submitted payment applications and accepted payment at $2.06 per square inch for the
terra cotta work. Joint Exhibit JJJ is an application and certificate for payment. At the point JJJ
was created, 100% of the original work was complete and Titan accepted $1, 710 for
approximately 832 square inches of work. Mathematically, this works out, rounded up by half a
cent, to $2.06 a square inch, just like the May bid called for. During the trial, in relation to Ex
JJJ, Mr. Garcia from Titan admitted that Titan billed $1,710 for approximately 832 inches of
TRC 02 work (See Ex JJJ at 001526 and TT 67-68). Thus, for the original scope of work Titan
charged and was paid at the rate of $2.06 for TRC 02 work.
At some subsequent point, the project expanded to an additional 50,026 square inches of
TRC 02 work. Mr. Garcia admitted that the bid unit pricing meant that the contractor would
perform additional work at the same unit price (TT 71). Nevertheless, Titan interposed a change
order that asked for $14 million dollars for the 50,026 square inches of additional work (see Ex
FFFF). Mr. Garcia admitted this request for $14M was based on $285 a square inch, a number
plaintiff has conceded was NOT what the parties had agreed to.
Plaintiff had apparently balked at the large amount of additional work, finding it
financially infeasible at $2.06/sq inch (see Ex GGG entitled "Response to AG&A letter dated
February 20th, 2019"):
"Furthermore, based on the project drawings and specifications, in addition to the insignificant base bid quantity of TRC 02, the detailed work to performed TRC 02 at $2.06 per square inch is absurd based on Industry cost. To execute and complete a typical square inch TRC 02 repair it would take a minimum 4 days excluding materials limitation to weather as per project documents guidelines. The difference to replace 1SF vs. 1SI is a material cost only, as labor tools remain unchanged."
4 of 8 Paqe 4 of 9 [* 4] [FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021 NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025
However, Titan does not explain why this circumstance enabled Titan to raise its unit
price when, as Mr. Garcia admitted, the original bid price was supposed to carry through to
additional work (TT 71). In addition. the increase in square inches should not matter. Titan was
being paid for the amount of work, not a flat fee. More square inches meant more money. If
Titan underbid the project, that circumstance is irrelevant to its contractual obligations.
Neither side briefed the standard of proof to demonstrate what a proponent of reformation
needs to adhere to after both sides agree that the contract contains a mutual mistake of fact, but
disagree about what the parties' actual agreement was. Hence, in an abundance of caution, the
court will apply a clear and convincing standard of proof (see Empery Asset Master Ltd, v Ait
Therapeutics, Inc., 215 AD3d 10, 14-15 [1 st Dep't 2023] [affirming decision after bench trial that
investors had established a mutual mistake in omitting anti-dilution provisions]).
The pattern jury instructions (PJI 1:64) describe clear and convincing evidence:
it is not enough to find that the preponderance of the evidence is in the plaintiffs favor. A party who must prove (his, her) case by a preponderance of the evidence only need satisfy you that the evidence supporting (his, her) case more nearly represents what actually happened than the evidence which is opposed to it. But a party who must establish (his, her) case by clear and convincing evidence must satisfy you that the evidence makes it highly probable that what (he, she) claims is what actually happened.
Applying that standard here, it is highly probable that the parties meant to agree to a unit
price of $2.06. As discussed, plaintiff has conceded that the unit price of $285/sq inch in the bid
document attached to the parties' contract was a mistake. The remaining evidence supports that
Titan bid, and defendant accepted, a unit price of $2.06. This evidence includes, as discussed
supra: Titan's final May bid containing a $2.06 unit price for TRC 02 work, the testimony at
trial, the field reports, Titan's invoices and its acceptance of payment at the rate of $2.06/inch.
5 of 8 Paoe 5 of 9 [* 5] [FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021 NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025
There is also Mr. Garcia's testimony that the accepted bid unit price was supposed to apply to
additional work.
Meanwhile, plaintiffs' assertions about the correct unit price are a moving target. First,
Mr. Garcia testified that Titan intended to bid $285 per square inch (TT46) This contradicts
Plaintiffs own counsel who said: "In our view it should have been $285 per square foot, not a
square inch" (TT 106). However, $285 per square foot also makes no sense for plaintiff as $285
per square foot divides down to $1.98 per square inch, an amount that is even less than the $2.06
plaintiff rejects. Going the other way, 50,026 square inches is 347 square feet. At $285 a square
foot, plaintiff would only be owed $98,895.00.
Even if Mr. Garcia's testimony, that Titan intended to bid $285 per square inch, did not
contradict plaintiffs position throughout this litigation, his testimony is not credible. In
defendant's exhibit 2, an April 17, 2019 email from Mr. Garcia, he claims yet a different amount.
He asserts there was now a "clerical error" on the May bid form "changing it from $206.00 to
$2.06" per square inch. What happened to the $285 per square inch? Which is it?
Then, there is plaintiffs expert's calculations. Plaintiffs expert developed a formula,
apparently for this litigation, to calculate linear flat and decorative patch work. His report
calculated a range from $700,000 to $900,000. This in itself is a moving target. The constantly
changing and contrived nature of plaintiff's supposed unit price does not reflect well on its
credibility.
Thus, defendant has carried its burden by clear and convincing evidence to show that the
parties actually intended to agree to $2.06 per square inch for the TRC 02 work. Because the
evidence shows what the parties actually agreed to, the court does not need to reach plaintiffs
expert and what he, or anyone else, considered to be reasonable.
6 of 8 Paae 6 of 9 [* 6] [FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021 NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025
II. Titan's Allegedly Incomplete and Defective Work
Defendant contends that Titan failed to: (1) fix damages metal panels, (2) properly
reconstruct the parapet walls that led to water intrusion, (3) repair and replace metal pavers and
(4) repair damage to a door.
A. The parapet wall
Defendant failed to carry its burden to show that Titan was responsible for the defects in the
construction of the parapet wall. Titan objected to the design, but built it to the specifications
that SSX gave it. Titan did what it was instructed to do. If the design was poor, that is not
Titan's fault. Further, all relevant entities, including the Department of Buildings, signed off on
the wall and Titan was paid for that work. Defendant terminated Titan on July 23, 2019. The
only reasons given in the termination letter (see Joint Ex. P), were (1) "failure to supply enough
properly skilled workers and proper materials" and (2) it's having issued change orders with
"Wholly unsubstantiated and commercially unreasonable" unit prices. There is no mention of
the wall. Finally, Mr. Galetta is not a neutral witness. SSX is his company and probably
responsible for the faulty design.
B. The remaining defects:
Titan appears to concede some of defendant's remaining grievances constitute defective
work. This is because on page 21 of its post-trial brief, it issues "Credits for defective work for
which evidence was presented." These total $34,415.00 and involve: (1) the panels to be
replaced, (2) coating on the meal doorframes, (3) drywall repair, (4) painting and (5) pavers.
Aside from the work underlying these credits, there is no evidence that plaintiff owes
defendant anything for other work. In Joint exhibit LL, Defendant lists additional work, some of
which it failed to discuss in the post trial brief, to claim that Titan owes it $425,028.00.
7 of 8 Paae 7 of 9 [* 7] [FILED: NEW YORK COUNTY CLERK 06/23/2025 04:04 P~ INDEX NO. 652243/2021 NYSCEF DOC. NO. 116 RECEIVED NYSCEF: 06/23/2025
However, there is no support in the record for most of the remaining entries and some are highly
suspicious. For instance, the largest bulk amount of the $425,028.00 is "SSX Services (to date)
$180,478" (see Ex LL). No where in Mr. Galetta' s direct trial affidavit ( see EDOC 110) does he explain
why SSX needed to charge $180,478 due to Titan's allegedly defective work. The lack of explanation is
compounded by the self-serving nature of the testimony as SSX is Galetta's own company. There is
utterly no explanation as to what New Bedford Management Services did to earn $59,884 and why Titan
should pay for it. Rather, the $425,028.00 seems to be a last minute contrivance to lessen the blow should
defendant have lost on the TRC 02 issue.
By defendant's own calculations, it still owes Titan $93,800.04 (see Ex LLL) for the TRC 02
work. With the credit of$34,415.00 for Titan's defective work, defendant still owes $59,385.04. As
Titan has not proved its case with respect to the unit price, and defendant has largely failed to prove its
counterclaims, neither party can be considered the prevailing party for purposes of the attorney fee
provision of the contract. Therefore, all requests for attorney's fees are denied.
The court has considered the remaining contentions of both parties and finds them unavailing. Accordingly, it is ORDERED THAT the clerk enter judgment in the amount of $59,385.04 with pre judgment interest from July 15, 2019, the date Titan was terminated, in favor of Titan Construction Services and against Board of Managers of PS 90 Condominium; and it is further ADJUDGED, DECREED AND DECLARED that there was a mutual mistake in the parties' contract concerning the unit pricing for TRC 02 work; and it is further ADJUDGED, DECREED AND DECLARED that the Parties agreed that Titan would perform the additional TRC 02 Work at a unit cost of $2.06 per square inch; and it is further ORDERED THAT there shall be no motion practice whatsoever without prior conference with the court, briefs that fail to contain a table of contents and table of authorities will be rejected.
6/23/2025 DATE ~ MELISSA A. CRANE, J.S.C. CHECK ONE: Q CASE DISPOSED □ NON-FINAL DISPOSITION □ GRANTED □ DENIED □ GRANTED IN PART □ OTHER
8 of 8 Paae 8 of 9 [* 8]