Tinsley v. Kemery

70 S.W. 691, 170 Mo. 310, 1902 Mo. LEXIS 63
CourtSupreme Court of Missouri
DecidedNovember 26, 1902
StatusPublished
Cited by11 cases

This text of 70 S.W. 691 (Tinsley v. Kemery) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tinsley v. Kemery, 70 S.W. 691, 170 Mo. 310, 1902 Mo. LEXIS 63 (Mo. 1902).

Opinion

MARSHALL, J.

This is a suit upon a contractor’s bond, in which plaintiff seeks to recover a judgment for $343.71, against the contractor and the sureties on the bond, and the contractor counterclaims for $366.70 extras. The plaintiff had judgment in the circuit court for $359.12, and the defendants appealed to the St. Louis Court of Appeals. .That court transferred the case to this court on the ground that appellate jurisdiction is vested in this court, because the trial court had denied the defendants a trial by jury as guaranteed by section 28, article 2, Constitution of Missouri of 1875. [Tinsley v. Kemery, 83 Mo. App. 94.] That ruling was based upon the rule laid down in Ice Co. v. Tamm, 138 Mo. 385.

The petition is bottomed upon an account stated, between the plaintiff and the contractor, growing out of a contract made by Kemery to build a house for the plaintiff, under which the plaintiff had paid $343.71 in excess of the contract price. An itemized statement was filed with the amended petition setting out the contract price, and the extras, and also all the payments made by the plaintiff, and showing the balance claimed. The contractor and sureties answered separately. The answer of the contractor is a general denial, special defenses, and a counterclaim for $366.70, with a bill of .items for extras amounting to that sum. The first special defense is that the bond sued on was not executed until long after the work had been begun, and that the bond was without consideration. The second special defense is substantially the same as the first. The third [313]*313special defense is that the payments made hy the plaintiff were not made to the defendant in person, nor were they made at the time agreed therefor hy the contract. (The fact was that the payments were 'prematurely made, hut no damage is shown to have resulted to the defendant for this rather extraordinary proceeding.) The fourth special defense' is that there were changes made in the plans and specifications and in the contract secured hy the bond. Then follows the counterclaim and the hill of items upon which it is based.

The answer of the sureties is a general denial, with seven special defenses, to-wit: first, that there is no consideration for the bond and that it was executed long after the contract it secures was made and the work begun' thereunder; second, that the contract was changed and the work done differently from- that contemplated by the plans and specifications, without the consent of the sureties; third,. that the plaintiff paid the contractor before the part payments were due hy the terms of the contract; fourth, that the plaintiff did not insure the building as required hy the contract; fifth, that by the terms of the contract the owner reserved a right to make alterations, additions or omissions in the work, which the contractor was obliged to carry out without its affecting the contract, but that the value of such alterations should he agreed upon in writing between the owner and the contractor before they should be made, and that alterations were made hut no such written agreement as to the value thereof was so made;.sixth, that it was agreed between the sureties and the plaintiff that one Baird should not be employed as architect or superintendent or have anything to do with the work or contract and that the plaintiff violated the agreement and permitted Baird to act as superintendent. The reply sets up that the contract provided that changes might be made in the work contemplated by the contract, and extra work done, as the parties might agree upon in writing and that no changes were made or extra work done except such as the parties agreed upon in writing.

The record shows that these answers were filed at [314]*314the November term, 1897, of tbe Louisiana Court of Common Pleas, and further shows: “Whereupon the-court of its own motion appoints W. H. Morrow, referee, over the objection of defendants J. D. Bowman and Mary E. Rupert” (the surety and administratrix of the deceased surety). The record further shows that at the adjourned November term, 1897, to-wit, on December 13th, 1897, the defendants moved the court to set aside the order of reference, assigning as grounds for the motion: “First, there is no such account between said parties as to justify the appointment of a referee; second, these defendants objected to said appointment at the time it was made, and the referee has not qualified as such at this time.” On December 14th, 1897, the court sustained the said motion, and modified the order of reference “so that the referee shall only be required to find and state an account between plaintiff W. G. Tinsley, and defendant J. W. Kemery, and if any of the items in account between plaintiff and J. W. Kemery were not contracted under the original contract, the referee must show the facts. Whereupon defendants J. D. Bowman and Mary E. Rupert, by John W. Matson, their attorney, except to this entry for the reasons stated in the motion. Defendant Kemery excepts to the orders of the court for the reason that it is not a case for reference."

The record then shows that on May 21, 1898, the referee filed his report stating in full the account between the owner and contractor. The report of the referee shows that the contract price for the building,' as called for by the plans and specifications, was $2,218, and that the plaintiff paid the contractor $2,759.50, and that the contractor also did work and furnished materials, “not contracted for under the original contract,” consisting of twenty-eight items, aggregating $197.79.

On May 26, 1898, during the regular May term, 1898, the defendants filed their exceptions to the report of the referee, asserting, inter alia, that the court “had no authority under the pleadings in this cause to refer any part of said cause to said referee."

[315]*315Afterwards at the November term, 1898, to-wit, on November 17, 1898, the court “elected to submit to the jury the issue as to whether the bond had been signed at the time of the signing of the contract, ’ ’ the parties announcing themselves ready for trial, and a jury was impaneled. The .court excluded all questions except whether the bond was executed with the building contract or in pursuance of it, and the defendants excepted to the ruling. Thereupon - the defendants’ attorney said to the court: “Under the ruling of the court I presume we have the opening and closing.” The court replied: “Yes, the burden is upon you.” Thereupon the trial proceeded, and at the close of the defendants’ showing, the court directed a verdict for the plaintiff.

On the next day, November 18,1898, at the November term, the defendants moved the court, “To strike out so much of its findings as is in anyway different from the report of the referee, and objects to the court determining any of the issues in the case, and requests that all issues not submitted to the referee be submitted to a jury, and that all issues and findings not submitted to said referee be submitted to a jury, and these defendants ask and request a jury trial of all said issues, and refuse to waive their right in said respect.” On the same day the court overruled the said motion, and after modifying the referee’s report by striking out three items aggregating $15.41, complained of by the defendants, and held by the court to be entirely disconnected with the contract, the court found that all extras were agreed upon by the parties, as also the value thereof, and entered judgment for the plaintiff for $359.12.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vannoy v. Swift Company
201 S.W.2d 350 (Supreme Court of Missouri, 1947)
Hancock v. State Highway Commission
149 S.W.2d 823 (Supreme Court of Missouri, 1941)
Ex Parte Higgins v. Hoctor
62 S.W.2d 410 (Supreme Court of Missouri, 1933)
Darlington v. Allison
12 S.W.2d 839 (Court of Appeals of Texas, 1928)
Wolf v. Hartford Fire Insurance Co.
263 S.W. 846 (Supreme Court of Missouri, 1924)
Johnston v. Star Bucket Pump Co.
202 S.W. 1143 (Supreme Court of Missouri, 1918)
Link v. Hathway
127 S.W. 913 (Missouri Court of Appeals, 1910)
Snyder v. Crutcher
118 S.W. 489 (Missouri Court of Appeals, 1909)
Smith v. Kunert
115 N.W. 76 (North Dakota Supreme Court, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
70 S.W. 691, 170 Mo. 310, 1902 Mo. LEXIS 63, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tinsley-v-kemery-mo-1902.