Timber Structures, Inc. v. Chateau Royale Corp.

199 N.E.2d 623, 49 Ill. App. 2d 343, 1964 Ill. App. LEXIS 791
CourtAppellate Court of Illinois
DecidedJune 11, 1964
DocketGen. 49,248
StatusPublished
Cited by2 cases

This text of 199 N.E.2d 623 (Timber Structures, Inc. v. Chateau Royale Corp.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Timber Structures, Inc. v. Chateau Royale Corp., 199 N.E.2d 623, 49 Ill. App. 2d 343, 1964 Ill. App. LEXIS 791 (Ill. Ct. App. 1964).

Opinion

ME. PEESIDING JUSTICE SCHWAETZ

delivered the opinion of the court.

This is an appeal from an order granting motions for summary judgment made by the defendants Apollo Savings & Loan Association (Apollo) and Chateau Eoyale Corporation (Chateau Eoyale) in a mechanic’s lien foreclosure suit.

Plaintiff is a subcontractor who supplied the materials to be used in the construction of an addition to a commercial building in Chicago owned by Chateau Eoyale and financed by Apollo, as the mortgagee. Apollo disbursed the construction loan. Before this suit was instituted, Ealph Scafuri & Co., Inc. (Scafuri), the general contractor, executed a general release of all its interest in the property and is not a party to this appeal.

The principal issues involve the authority of an agent of plaintiff to execute a waiver of lien upon which Apollo made payment to the general contractor, and whether Apollo and Chateau Eoyale are estopped from making this defense.

On December 28, 1959, Apollo made the loan in question to Chateau Boyale for the construction of an addition to a building at 5743 West Chicago Avenue, Chicago. Chateau Boyale engaged Scafuri as general contractor, and he contracted with plaintiff for the manufacture and installation of wooden trusses for the building. Plaintiff’s headquarters are in Portland, Oregon. Its agent in Chicago is Bobert P. Dorman, described as Central Division Manager, with offices in Schiller Park, Illinois. On March 24, 1960, Apollo received a verification in writing, signed by Dorman, of plaintiff’s contract with Scafuri. Plaintiff’s home office was aware that Dorman had delivered the verification to Apollo, as indicated by a letter dated April 11, 1960, from plaintiff’s home office to Apollo, in which the verification is referred to. The letter also asked for confirmation of the fact that “you [Apollo] will be paying directly to subcontractors by means of regular payout orders.” In response to plaintiff’s request, Apollo on April 14, 1960, said that it “will remit our check to your corporation after the installation of the trusses and upon receipt of proper payout requisition and waiver of lien.”

Plaintiff completed its work on August 31, 1960, but did not present its mechanic’s lien waiver to Apollo directly for payment. Instead, on or about September 7,1960, Dorman accepted payment from Scafuri by the latter’s uncertified check, and Dorman on behalf of plaintiff thereupon delivered to Scafuri a full waiver of mechanic’s lien. This waiver bore the signature of Bobert P. Dorman, Division Manager, Timber Structures, Inc., Central Division, and recited that the plaintiff had received payment and waived any lien claim against the property. Dorman did not present Scafuri’s check for payment in Chicago, but on September 9, 1960, mailed it to plaintiff’s home office in Oregon together with his memorandum of payment indicating that the job had been paid for and a waiver of lien delivered. The check and accompanying memorandum of payment were received at plaintiff’s Portland office on September 12,1960.

Later, on or about September 14, 1960, Apollo received a payout order from Scafuri, signed by Adam N. Stillo, secretary of Chateau Royale, authorizing Apollo to pay $6,734 to Scafuri. That amount apparently represented payment for work done by plaintiff, .as well as some work done by Scafuri, because Scafuri presented his own waiver of lien, as well as the waiver of lien signed by Dorman. Apollo’s construction loan manager, Philip J. Koop, verified the installation of the wooden trusses, compared the signatures on the lien waivers and affidavits with the signature cards on file with Apollo, and on September 15,1960, paid Scafuri the full amount.

On September 21, 1960, two weeks after plaintiff delivered its alleged waiver of lien, and six days after Apollo’s payout based thereon, plaintiff, by Joseph L. Heinz, its secretary, advised Apollo by telephone that Scafuri’s check had been returned marked “Insufficient Funds,” and also advised Apollo that plaintiff’s waiver of lien had been delivered to the general contractor upon condition that the check would be honored. Koop advised Heinz that Apollo had already made payment to the general contractor based on plaintiff’s lien waiver and informed Heinz not to worry, that Apollo would take care of the matter; that there was approximately $150,000 left of a $300,000 mortgage, and that there would be no problem in making the check good. The following day the conversation was confirmed by Apollo’s letter to plaintiff, stating that ’Scafuri had been contacted and had told Koop to tell plaintiff funds were available in his account and that plaintiff should redeposit the check. Koop added a provision that “ [i]f, for any reason, this is not acceptable or the information given to us is false, please notify the undersigned as soon as possible.” The check was redeposited by plaintiff on September 28th and came back marked “Insufficient Funds,” on October 4,1960.

In the meantime, Chateau Royale was becoming disillusioned with Scafuri as its general contractor. It (Chateau Royale) had booked parties, expecting Scafuri to finish the work during September, but they had to be cancelled because of delay. During the week of September 20th, .the City of Chicago stopped the work for three reasons: prestressed, instead of precast, concrete had been used in the building, no driveway permit had been obtained, and certain plans covering electrical and plumbing work had not been filed with the city. The NSF check to the plaintiff followed, and Chateau Royale deciding to terminate its relations with Scafuri, obtained a general release of his interest in the construction fund on October 1, 1960, and engaged a new general contractor, one Sanders. A payout order dated September 24, 1960, bearing Sanders’ name as a general contractor, was received by Apollo and paid September 30, 1960. Ralph Scafuri was not on the job after September 24th. Chateau Royale, through Stillo, was in touch with Heinz, but did not advise him that Scafuri’s discharge was imminent or that the work had been stopped. Stillo told Heinz he would present the story of the NSF check to the owner, and he asked Heinz to call back in a week. On October 5, 1960, plaintiff learned of Scafuri’s discharge through a telephone call from Sanders.

On July 12, 1961 plaintiff filed suit, asking, among other things, for a foreclosure of its mechanic’s lien. After various pleadings, interrogatories and requests for admission, the important portions of which have been summarized, Apollo and Chateau Royale filed motions for summary judgment and presented affidavits of Philip J. Koop and Adam N: Stillo in support thereof. In opposition, plaintiff filed the affidavits of Joseph L. Heinz, its secretary, and Philip R. Toomin, its attorney. Toomin’s affidavit said he had taken depositions of Stillo, Koop and Sanders, and that he was setting forth pertinent parts thereof which had not been previously presented. The trial court granted the motions for summary judgment on the mechanic’s lien foreclosure count and found there was no just reason for delaying enforcement or appeal. Ill Rev Stats c 110, § 50(2) (1963).

As this appeal is from an order of the trial court granting Apollo’s and Chateau Royale’s motions for summary judgment, we must determine whether from pleadings, depositions and admissions on file, together with the affidavits, there is any genuine issue of material fact presented.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Capitol Plumbing & Heating Supply Co. v. Snyder
244 N.E.2d 856 (Appellate Court of Illinois, 1969)
G. Chicoine Contractors, Inc. v. John Marshall Building Corp.
222 N.E.2d 712 (Appellate Court of Illinois, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
199 N.E.2d 623, 49 Ill. App. 2d 343, 1964 Ill. App. LEXIS 791, Counsel Stack Legal Research, https://law.counselstack.com/opinion/timber-structures-inc-v-chateau-royale-corp-illappct-1964.