Tim Romero Painting, LLC v. John J. Romero
This text of Tim Romero Painting, LLC v. John J. Romero (Tim Romero Painting, LLC v. John J. Romero) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
NOT DESIGNATED FOR PUBLICATION
STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT
CA 14-1255
TIM ROMERO PAINTING, LLC
VERSUS
JOHN J. ROMERO
**********
APPEAL FROM THE SIXTEENTH JUDICIAL DISTRICT COURT PARISH OF IBERIA, NO. 122864 HONORABLE GERARD B. WATTIGNY, DISTRICT JUDGE
BILLY HOWARD EZELL JUDGE
Court composed of Jimmie C. Peters, Billy Howard Ezell, and Phyllis M. Keaty, Judges.
AFFIRMED. Kreig Anthony Breaux Landry, Watkins, Respaske & Breaux P. O. Drawer 12040 211 East Main Street New Iberia, LA 70562-2040 (337) 364-7626 COUNSEL FOR PLAINTIFF/APPELLEE: Tim Romero Painting, LLC
R. Michael Moity, Jr. The Moity Law Firm 340 Weeks St. New Iberia, LA 70560 (337) 365-5529 COUNSEL FOR DEFENDANT/APPELLANT: John J. Romero EZELL, Judge.
In this matter, John Romero appeals a judgment in favor of Tim Romero
Painting, L.L.C. for $26,260.00 for breach of contract. For the following reasons,
we hereby affirm the judgment of the trial court.
Tim Romero Painting, L.L.C. (TRP) was approached by an agent for John
Romero (hereinafter Mr. Romero) in February of 2013 about applying a new roof
on a building owned by Mr. Romero. TRP submitted a proposal to Mr. Romero
dated February 12, 2013, including literature with reference to the types of
materials that would be used for the re-roofing project, together with the manner in
which they would be applied and the warranty periods that would be furnished for
the materials to be chosen from. The price of the roof was to be $33,000.00. Mr.
Romero had his agent advise TRP that the proposal was approved and to start work
as soon as possible.
TRP began work in early March of 2013. TRP began the prep work of
pressure washing the roof to remove debris and dirt. The pressure washing took
roughly three ten-hour days. TRP then applied caulk to the flashing where
required and began to build up low spots on the flat roof with a product called
Slope Builder. TRP then applied the base coat and one of two ―top coats‖ of an
elastomeric product. TRP could not finish applying these coats to the entire roof,
however, as a fire escape catwalk existed on part of the roof that was in violation
of the fire code. TRP was supposed to wait to address this area until the Fire
Marshal approved a plan for a new catwalk. Because of this catwalk issue, the
final top coat layer could not be applied at all, as it would need to be applied all at
once for the coating to be seamless for maximum protection from water. Approval
from the Fire Marshal was not obtained by Mr. Romero until one week prior to the April 2014 trial. However, Mr. Romero saw some bubbling in the application of
the first top coat, was not satisfied with how he felt it was being applied, and told
two TRP employees to leave the job site. He never told TRP it could return to the
jobsite to fix any problems.
After trial on the matter, the trial court found that TRP had completed eighty
percent of the work and awarded it $26,260.00 for breach of contract. From that
decision, Mr. Romero appeals.
On appeal, Mr. Romero asserts two assignments of error. He claims that the
trial court erred in finding the workmanship performed was in accordance with the
proposal and that the trial court erred in finding eighty percent of the work was
done prior to stoppage.
The two assignments of error both relate to findings of fact by the trial court
which are reviewed by this court under the manifest error standard of review. An
appellate court cannot set aside the findings of fact by the trial court unless those
findings are clearly wrong or manifestly erroneous. Rosell v. ESCO, 549 So.2d 840
(La.1989). An appellate court is not to determine whether the trier of fact was right
or wrong, but instead, whether the fact finder’s conclusion was a reasonable
one. Lyons v. Bechtel Corp., 00-364 (La.App. 3 Cir. 12/27/00), 788 So.2d 34, writ
denied, 01-282 (La. 3/23/01), 787 So.2d 996.
Mr. Romero claims that the work performed by TRP was not workmanlike
in that there was bubbling in the second layer as well as a few leaves and a screw
in that layer. However, the trial court found and the record shows that these
problems were not at all uncommon in the application of a roof like this.
Moreover, Tim Romero, the owner of TRP, testified that these problems would
have been addressed before the application of the final top coat, had he been
2 allowed to complete the job. However, he was unable to remove these potential
problems because Mr. Romero failed to address the catwalk and then terminated
the job. Furthermore, the job was unfinished due to Mr. Romero’s actions and not
those of TRP. As there is a reasonable factual basis in the record for the trial
court’s findings, we cannot find manifest error in the trial court’s determination on
the quality of TRP’s work.
Finally, Mr. Romero claims that the trial court erred in finding that eighty
percent of the contracted work had been completed. We disagree. Tim Romero
testified that eighty percent of the work had been finished. This testimony was
completely uncontradicted by Mr. Romero. Tim Romero stated TRP pressure
washed the roof, applied caulk to the flashing where required, and built up low
spots on the flat roof with Slope Builder. TRP then applied the base coat and the
first of two required top coats. The only work not completed was the final top coat
and any work done under the catwalk. TRP’s inability to perform these tasks were
through no fault but Mr. Romero’s. While eighty percent of the roof may have not
been completed to a final status, we can find no error in the trial court’s finding
that eighty percent of the total work had been completed.
The trial court in this matter provided thorough and lengthy reasons for
judgment totaling nineteen pages. We find them to be persuasive and an excellent
summary of the evidence in the record before this court. It is clear that the trial
court carefully considered the evidence before it, and we can find no manifest error
in its findings.
3 For the above reasons, we hereby affirm the decision of the trial court. Costs
of this appeal are hereby assessed against John Romero.
AFFIRMED.
This opinion is NOT DESIGNATED FOR PUBLICATION. Uniform Rules—Courts of Appeal. Rule 2–16.3.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Tim Romero Painting, LLC v. John J. Romero, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tim-romero-painting-llc-v-john-j-romero-lactapp-2015.