Tim Edward Brugger II v. Midland County Bd of Road Commissioners

920 N.W.2d 388, 324 Mich. App. 307
Michigan Court of Appeals·Decided May 15, 2018·No. 337394·Published·Cited by 5 cases

Opinion

Shapiro, P.J.

*310 Defendant, the Midland County Board of Road Commissioners, appeals the trial court's denial *311 of its motion for summary disposition. Because plaintiff's presuit notice complied with the applicable statute, we affirm.

I. FACTS

Plaintiff, Tim E. Brugger II, was injured on April 27, 2013, when he lost control of his motorcycle and crashed. He filed suit against defendant, asserting that the crash was the result of large potholes and uneven pavement on a road maintained by the Midland County Road Commission. Governmental immunity does not shield a road commission from liability when it fails to maintain the road in a condition "reasonably safe and convenient for public travel." MCL 691.1402(1).

On August 15, 2013, 110 days after the crash, plaintiff served defendant with presuit notice in accordance with *390 MCL 691.1404 of the governmental tort liability act (GTLA), MCL 691.1401 et seq . After suit was filed, the case progressed in typical fashion until this Court issued the decision in Streng v. Bd. of Mackinac Co. Rd. Comm'rs , 315 Mich. App. 449 , 890 N.W.2d 680 (2016). In Streng , id. at 462-463, 890 N.W.2d 680 , the Court concluded that MCL 224.21(3) (a provision of the county road act), rather than MCL 691.1404, controlled the timing and content of a presuit notice directed to a road commission. Following that decision, defendant, relying on Streng , moved for summary disposition, arguing that plaintiff's presuit notice-filed within the 120 days as set forth in the GTLA-was ineffective because it was not filed within the 60-day limit set forth in the county road act.

The trial court denied the motion, concluding that Streng should be given prospective application because, for decades, parties and the courts had understood *312 that the GTLA notice provision controlled. The trial court set forth its opinion from the bench, stating:

From the Court's perspective, I find that the Supreme Court in Rowland [ 1 ] specifically indicated that the GTLA is the notice provision for which road commission cases are subject to being followed and it had done that consistent with a fairly significant long line of cases, two of which they overruled.
However, it was consistent as to what was the proper statutory provision in the Court's perspective is that it was the application of that provision that was found to be inapplicable and, therefore, stricken by the Supreme Court in Rowland .
So, therefore, the Court finds that the circumstances in this case are in compliance with the requirements of the GTLA. And, therefore, that it is-summary disposition on that basis is denied.
However, I will also indicate if the analysis is, in fact, inaccurate and Streng was correctly decided, ... I will find that based upon the criteria that was announced in Bahutski [ 2 ] [sic] as well as the other case that was cited in Rowland that it is, in fact, to be applied prospectively, because there had been no indication that the differentiation was appropriate to provide notice to claimants that were coming forward.
And that it would-it would, in fact, result in manifest injustice to deny claims that had been in compliance with the agreed-with what had been agreed upon as the proper notice provision, but there was a change, from the Court's perspective, a change in the application of that interpretation by the Court of Appeals decision and that occurred after the notice had already been provided in this case.
*313 And, therefore, the Court's ... opinion [is that] it does not prevent the application of the GTLA provision of 691.1404.

Defendant appeals the trial court's ruling, arguing that plaintiff's failure to file a notice consistent with the requirements of the county road act mandates dismissal.

The question before us, therefore, is whether the decision in Streng should apply to all pending cases or only to those cases that arose after it was issued.

II. ANALYSIS

This case presents a highly unusual circumstance. The Legislature has enacted *391 two inconsistent statutes governing presuit notice to road commissions. The GTLA requires that notice be provided within 120 days of the injury. MCL 691.1404(1). In contrast, the county road act allows for a 60-day period. MCL 224.21(3). The statutes also vary somewhat regarding the required content of the notice.

In 1970, the Michigan Supreme Court held that the 60-day notice provision in MCL 224.21(3) violated due process as applied to an incapacitated individual. Grubaugh v. City of St. Johns , 384 Mich. 165 , 176, 180 N.W.2d 778 (1970), abrogated by Rowland v. Washtenaw Co. Rd. Comm. , 477 Mich. 197 , 731 N.W.2d 41 (2007). Grubaugh did not extend its conclusion to all claimants however, noting that was a question for another day. Id. at 176-177 . In 1972, in Reich v. State Hwy. Dep't , 386 Mich. 617 , 623-624,

Free access — add to your briefcase to read the full text and ask questions with AI

Tim Edward Brugger II v. Midland County Bd of Road Commissioners, 920 N.W.2d 388, 324 Mich. App. 307 (Mich. Ct. App. 2018).

920 N.W.2d 388 (Tim Edward Brugger II v. Midland County Bd of Road Commissioners) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

20221122_C359999_35_359999.Opn.Pdf
Michigan Court of Appeals, 2022
Ryan Harston v. County of Eaton
922 N.W.2d 391 (Michigan Court of Appeals, 2018)