Tillman Infrastructure LLC v. The Board of Supervisors of Culpeper County, Virginia

District Court, W.D. Virginia·Decided December 30, 2022·No. 3:21-cv-00040·Unknown

Opinion

CLERKS OFFICE U.S. DIST. COL AT LYNCHBURG, VA FILED UNITED STATES DISTRICT COURT 12/30/2022 WESTERN DISTRICT OF VIRGINIA Laura a. austin, cLERK CHARLOTTESVILLE DIVISION BY: s/CARMEN AMOS DEPUTY CLERK

TILLMAN INFRASTRUCTURE LLC, CASE No. 3:21-cv-00040 Plaintiff, v. MEMORANDUM OPINION THE BOARD OF SUPERVISORS OF CULPEPER COUNTY, VIRGINIA, et al., JUDGE NORMAN K. Moon Defendants. Plaintiff Tillman Infrastructure LLC alleges that Culpeper County, Virginia, and the Board of Supervisors of Culpeper County (collectively, “Defendants”) wrongfully denied its application for a conditional use permit to build a telecommunications tower. Both parties have moved for summary judgment. Plaintiff's Summary Judgment Motion will be granted because substantial evidence does not support the Board’s denial of Plaintiff's application and because the Board did not timely approve or disapprove Plaintiff's complete application. On these grounds, Defendants’ Summary Judgment Motion will also be denied.

Background Tillman is a telecommunications company that invests in and manages cell towers and other telecommunications infrastructure. Dkt. 25 § 2. On March 22, 2021, Tillman submitted paperwork to Culpeper County, proposing to construct a new telecommunications tower in the City of Rapidan, an area in the County. Dkt. 36-4 at 3-4. The paperwork stated that the “proposed site will allow wireless carriers to improve the quality of services for their customers in Culpeper County and the City of Rapidan.” /d. at 4. It also noted that the proposed tower is

designed to accommodate up to four carriers and be designed as a 195-foot self-support structure with an additional four-foot lightning rod. Id. At the time Tillman submitted its application, only one telecommunications tower was in the Rapidan area. Dkt. 36 ¶ 5. That 199-foot monopole tower (the “SBA Tower”) had been approved for construction by the Culpeper County Board of Supervisors in April 2001 and is

owned by SBA Towers III, LLC (“SBA”). Dkt. 41 at 2. AT&T and Verizon Wireless lease space at the SBA Tower for placement of communications equipment. Id. at 2. Claiming unreasonable fees and costs to use the SBA Tower, AT&T sought to work with Tillman to build a more affordable tower in the area. See id. at 3. The proposed tower was to be built in the Cedar Mountain Battlefield area, Dkt. 41-17 at 2–3, and located 0.54 miles from N. James Madison Highway, a designated Virginia Scenic Byway, Dkt. 36-12 at 94. On April 8, 2021, the Zoning Administrator emailed the Tillman representative: In an abundance of caution[,] I am writing to confirm that your complete submission is still under a dropbox folder named: 15862-Pre-App Zoning Package and contains 16 files in total?

I want to make sure these files are indeed the finalized submission and not earlier versions that you uploaded for the pre-app meeting.

Maybe rename the folder and reshare?

Any case please confirm that these are the latest.

Id. at 45, 58 (emphasis in original). On that same day, the Tillman representative responded that she had “renamed the folder ‘15682-Zoning Application Package’” and clarified “[t]here are 17 docs in all.” Id. at 46, 57. The Zoning Administrator replied by thanking the representative “for buttoning things up” and stated he would “be in touch if [he saw] something missing.” Id. at 51, 56. The Tillman representative then emailed a scanned copy of a check for the application fee. Id. at 54–55. The County contracted CTA Consultants, LLC (“CTA”) to provide a comprehension review of Tillman’s conditional use permit application and its proposed tower. Dkt. 36-4 at 245. In CTA’s technical review report, issued on May 12, 2021, it found that Tillman’s application complied “with the County’s application process, tower ordinances, and other applicable codes for telecommunications support structures.” Id. To remain in compliance with County

ordinances, CTA recommended several conditions, including that “AT&T FirstNet equipment must be present on the proposed tower after construction for the new tower to be considered an emergency service tower.” Id. The County Department of Development Planning and Zoning staff agreed with CTA’s recommendation. Dkt. 36-12 at 85. On June 9, 2021, the County Planning Commission held a public hearing. Dkt. 36-4 at 138. Prior to the hearing, SBA’s counsel sent a letter of opposition on June 7, 2021, claiming the proposed tower was not needed and that the SBA Tower provided sufficient coverage. Dkt. 36-7 at 6. Following the hearing, the Commission recommended by a unanimous vote that the Board approve the application with certain conditions, including

requiring Tillman to install FirstNet for its tower to qualify as an emergency service tower. Dkt. 36-4 at 139. The Commission also found by an 8–1 vote that “the subject-proposal’s general or approximate location, character and extent are substantially in accord with the County’s Comprehensive Plan.” Id. at 138. On July 6, 2021, the Board considered Tillman’s application at a public hearing. See Dkt. 36-13 at 69–168. Prior to the hearing, Supervisor Frazier asked Tillman to convert its tower design from a lattice-design to a monopole-design. Id. at 88. During the hearing, the Tillman representative stated that Tillman would change its design to a monopole-design. Id. At the conclusion of the hearing, the Board decided to defer voting on the application to allow SBA and AT&T time to negotiate an agreement. Id. at 118–22. The Board hoped they could find an agreement whereby AT&T would not need another tower to be built in the area. Id. In an email sent on July 29, 2021, the County Director of Planning and Zoning Samuel McLearen stated: Just an FYI. I received this [attachment] yesterday relating to the Tillman Infrastructure cell tower use permit request that is scheduled to come back to the [Board] in October. I am filing this with the case file information. Basically[,] they submitted documentation as part of their ongoing NEPA certification/review stating their proposed structure is now a “monopole” and not a lattice structure. Same height, so it really doesn’t impact our review.

Free access — add to your briefcase to read the full text and ask questions with AI

Tillman Infrastructure LLC v. The Board of Supervisors of Culpeper County, Virginia, (W.D. Va. 2022).

Tillman Infrastructure LLC v. The Board of Supervisors of Culpeper County, Virginia (Tillman Infrastructure LLC v. The Board of Supervisors of Culpeper County, Virginia) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

T-MOBILE NORTHEAST LLC v. City of Newport News
674 F.3d 380 (Fourth Circuit, 2012)
Sylvia Development Corporation v. Calvert County
48 F.3d 810 (Fourth Circuit, 1995)
Variety Stores, Inc. v. Wal-Mart Stores, Inc.
888 F.3d 651 (Fourth Circuit, 2018)