Tillman Infrastructure LLC v. Board of Supervisors of Culpeper County, Virginia
Opinion
UNPUBLISHED
UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT
No. 23-1094
TILLMAN INFRASTRUCTURE LLC, Plaintiff – Appellee,
v.
BOARD OF SUPERVISORS OF CULPEPER COUNTY, VIRGINIA; CULPEPER COUNTY, VIRGINIA,
Defendants – Appellees.
Appeal from the United States District Court for the Western District of Virginia, at Charlottesville. Norman K. Moon, Senior District Judge. (3:21-cv-00040-NKM-JCH)
Argued: March 5, 2024 Decided: August 13, 2025
Before DIAZ, Chief Judge, and RICHARDSON and RUSHING, Circuit Judges.
Affirmed by unpublished opinion. Judge Rushing wrote the opinion, in which Chief Judge Diaz and Judge Richardson joined.
ARGUED: Michael W.S. Lockaby, SPILMAN, THOMAS & BATTLE, PLLC, Roanoke, Virginia, for Appellants. Bethany Jean Fogerty, WILLCOX & SAVAGE, P.C., Norfolk, Virginia, for Appellee. ON BRIEF: Gary A. Bryant, WILLCOX & SAVAGE, P.C., Norfolk, Virginia, for Appellee.
Unpublished opinions are not binding precedent in this circuit.
RUSHING, Circuit Judge:
Tillman Infrastructure LLC sought a conditional use permit to build a telecommunications tower in Culpeper County, Virginia. The County’s Board of Supervisors denied Tillman’s application, so Tillman sued in federal court. Following cross-motions for summary judgment, the district court held that the Board’s denial was not supported by substantial evidence and was void in any event because Tillman’s application was deemed approved as a matter of state law when the Board failed to approve or disapprove it within 150 days of receipt. Because the latter ground is sufficient to resolve the case, we affirm on that basis.
I.
To construct a telecommunications tower in Culpeper County, Tillman applied for a conditional use permit in accordance with local zoning regulations. See Culpeper Cnty., Va., Code of Ordinances app. A Zoning Ordinance (ZO) §§ 17-1, 17-2, 17-6 (Feb. 2021). Tillman attended a pre-application meeting with county officials, including Zoning Administrator Neil Drumheller, in March 2021. Before the meeting, Tillman shared with county officials a digital Dropbox folder titled “15862-Pre-App Zoning Package.” J.A. 1660–1661. A couple of weeks later, on April 8, Drumheller contacted Tillman “to confirm” whether the shared folder was Tillman’s “finalized submission.” J.A. 1672. He suggested that Tillman “rename the folder and reshare” it. J.A. 1672. Tillman did so immediately, renaming the folder “15682-Zoning Application Package.” J.A. 1673. The application package contained several documents, including an application form, an application letter, a supplemental narrative, a structural design analysis, and various
exhibits. Tillman also submitted the required application fee. The same day, Drumheller confirmed receipt, thanked Tillman for “buttoning things up,” and advised that he would “be in touch if [he saw] something missing.” J.A. 1678.
After receiving Tillman’s materials, the County forwarded them to state agencies and a third-party consulting firm, CTA Consultants LLC, for review. CTA recommended approval subject to installation of emergency communication services on the tower and a “new structural analysis.” J.A. 587. Tillman accordingly submitted a revised structural analysis on May 12, 2021. The County Planning Commission subsequently held a public hearing and concluded that Tillman’s application was substantially in accord with the County’s Comprehensive Plan.
The Board of Supervisors considered Tillman’s application at its July 6, 2021, meeting but did not issue a decision. In response to a request from one of the supervisors, Tillman amended its application later that month to propose a monopole tower rather than a lattice tower. County staff indicated to Drumheller that the amendment “doesn’t impact our review.” J.A. 1381. On October 5, 2021, the Board met again and voted to deny Tillman’s application.
Tillman sued. It alleged that the Board violated the Telecommunications Act of 1996 because the denial was not supported by substantial evidence, 47 U.S.C. § 332(c)(7)(B)(iii), and unreasonably discriminated against Tillman’s proposed tower, id. § 332(c)(7)(B)(i). Tillman also brought state law claims, alleging that the Board based its denial on impermissible considerations, Va. Code Ann. § 15.2-2316.4:2(A)(1), and unlawfully discriminated against Tillman, id. § 15.2-2316.4:2. Finally, Tillman alleged
that the Board failed to decide its application within 150 days as required by state law and requested a declaratory judgment that the denial was therefore void and its application was deemed approved by operation of law. See id. § 15.2-2316.4:1(C)(2)(a), (D).
The parties cross-moved for summary judgment, and the district court granted judgment for Tillman. The court concluded that substantial evidence did not support the Board’s denial and that Tillman’s application had already been approved by operation of law at the time of that decision. See Tillman Infrastructure LLC v. Bd. of Supervisors of Culpeper Cnty., Va., 648 F. Supp. 3d 731, 744, 746 (W.D. Va. 2022). The court then dismissed Tillman’s remaining claims as moot. The Board appealed.
II.
We review the district court’s award of summary judgment de novo. T.H.E. Ins.
Co. v. Davis, 54 F.4th 805, 818 (4th Cir. 2022). Summary judgment is appropriate if, viewing the facts in the light most favorable to the Board, Tillman shows there is no genuine dispute as to any material fact and Tillman is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(a).
Virginia law requires localities to act on zoning applications for wireless communications towers within timelines set by statute. Two statutory deadlines are relevant here. First, if a locality receives an incomplete permit application, it must notify the applicant of any deficiencies “[w]ithin 10 business days after receiving [the] incomplete application.” Va. Code Ann. § 15.2-2316.4:1(C)(1). “If the locality fails to provide such notice within such 10-day period, the application shall be deemed complete.” Id. Second, a locality must “approve or disapprove” a zoning application for a new wireless
communications tower “within the lesser of 150 days of receipt of the completed application or the period required by federal law for such approval or disapproval.” Id. § 15.2-2316.4:1(C)(2)(a). This period “may be extended by mutual agreement between the applicant and the locality.” Id. § 15.2-2316.4:1(C)(3). “A complete application for a project shall be deemed approved if the locality fails to approve or disapprove the application within the [statutory] period . . . or any agreed extension thereof . . . .” Id. § 15.2-2316.4:1(D).
We agree with the district court that these straightforward rules resolve this case.
The County received Tillman’s application on April 8, 2021. That was the day Tillman transmitted its “finalized submission” by renaming its “15862-Pre-App Zoning Package” to “15682-Zoning Application Package,” resharing it with the County, and submitting the required application fee. J.A. 1660–1661, 1672–1673. The same day, Drumheller confirmed receipt. The parties agree that the record contains no evidence of the County notifying Tillman that its application was incomplete at any time over the next 10 business days. Thus, the April 8 application was “deemed complete.” Va. Code Ann. § 15.2- 2316.4:1(C)(1). Having received Tillman’s “complete application,” the County then had 150 days to “approve or disapprove” it, as the parties agree no federal deadline controls here and the record contains no evidence of any extension by mutual agreement. Id. § 15.2- 2316.4:1(C)(2)(a), (C)(3). Yet the Board did not deny Tillman’s application until October 5, 2021—180 days after April 8. Because the Board “fail[ed] to approve or disapprove the application within the applicable [statutory] period,” Tillman’s application had already
been “deemed approved” by operation of law before the Board conducted its tardy vote. Id. § 15.2-2316.4:1(D).
Free access — add to your briefcase to read the full text and ask questions with AI
Tillman Infrastructure LLC v. Board of Supervisors of Culpeper County, Virginia (Tillman Infrastructure LLC v. Board of Supervisors of Culpeper County, Virginia) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.