TIG Ins v. Woodsboro Farmers Coop

117 F.4th 715
CourtCourt of Appeals for the Fifth Circuit
DecidedSeptember 20, 2024
Docket23-40435
StatusPublished
Cited by2 cases

This text of 117 F.4th 715 (TIG Ins v. Woodsboro Farmers Coop) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TIG Ins v. Woodsboro Farmers Coop, 117 F.4th 715 (5th Cir. 2024).

Opinion

Case: 23-40435 Document: 65-1 Page: 1 Date Filed: 09/20/2024

United States Court of Appeals for the Fifth Circuit United States Court of Appeals Fifth Circuit

____________ FILED September 20, 2024 No. 23-40435 Lyle W. Cayce ____________ Clerk

TIG Insurance Company, as successor by merger to American Safety Indemnity Company,

Plaintiff—Appellee,

versus

Woodsboro Farmers Cooperative,

Defendant—Appellant. ______________________________

Appeal from the United States District Court for the Southern District of Texas USDC No. 5:18-CV-191 ______________________________

Before Dennis, Southwick, and Ho, Circuit Judges. Leslie H. Southwick, Circuit Judge. In this insurance-coverage action, we must decide what constitutes “property damage” that would invoke an insurer’s obligation to indemnify under a common Commercial General Liability insurance policy. The district court determined there was no property damage under the policy, and the insurer therefore had no duty to indemnify the insured for an adverse state arbitration award. We find there to be fact questions that invalidate the grant of summary judgment. We REVERSE and REMAND. Case: 23-40435 Document: 65-1 Page: 2 Date Filed: 09/20/2024

No. 23-40435

FACTUAL AND PROCEDURAL BACKGROUND In March 2013, Woodsboro Farmers Cooperative contracted with E.F. Erwin, Inc. to construct two Brock 105’ diameter grain silos in Woodsboro, Texas. Erwin hired subcontractor AJ Constructors, Inc. (“AJC”) to construct the silos, and Erwin was responsible for supervising the work. Though the contracts had no deadline, Erwin told Woodsboro that the silos, or at least their bins, would be ready by June or July — in time for the 2013 harvest. Brock silos start as kits shipped from the manufacturer and are then assembled according to the manufacturer’s manuals and specifications. The kits include prefabricated metal walls, roof sheets, and other items necessary for construction. The silos are constructed section by section, starting with the roof. The prefabricated, corrugated metal walls are bolted together to form a ring, and the roof is raised and secured to the first ring with purlins, joists, and struts. The first ring is then jacked up and the next ring is bolted to the first. The process continues until the silo is fully assembled. In short, constructing a silo is a matter of assembly. It requires putting the pieces together pursuant to the manufacturer’s instructions.1 AJC began erecting the silos in May 2013 and completed its work in June or early July. At various stages, Erwin inspected the quality and progress of AJC’s work. Although Erwin observed some cosmetic problems in the roofing, he determined the silos were structurally sound and not defective. AJC left the job site after completing the assembly. Erwin completed the rest of the project on November 1, 2013, and signed an affidavit of completion as required by the contract with Woodsboro.

_____________________ 1 There are other aspects of the job, e.g., laying a concrete foundation and post- assembly millwright and electrical work. This case, however, concerns only the assembly.

2 Case: 23-40435 Document: 65-1 Page: 3 Date Filed: 09/20/2024

According to Woodsboro, at this time Erwin represented that the silos were ready to be used as intended. Before Woodsboro tendered its final payment, it noticed several defects that caused the silos to leak. To address the leaks, Woodsboro and Erwin signed an addendum to their original contract in late November 26, 2013. Woodsboro agreed to make the final payment to Erwin as consideration for repairing a list of deficiencies for each silo. Sometime between November 2013 and May 2014, Erwin attempted to repair the defects but was unable to make them watertight. When it became clear Erwin would not be able to fully repair the silos, Woodsboro contacted Buck Pitcock of Pitcock Supply, Inc., to inspect them. Pitcock observed numerous faults with the silos’ assembly, including missing or loose bolts; gaps in the tank walls and ceiling; incorrectly installed tank stiffeners; improper sealing; and unsecured roofing. Pitcock concluded that the failure to secure the roofs properly allowed them to “flex and move” in the wind and weather, causing the silos’ metal parts to fatigue and bend. As the overall condition of the silos deteriorated, damage from wind and weather accelerated. This could have led the entire structures to fail. Pitcock attributed the damage to AJC’s “poor workmanship.” Because the silos are constructed by jacking up each section, starting with the roof, they had to be deconstructed in their entirety to fix the damage and then reconstructed. It is undisputed that Woodsboro had to take these steps to fix the problem. In March 2015, Woodsboro hired Pitcock Supply to repair the silos. New Brock kits were purchased because certain parts were so damaged they could not be re-used. When Pitcock Supply finished its work in June, Woodsboro’s total cost was $805,642.74. In August 2014, Woodsboro sued Erwin in Texas state court for breach of contract. In 2017, the case was sent to an arbitration panel. The

3 Case: 23-40435 Document: 65-1 Page: 4 Date Filed: 09/20/2024

panel found AJC had negligently constructed the silos; the silos were defective and did not conform to the construction contract and subcontract; and Erwin was unwilling or unable to repair them. The panel awarded Woodsboro a total of $988,073.25 in damages.2 In October 2018, Woodsboro moved for the Texas state court to confirm the award, and then in November asked the arbitration panel to amend the award to account for certain costs. The motion to confirm was pending for nearly four years before the court issued a final judgment confirming the award in September 2022. In December 2018, TIG Insurance Company, successor by merger to American Safety Indemnity Company (“TIG”), sued Woodsboro and Erwin in the United States District Court for the Southern District of Texas. TIG invoked diversity jurisdiction and sought declaratory relief on its duty to defend and indemnify as Erwin’s insurer. Woodsboro and Erwin then moved to dismiss for lack of subject matter jurisdiction, arguing the matter was not ripe for adjudication because the Texas state court had not yet issued a final judgment, leaving TIG without standing. The district court denied the motion because, even if the issue of TIG’s duty to indemnify was not ripe, the issue of its duty to defend was ripe and was sufficient to provide standing. In March 2022, the district court ruled on the parties’ cross-motions for summary judgment. The court granted TIG’s motion as to its duty to defend, finding the underlying pleadings failed to show that Erwin’s breaches resulted in “property damage” required for coverage under the policy and, even if such damage existed, several exclusions would apply. See VRV Dev. L.P. v. Mid-Continent Cas. Co., 630 F.3d 451, 456–57 (5th Cir. 2011). The court did not rule on the issue of indemnity because final judgment in the _____________________ 2 Woodsboro’s net award, including prejudgment interest and attorneys’ fees, was $1,300,241.39. Erwin was awarded a total recovery of $1,079,963.81 against AJC. Arbitration costs were divided between Erwin and AJC.

4 Case: 23-40435 Document: 65-1 Page: 5 Date Filed: 09/20/2024

underlying case had not yet issued. Thereafter, Woodsboro and Erwin filed another motion to dismiss for lack of jurisdiction, but by the time the district court ruled on the motion in October 2022, the state court had entered a final judgment and the issue of indemnity was ripe. In June 2023, the district court granted the remainder of TIG’s motion for summary judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
117 F.4th 715, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tig-ins-v-woodsboro-farmers-coop-ca5-2024.