Thurber v. Ryan

12 Kan. 453
Supreme Court of Kansas·Decided January 15, 1874·Published·Cited by 8 cases

Opinion

The opinion of the court was delivered by

Brewer, J.:

In this case a preliminary question arises on the “case made.” The action was tried in the district court [455] of Greenwood county, and judgment rendered on March 4th, 1873. Thirty days were given to make a case. On March 13th, 1873, a law took effect * which detached Greenwood county from the 13th and attached it to the 5th judicial district. (Laws 1873, p. 168.) By that law the judge who tried the case ceased to be judge of the district court of Greenwood county, and the judge of the 5th district was vested with all the powers of the judge of that court. Notwithstanding this, the trial-judge thereafter, and on the 1st of April 1873, signed and certified the “case made.” Is this “case made” so signed and certified as to be a sufficient record for review in this court? The law of 1873 above cited makes no provision for a completion by the acting judge of work partially performed. It simply transfers the county from one district to another. But in 1870 a law was passed which provides that in all cases when the term of office of the trial-judge shall expire before the time fixed for settling and signing a case, it shall be his duty to settle and sign the same in all respects as if his term had not expired. In Wisconsin it is held, even in the absence of any statute, that the judge who tried the case may settle and sign a bill of exceptions, although he may be at the time out of office: Fellows v. Tait, 14 Wis., 156; Davis v. The President of the Village of Menasha, 20 Wis., 194; Hale v. Haselton, 21 Wis., 320. Whether such ruling could be sustained under our statutes, may not be clear. But we think it no strained and violent construction of the language, to hold the law of 1870 applicable to the ease at bar. The judge who tried this case ceased to be judge of the district court of Greenwood county on the 13th of March. In one sense, and that a sense appropriate to the purpose of this statute, his term of office as judge of that court then expired.

The principal questions arise on the construction of a contract. Murphy & Ryan, sub-contractors, had a contract to furnish the material and do the stone work in the erection of a court-house at Eureka. They entered into a contract with [456] one John W. Berry to furnish the material. After the latter had done some work thereunder, he, with the consent of Murphy & Ryan, assigned his contract to the plaintiffs in error, who by written agreement assumed all of Berry’s obligations under said contract. They delivered some material, but after the expiration of a month, and on the 27th of February 1872, refused to deliver any more. This action was brought to recover damages for such refusal. Plaintiffs in error claim that Murphy & Ryan were guilty of the first breach, and that therefore they were justified in refusing to deliver any more material. The breach they allege is a failure to pay, at the expiration of a month, for the material delivered during that month. The contract in terms stipulates for payments in monthly instalments, and it is undisputed that they delivered material during an entire month, and then, receiving no pay, stopped work. On the other hand it is claimed that by the contract of Berry, and subsequent agreement of the plaintiffs in error, Murphy & Ryan were to pay only upon the estimate of the architect, and that until such estimates were made they were under no obligations to make payment. This we think is correct. The contract, after describing the kind of stone to be delivered, and the purpose for which it was to be used, provides that “All of said stone shall be of good quality, such as shall be approved by J. G. Haskell, Esq., the architect of said court-house,” and also that Murphy & Ryan shall pay “the sum of four dollars per cord for the quantity of stone so delivered, it being agreed by the parties hereto that said stone shall be measured in the wall of said court-house building.” The subsequent agreement signed by all the parties, after referring to the original contract and assignment, and stipulating that no change in its terms and obligations is made by this agreement, recites the existence of certain indebtedness, and stipulates “that after the first estimate is made by J. G. Haskell, the architect of said courthouse,” a certain debt shall be paid out of the moneys due, and whatever is left shall be paid to plaintiffs in error; “that the second estimate shall be paid” to plaintiffs in error, or [457] according to their direction; “that before the final estimate shall be made on said court-house as aforesaid, the whole of said liabilities shall be fully discharged,” and also “that if after the final estimate is made there should be a balance due” it should be paid to the plaintiffs in error. These several stipulations, fairly construed, show that the parties contemplated monthly payments uppn the architect’s estimates, and that the defendants in error were guilty of no breach of the contract in waiting at the end of the month for the estimate of the architect before making payment. It is undisputed that all estimates made before the 27th of February had been fully paid prior to that day. Nothing therefore was due and payable until the making of another estimate."* There was no error in the ruling of the district court upon this question.

Free access — add to your briefcase to read the full text and ask questions with AI

Thurber v. Ryan, 12 Kan. 453 (kan 1874).

12 Kan. 453 (Thurber v. Ryan) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Fugh Coal Co. v. City of Pittsburgh
70 Pa. D. & C. 299 (Alleghany County Court of Common Pleas, 1949)
N. S. Sherman MacHine & Iron Works v. Carey, Lombard, Young & Co.
1924 OK 549 (Supreme Court of Oklahoma, 1924)
Burnett v. Davis
1910 OK 263 (Supreme Court of Oklahoma, 1910)
Barnes v. Lynch
1899 OK 1 (Supreme Court of Oklahoma, 1899)
St. Louis & San Francisco Railway Co. v. Corser
31 Kan. 705 (Supreme Court of Kansas, 1884)
Taylor v. Mason
28 Kan. 381 (Supreme Court of Kansas, 1882)
M. K. & T. Railway Co. v. City of Fort Scott
15 Kan. 435 (Supreme Court of Kansas, 1875)