Thunderbird Engineering, Inc. v. American Design, Inc.

CourtCourt of Appeals of Wisconsin
DecidedJuly 7, 2023
Docket2021AP001985
StatusUnpublished

This text of Thunderbird Engineering, Inc. v. American Design, Inc. (Thunderbird Engineering, Inc. v. American Design, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thunderbird Engineering, Inc. v. American Design, Inc., (Wis. Ct. App. 2023).

Opinion

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. July 7, 2023 A party may file with the Supreme Court a Samuel A. Christensen petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2021AP1985 Cir. Ct. No. 2019CV2861

STATE OF WISCONSIN IN COURT OF APPEALS DISTRICT IV

THUNDERBIRD ENGINEERING, INC.,

PLAINTIFF-APPELLANT,

V.

AMERICAN DESIGN, INC. AND JOHN T. WILLIAMS,

DEFENDANTS-RESPONDENTS.

APPEAL from an order of the circuit court for Dane County: STEPHEN E. EHLKE, Judge. Affirmed.

Before Fitzpatrick, Graham, and Nashold, JJ.

Per curiam opinions may not be cited in any court of this state as precedent or

authority, except for the limited purposes specified in WIS. STAT. RULE 809.23(3).

¶1 PER CURIAM. Thunderbird Engineering, Inc. (“Thunderbird”) appeals an order denying its request for exemplary damages and partially denying No. 2021AP1985

its request for attorney fees pursuant to WIS. STAT. § 895.446(3) (2021-22).1 Thunderbird also appeals the circuit court’s ruling denying its requests for attorney fees under WIS. STAT. § 802.05(3) associated with responding to an unsuccessful request for sanctions filed by American Design, Inc. (“American Design”) and John Williams (collectively, “Defendants”), and under WIS. STAT. § 804.12(2) for Defendants’ alleged discovery violations. We affirm.

BACKGROUND

¶2 This appeal arises in a somewhat unique procedural posture. The circuit court granted summary judgment to Thunderbird on its breach-of-contract and theft-by-contractor claims after Defendants failed to respond to Thunderbird’s requests for admission. Defendants do not challenge the court’s order granting summary judgment against them. Instead, Thunderbird appeals the court’s denial of its request for exemplary damages and the court’s award of only partial attorney fees on Thunderbird’s theft-by-contractor claims. Therefore, the following background focuses on facts relevant to these limited issues.

¶3 American Design is an architectural firm, with Williams as its president, majority owner, and sole active officer. In 2018, American Design entered into contracts to serve as the prime contractor for the renovation of two buildings in Milwaukee: the Andrew S. Douglas School (“Douglas project”), owned by the Milwaukee Public Schools (“MPS”); and the Merchant & Farmers State Bank Building (“Bader project”), owned by Bader Philanthropies, Inc.

1 All references to the Wisconsin Statutes are to the 2021-22 version unless otherwise noted.

2 No. 2021AP1985

¶4 American Design hired Thunderbird as one of its subcontractors, to perform HVAC, plumbing, and electrical services on both projects. Shawn Woldt is the president of Thunderbird.

¶5 American Design and Thunderbird entered into contracts for the Douglas and Bader projects (the “Douglas contract” and “Bader contract,” respectively). The Douglas contract required that American Design “attempt” to pay Thunderbird for its services within thirty days of receiving payment from MPS. The Bader contract required that American Design pay Thunderbird “promptly” after receiving payments from Bader Philanthropies, Inc. In addition, each contract required Thunderbird to name each project owner, MPS and Bader Philanthropies, respectively, as an additional insured under its general liability and umbrella liability insurance policies. Thunderbird’s failure to comply with these insurance requirements could result in American Design being in breach of its contract with the project owners.

¶6 Over the course of the projects, MPS and Bader Philanthropies timely paid American Design approximately $380,000. Out of those funds, American Design would ultimately owe Thunderbird a total of $87,495 for its work on the Douglas project and $41,520 for its work on the Bader project.

Douglas Project

¶7 Thunderbird’s work on the Douglas project began in late 2018 or early 2019, with most of the work completed by August 2019. On October 3, 2018, American Design’s office manager, Beverly Helbling, emailed Thunderbird’s business manager, requesting that Thunderbird send Helbling a copy of Thunderbird’s certificate of insurance (“COI”) naming MPS as an additional insured on its policies, as the contract required. Helbling repeated this request in

3 No. 2021AP1985

emails sent on December 10 and 12, 2018. Despite Thunderbird’s attempts to rectify the insurance issues, as of April 4, 2019, Thunderbird still had not satisfied the contract requirement that MPS be included as an additional insured. In addition, as the circuit court found, there continued to be “legitimate concerns regarding insurance in the months after April of 2019,” which “[e]ven Mr. Woldt admitted [to] in his deposition testimony.” Thunderbird did not produce a COI for the Douglas project containing the correct “additional insured” language until March 12, 2021, a few weeks before trial.2

¶8 In addition to the insurance issues, there were also issues involving Thunderbird’s failure to sign the Douglas contract. In November 2018, Helbling notified Thunderbird that American Design had not yet received a signed copy of the contract and Helbling twice emailed Thunderbird the contract for signature. About seven months later, in June 2019, following Woldt’s complaints to American Design about payment delays, Williams explained that he had needed to apply his “executive override” to pay Thunderbird because Woldt had not signed the contract. Williams requested that Woldt sign the contract. In July 2019, there were still ongoing emails and discussions about getting the Douglas contract signed, with Thunderbird ultimately signing the contract on July 23, 2019.

2 Defendants state that, by the start of trial, American Design had asked Thunderbird to provide a compliant COI nine times but never received one. Thunderbird argues that this is a “blatant mischaracterization of the evidence.” However, in support of this assertion, Thunderbird cites, among other things, Woldt’s own testimony at trial in which he twice agreed that Defendants had requested the insurance information nine times before receiving it. We therefore question Thunderbird’s characterization of Defendants’ statement as a “blatant mischaracterization.” It is unnecessary for purposes of our decision in this case, however, to determine the exact number of times that Defendants requested the COI. The circuit court concluded that there were ongoing “legitimate” concerns about the insurance issues, extending up through and after April 2019. Although Thunderbird argues that the insurance concerns expressed by Defendants were only a “pretext to cover up Defendants’ misuse of the project funds,” Thunderbird has not shown—or even argued—that the court’s contrary finding that Defendants’ insurance concerns were “legitimate” is clearly erroneous. See WIS. STAT. § 805.17(2).

4 No. 2021AP1985

¶9 During the same time period in which the parties were attempting to resolve the insurance and contract signature issues, Thunderbird was also attempting to obtain payments from American Design for work that Thunderbird had performed. In November 2018, Thunderbird attempted to send its first invoice to American Design but sent it to the wrong email address. Although the contract required that invoices be sent to Helbling, Woldt either attempted to or did email the November invoice to Williams instead.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Pettit
492 N.W.2d 633 (Court of Appeals of Wisconsin, 1992)
Ten Mile Investments, LLC v. Sherman
2007 WI App 253 (Court of Appeals of Wisconsin, 2007)
Gaugert v. Duve
2001 WI 83 (Wisconsin Supreme Court, 2001)
State v. Wolter
270 N.W.2d 230 (Court of Appeals of Wisconsin, 1978)
Schlieper v. State Department of Natural Resources
525 N.W.2d 99 (Court of Appeals of Wisconsin, 1994)
Tri-Tech Corp. of America v. Americomp Services, Inc.
2002 WI 88 (Wisconsin Supreme Court, 2002)
Shopko Stores, Inc. v. Kujak
433 N.W.2d 618 (Court of Appeals of Wisconsin, 1988)
Imposition of Sanctions in Alt v. Cline
589 N.W.2d 21 (Wisconsin Supreme Court, 1999)
Stathus v. Horst
2003 WI App 28 (Court of Appeals of Wisconsin, 2003)
Estate of Stanley G. Miller v. Diane Storey
2017 WI 99 (Wisconsin Supreme Court, 2017)
Maryland Arms Ltd. Partnership v. Connell
2010 WI 64 (Wisconsin Supreme Court, 2010)
Barrows v. American Family Insurance
2014 WI App 11 (Court of Appeals of Wisconsin, 2013)
Laughland v. Beckett
2015 WI App 70 (Court of Appeals of Wisconsin, 2015)
CoVantage Credit Union v. Stangel (In re Stangel)
593 B.R. 607 (E.D. Wisconsin, 2018)
Century Fence Company v. American Sewer Services, Inc.
2021 WI App 75 (Court of Appeals of Wisconsin, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Thunderbird Engineering, Inc. v. American Design, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/thunderbird-engineering-inc-v-american-design-inc-wisctapp-2023.