Thunder Bay Quarries Co. v. Pollard

3 N.W.2d 316, 301 Mich. 388, 1942 Mich. LEXIS 552
CourtMichigan Supreme Court
DecidedApril 6, 1942
DocketDocket No. 41, Calendar No. 41,845.
StatusPublished
Cited by1 cases

This text of 3 N.W.2d 316 (Thunder Bay Quarries Co. v. Pollard) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thunder Bay Quarries Co. v. Pollard, 3 N.W.2d 316, 301 Mich. 388, 1942 Mich. LEXIS 552 (Mich. 1942).

Opinion

Butzel, J.

On May 20, 1938, defendant B. J. Pollard, who was engaged in the business of selling stone, obtained an order from the Works Progress Administration of the Federal government for 30,000 tons of crushed stone of an odd size, to be used by the W.P.A. for pavement of alleys. Pollard rented a parcel of property of approximately 13 acres on West Fort street, Detroit, Michigan. It has a frontage on one side of 625 feet, or thereabouts, abutting on the Rouge river, near where it runs into the Detroit river. The government contract was elastic in that it gave the government the privilege of increasing or decreasing the order to the extent of 25 per cent. The contract provided that deliveries could not be made without the government’s consent after June 30, 1938. The government accepted delivery of the full 30,000 tons and evidently a cancellation had not been anticipated. The crushed stone was not of a standard size carried by quarries and as a rule would have to be manufactured, although in this particular case it could largely be gathered together from the small pieces left over in the quarrying of large-sized stone. Pollard negotiated with the Thunder Bay Quarries Company, plaintiff herein, for stone to fill the government contract. Just what the agreement with the plaintiff was became one of the main issues of the present litigation. It is con *393 ceded that plaintiff was to furnish stone at 90 cents per ton less 5 cents discount should payment be made in 30 days.

Pollard claims that he ordered only one boatload of stone on May 20,1938, and it was shipped June 2, 1938, by the steamship George P. Rand. It was delivered at Pollard’s dock with the charges paid by plaintiff in accordance with a purchase order for one boatload of the stone, signed by Pollard, sent plaintiff. Pollard’s dock consisted of unimproved property on the Rouge river. Pollard had covered part of it with a sprinkling of lime waste, evidently to keep the stone clean when it arrived. This dock, consisting of land abutting the shore, had no reinforcement or artificial support either under or on the surface along the bank. Shortly after the delivery of this first cargo consisting of 9,689 tons, and after some telephone conversations, two other shipments were made. On June 16,1938, 8,791 tons, and on July 8,1938, 9,573 tons, of the specified stone were consigned to Pollard by the steamer Consumers Power. All of plaintiff’s three bills referred to order C 229. The second shipment was made after plaintiff received a letter signed by Pollard. It stated that:

“Relative to our telephone conversation of June 9th, about placing second cargo of stone on my dock to apply on W.P.A. order 51 34182 this material to be billed as of date when 75 per cent, of present cargo has been removed. I further agree that none of this material will be used to fill any other than above-mentioned order.”

The third shipment was sent after the receipt of a letter from Pollard, which stated:

‘ ‘ This is to authorize the placing of 3d cargo of 4" down stone on my dock in Detroit.' Billing to be *394 made as of -when 75 per cent, of 2d cargo has been used by W.P.A.
“It is agreed by me that none of this stone will be used to fill any orders other than W.P.A. 51 34182.”

The order for the first shipment did not contain the agreement by Pollard that the material would not be used to fill any order other than this specific one from the W.P.A., but the stone of odd size was ordered for this purpose. At the time that the second shipment was made by plaintiff, no part of the stone from the first shipment had been delivered to the government. At the time the third shipment was made, a small quantity, less than either of the first two shipments, had been delivered to the government. However, the government was beginning to take a substantial amount almost at regular short intervals of a day" or two from and after July 1, 1938.

Eleven hours and 35 minutes after the completion of the unloading of the third shipment on Pollard’s dock, the bank of the river gave way and sheared off and an undetermined portion of the stone piled thereon slid into the river. Some of the stone was retrieved but 3,180 tons were never recovered. Pollard was ordered by the United States War department to clear the river of the stone in order to restore the navigability.of the stream and he was put to a large expense in recovering part of the stone. One of the main controversies-in the case is, Who is responsible for the loss of the stone that was not retrieved and for the expense of recovering that which was salvaged?

Because plaintiff was unwilling to extend credit to Pollard either for the large amounts that would become due it, and inasmuch as Pollard’s credit was not too strong, and the government would not permit *395 the assignment of the proceeds of the contract, Pollard agreed that the government should forward its cheeks, made payable to Pollard, to plaintiff, and that Pqllard would thereupon indorse them over to plaintiff up to the amount of his indebtedness. This agreement was assented to by the government. Pollard at first for some time carried out this agreement after the slide occurred. Later, however, when plaintiff presented checks to him for indorsement, he retained them and refused to return them to plaintiff. The latter thereupon filed a bill for specific performance in the instant case to compel Pollard to turn over the checks duly indorsed to it according to the agreement. Pollard, in turn, in addition to his answer, filed a cross bill in which he impleaded the American Steamship Company, which owned the steamer Consumers Power, and also Boland and Cornelius, its managing agents, as defendants. The steamship company and agents finally withdrew their objections to being thus impleaded so that the entire controversy could be settled in one suit. As a court of equity was the proper forum in which to file a bill for specific performance in the first place, and the impleaded parties consented to the jurisdiction, and no claim of error is made on that account, all questions were disposed of in this equity suit. The judge held that, as there was no liability on the part of plaintiff Thunder Bay Quarries Company or cross-defendant American Steamship Company or its agents, Pollard was liable for the balance due plaintiff for stone that had been delivered. Defendant. Pollard appeals from decree against him and from denial of a decree against plaintiff and the others as cross-defendants.

The questions involved are largely those of fact. Did Pollard absolutely purchase the three cargoes of stone, did he enter into a conditional sales contract, *396

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Consolidated Paper Co. v. Department of Revenue
10 N.W.2d 833 (Michigan Supreme Court, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
3 N.W.2d 316, 301 Mich. 388, 1942 Mich. LEXIS 552, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thunder-bay-quarries-co-v-pollard-mich-1942.