Thos. M. Madden Co. v. State

48 Ill. Ct. Cl. 319, 1996 Ill. Ct. Cl. LEXIS 12
CourtCourt of Claims of Illinois
DecidedJanuary 23, 1996
DocketNo. 91-CC-3047
StatusPublished

This text of 48 Ill. Ct. Cl. 319 (Thos. M. Madden Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thos. M. Madden Co. v. State, 48 Ill. Ct. Cl. 319, 1996 Ill. Ct. Cl. LEXIS 12 (Ill. Super. Ct. 1996).

Opinion

OPINION

Epstein, J.

This is a contractors claim against the Illinois Department of Transportation (“IDOT”) for $73,352.15 of alleged additional work ordered by IDOT on a 1989 construction contract. This case arises out of IDOT contract no. 80340 for the construction of a double box culvert and removal of the old two-span concrete bridge on Illinois Route 47 over Rob Roy Creek (the “creek”) at U.S. Route 30 in Kane County, Illinois (original contract price $756,254.41).

The Claimant, Thos. J. Madden Co. (“Madden”), was hired by IDOT to build a new bridge over an old creek. The construction required diversion of the creek around the work site. To everyone’s great surprise, however, the creek diversion caused water to back up underground into the surrounding farm fields through drainage tiles located under those fields. Both IDOT and the contractor were blissfully unaware of the tiles until angry farmers complained that they could not plant their mysteriously wet fields. In response to the angry neighboring farmers’ complaints, IDOT ordered additional “dewatering” or diversion of the creek flow to reduce the water level to an altitude lower than that of the farmers’ fields (specifically, below elevation 651.0). The issue in this case is who pays the $73,000+ cost of the “additional” diversion.

Procedural Posture of this Claim

Thos. M. Madden Co. (“Claimant” or “Madden”) filed a one count complaint, sounding in contract, claiming $73,352.15 of additional compensation for the equipment, labor and miscellaneous costs of the “additional” dewatering work ordered by IDOT. The Respondent did not answer, which our rules permit, but filed its Departmental Report as allowed under our rules and later amended that report. The Claimant moved for summary judgment and the Respondent tardily moved to dismiss the claim for failure to state a cause of action, asserting that the contract failed to provide a basis for Claimant to recover.

Because both parties’ motions squarely contend that this claim is determinable on the face of the contract and the pleaded facts, and because both parties maintain that the relevant contract provisions are unambiguous and only require interpretation and application to the undisputed facts, we directed, without objection, that the motions would be treated as cross-motions for summary judgment, (order of May 24,1995.)

Contentions of the Parties

The Claimant, Madden, contends in essence that it had already met its dewatering and creek diversion duties under the contract terms when IDOT ordered the additional dewatering and that the added work was not required by any provision of the contract and is an “extra” that is separately compensable under the additional work provisions. Alternatively, Madden contends the unknown subsurface drainage problem was a changed condition that warrants additional compensation. Madden maintains that neither party in fact knew about the underground tiles in the area, that in any case it was IDOT’s responsibility to inform the contract bidders of any such condition, and that as a bidder and contractor it was unable to determine the existence of the tiles in off-site areas beforehand because drainage tiles are not of record and because contractors lack access to private offsite properties and therefore cannot malee inspections or subsurface tests.

The Respondent disputes Maddens claim in its entirety, contending that the additional dewatering was the contractor’s responsibility under the original contract terms and was within the scope of the contracted work. Respondent urges that the contractor is responsible for hidden underground conditions as well as avoidance of damage to private property under express contract terms, and was obliged by the contract to inspect the adjacent areas as well as the contract site. IDOT disputes the applicability of the “changed condition” clause. IDOT concedes that both parties were in fact unaware of the existence of the underground drain tiles, but claims that such tiles are commonplace in certain areas of Illinois and contends that this is sufficient to put the contractor on notice.

The Contract Issues

The interpretation issues presented concern the application of contract language to an unexpected circumstance — the presence of underground drainage tiles in areas adjacent to the construction site — in this construction job. It is undisputed that neither IDOT nor Madden actually knew beforehand that the subsurface drain tiles were there. Neither side contends that the off-site water backup was caused by subsurface conditions on the site itself. Both parties concede that underground drain tiles are commonplace in some areas of the State, at least in farm areas with certain soil conditions. A question of some precedential significance, therefore, is presented by this issue of who bears the responsibility for unknown underground tiles in IDOT construction projects under IDOTs standard specifications for road and bridge construction (“Standard Specifications”) which are part of most if not all IDOT construction contracts.

Of course, in construing this or any construction contract, it is axiomatic that the specific contract provisions directed at the particular project ordinarily take precedence, as a matter of interpretation, over the standard specifications, which are general provisions by their nature, to the extent that the two may be inconsistent or in conflict. However, it is also true that the law of interpretation of contracts mandates that provisions be reconciled insofar as possible and practicable, so that findings of conflicts are minimized. We are also mindful, especially in cases of complex government construction jobs, that the language of the contracts is almost always drafted by the State and is almost always written in terminology and style comporting with the standard conditions.

The primary contract provisions on which the Claimant relies, are as follows:

“It shall be the responsibility of the Contractor to divert the stream flow during construction in order to keep the construction areas free of water. The method of water diversion shall be subject to the approval of the Engineer and the cost shall be included in the unit bid price * e Culvert Details, specifications sheet no. 2 of 8 sheets.
"9. The undersigned further agrees that the Engineer may at any time during the progress of work covered by this contract order other work or materials incidental thereto and that all such work and materials as do not appear in the proposal or contract as a specific item accompanied by a unit price, and which are not included under the bid price for other items in the contract, shall be performed as extra work, and that he will accept full compensation therefor as provided in the specifications.” Madden Bid Proposal (on IDOT prescribed form).

The primary contract provisions on which the Respondent relies, all of which are provisions of the standard specifications, are as follows:

“502.01 Description.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
48 Ill. Ct. Cl. 319, 1996 Ill. Ct. Cl. LEXIS 12, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thos-m-madden-co-v-state-ilclaimsct-1996.