Thorpe See-Op Corporation

CourtArmed Services Board of Contract Appeals
DecidedFebruary 3, 2016
DocketASBCA No. 58960, 58961
StatusPublished

This text of Thorpe See-Op Corporation (Thorpe See-Op Corporation) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thorpe See-Op Corporation, (asbca 2016).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Thorpe See-Op Corporation ) ASBCA Nos. 58960, 58961 ) Under Contract No. W911 W6-05-C-0047 )

APPEARANCE FOR THE APPELLANT: Mr. Virgil Clark Vice President of Business Development

APPEARANCES FOR THE GOVERNMENT: E. Michael Chiaparas, Esq. DCMA Chief Trial Attorney Stephen D. Sanders, Esq. Trial Attorney Defense Contract Management Agency Dallas, TX Douglas R. Jacobson, Esq. Trial Attorney Defense Contract Management Agency Bloomington, MN

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL

INTRODUCTION

The government contracted with appellant, Thorpe See-Op Corporation, to develop an unmanned aerial vehicle that could be launched from an aircraft using a rocket launcher. Subsequently, the government terminated the contract for convenience, and appellant submitted a termination for convenience settlement proposal. Subsequently, the government demanded repayment of a portion of the interim payments that it had already made. Appellant appeals from the government's payment demand, and from the denial of its request for further payment pursuant to its settlement proposal. Because the appeals address the same issues, we address these consolidated appeals together. We deny the appeals. 1

1 We previously denied government's motion to dismiss and cross-motions for summary judgment. Thorpe See-Op Corporation, ASBCA Nos. 58960, 58961, 15-1BCA~35,833. FINDINGS OF FACT

On 24 January 2005, the Aviation Applied Technology Directorate (government) awarded Contract No. W911 W6-05-C-0047, a cost-plus-fixed-fee contract for $500,000 (including a fixed fee of $23,810) to appellant "develop a sensor and weapons equipped software test [Wing Store Unmanned Aerial Vehicle]" (R4, tab 1, at 1, 3, 4). On 9 May 2005, the government increased the contract amount by $70,000 to $570,000 (including a $3,334 increase in the fee to $27,144) (R4, tab 8 at 27-28). The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.216-7, ALLOWABLE COST AND PAYMENT(DEC 2002) (R4, tab 1at16), which provides:

(a) Invoicing. (1) The Government will make payments to the Contractor when requested as work progresses ....

(2) Contract financing payments are not subject to the interest penalty provisions of the Prompt Payment Act. Interim payments made prior to the final payment under the contract are contract financing payments ....

(g) Audit. At any time or times before final payment, the Contracting Officer may have the Contractor's invoices or vouchers and statements of cost audited. Any payment may be-

( 1) Reduced by amounts found by the Contracting Officer not to constitute allowable costs or

(2) Adjusted for prior overpayments or underpayments.

From 8 February 2005 through 3 May 2005, appellant submitted to the government seven vouchers for payment (Voucher Nos. 1-7) in amounts totaling $303,023.57 (R4, tab 110). The government subsequently paid-that amount (tr. 1/20). The record also contains appellant's Voucher No. 8, which lists $38,060.12 in costs and $1,903.01 in fees for the period 2 May 2005 through 12 June 2005 (app. supp. R4, tab 3a). Supporting that voucher are purchase receipts for materials and tools, an invoice for services, as well as timecards for various personnel (id.).

2 On 13 June 2005, the government ordered appellant to stop work (tr. 2/118). On 29-30 June 2005, a government team inspected appellant's worksite and determined that appellant had performed only 15% of the contract work (R4, tab 10 at 34). The government team concluded that there had been "little data generated to support the claim for $326,964.18 of effort,"2 that many of the items that appellant had shown to the government team had been generated after the government had ordered appellant to stop work, and that some of the appellant's work may have been associated with another contract, with the Department of the Navy (id.). On 22 August 2005, the contracting officer issued a unilateral modification terminating the contract for convenience pursuant to FAR clause 52.249-6, which the modification stated was read into the contract pursuant to G.L. Christian & Associates v. United States, 320 F.2d 345 (Ct. Cl. 1963) (R4, tab 12 at 40-41). The contracting officer's warrant recites his authority to perform "Duties as a Terminating Contracting Officer pursuant to FAR 42.302(a)(23)" (app. 4th supp. R4, tab 1).

FAR clause 52.249-6, TERMINATION (COST-REIMBURSEMENT) (MAY 2004), provides, in pertinent part:

(h) If the Contractor and the Contracting Officer fail to agree in whole or in part on the amount of costs and/or fee to be paid because of the termination of work, the Contracting Officer shall determine, on the basis of information available, the amount, if any, due the Contractor, and shall pay that amount, which shall include the following:

( 1) All costs reimbursable under this contract, not previously paid, for the performance of this contract before the effective date of the termination, and those costs that may continue for a reasonable time with the approval of or as directed by the Contracting Officer; however, the Contractor shall discontinue these costs as rapidly as practicable.

(2) The cost of settling and paying termination settlement proposals under terminated subcontracts that are properly chargeable to the terminated portion of the contract if not included in subparagraph (h)(l) of this clause.

2 The source for the government team's $326,964.18 figure is not apparent. Voucher No. 8 lists a cumulative cost figure through 12 June 2005 of $326,654 (app. supp. R4, tab 3a at 1). 3 (3) The reasonable costs of settlement of the work terminated, including-

(i) Accounting, legal, clerical, and other expenses reasonably necessary for the preparation of termination settlement proposals and supporting data;

(ii) The termination and settlement of subcontracts (excluding the amounts of such settlements); and

(iii) Storage, transportation, and other costs incurred, reasonably necessary for the preservation, protection, or disposition of the termination inventory. If the termination is for default, no amounts for the preparation of the Contractor's termination settlement proposal may be included.

(4) A portion of the fee payable under the contract, determined as follows:

(i) If the contract is terminated for the convenience of the Government, the settlement shall include a percentage of the fee equal to the percentage of completion of work contemplated under the contract, but excluding subcontract effort included in subcontractors' termination proposals, less previous payments for fee.

(i) The cost principles and procedures in Part 31 of the Federal Acquisition Regulation, in effect on the date of this contract, shall govern all costs claimed, agreed to, or determined under this clause.

In October 2006, appellant submitted a settlement proposal to the government (R4, tab 16 at 56). On 31 January 2007, the Defense Contract Audit Agency (DCAA), responding to a request to audit that proposal, determined that it had "significant concerns over the accuracy and reliability of [appellant's] books and records," and that "due to the repeated alteration of the books and records and poor internal controls exercised over them, it will be impossible for us to render an audit opinion on the total costs (direct costs or indirect rates) for this subject contract" (R4, tab 19 at 62). In May 2011, appellant presented two revised termination settlement proposals,

4 ultimately requesting $339,071.88 (R4, tabs 36, 37).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

G. L. Christian and Associates v. The United States
320 F.2d 345 (Court of Claims, 1963)
Jacobs Engineering Group, Inc. v. United States
434 F.3d 1378 (Federal Circuit, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Thorpe See-Op Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thorpe-see-op-corporation-asbca-2016.