Thorn & Hunkins Lime & Cement Co. v. St. Louis Expanded Metal Fire Proofing Co.

77 Mo. App. 21, 1898 Mo. App. LEXIS 490
Missouri Court of Appeals·Decided November 29, 1898·Published·Cited by 1 cases

Opinions

Biggs, J.

The plaintiff sues the defendant on its acceptance of an order for $1,000 drawn by the King Granitoid Construction Company. The following is the order and a copy of the acceptance as written and punctuated by the acceptor.

“St. Louis Iron Wire & Expanded Metal Co., “Odd Fellows Bldg., City.

“Gentlemen: — Please pay to the order of the Thom & Hunkins Lime & Cement Co., one thousand dollars ($1,000), and charge same to our account with you for our contract at the Liggett & Meyers Tobacco Co.'s Warehouses Nos. 1 and 2.

“King Granitoid Construction Co.,

“Per William J. King, 2d Pres.

“Accepted February 10, 1897.

“The above contract accepted, payable in sixty days or sooner, if we receive payment before said date. “St. Louis Expanded Metal Fire-Proofing Co.,

“D. E. Garrison, Jr., Treas.”

The action was brought sixty days after the date of the acceptance, the plaintiff making no claim or pretense of a liability prior to the expiration of the sixty days. The petition also averred that at the time of the acceptance of the order the King Granitoid Construction Company (hereinafter designated as the Construction Company), owed, the plaintiff $1,000, and that the defendant was indebted to the Construction Company in a sum in excess of $1,000.

In addition to a general denial the defendant answered, to wit: “And for further answer, defendant says that said order was drawn by the said King Granitoid Construction Company, to be paid out of a particular fund, to wit, moneys which it was at the time of said acceptance supposed by this defendant would be due the said King Granitoid Construction Company on [25] the said contract at the Liggett & Meyers Tobacco Company Warehouses Nos. 1 and 2, and defendant says that the said King Grranitoid Construction Company thereafter abandoned their work under said contract and never did perform the said contract, and that no moneys ever became due to the said Grranitoid Construction Company from defendant, out of which the said acceptance could be paid, or was payable, wherefore, having fully answered, defendant prays to be dismissed with its costs.”

The cause was submitted to the circuit court without a jury. The finding and judgment were for the plaintiff for the full amount of the order. The defendant has appealed.

At the commencement of the trial the defendant objected to the introduction of any evidence, upon the ground that the petition failed to state a cause of action in that the acceptance was conditional and the pleading failed to note the condition and aver a liability consistent with it. The objection was overruled, and the defendant excepted. It is insisted by the counsel for appellant that upon the face of the acceptance and order the amount of the order was made payable out of a particular fund thereafter to be collected by the defendant from the Liggett & Meyers Tobacco Company and belonging to the Construction Company, which made the acceptance a conditional one and required the plaintiff to aver and prove the receipt of such fund or some portion of it by the defendant. We can not concur in this view. Reading the acceptance as punctuated it is impossible without the aid of extraneous facts, to say to what the last clause refers. This clause is relative, and the question is whether it was intended to qualify all that precedes it or only that portion which indicates a possible payment at an earlier date than sixty days. Again the acceptance says, “if we [26] receive payment.” What payment? Was it intended to refer to money belonging to the Construction Company to be thereafter received by appellant, or did it have reference to funds to be thereafter collected and belonging to the appellant and out of which it expected to get the money to meet its obligation. If the former was meant, then the acceptance is conditional as the order was to be paid if the appellant received money of the drawer sufficient to pay it, but if the latter was intended, then it is clear that the acceptance was unconditional'. .If the comma in the sentence could be placed after the word days, there would be no difficulty whatever about the true interpretation. The acceptance would be unconditional beyond dispute. But the evidence shows that it was punctuated by the acceptor as it herein appears, and we must accept and construe the writing as it left his hands. 1 Bish. Contracts, sec. 730; Ewing v. Bump, 11 Pet. 41; Sutherland, Stat. Const., sec. 232. The writing being thus ambiguous, the circuit court did right in overruling the appellant’s objection to the admission of evidence, for if the alleged conditional character of the agreement could be made to appear only by inquiring into the attending facts it is manifest that in order to determine the question it was necessary for the court to hear the evidence. We will therefore overrule the first assignment.

Construction of wriuen contract,

Where a written contract is unambigous its construction is always a matter of law for the court, and even where an ambiguity exists and it is solved by extraneous matter about which there is no dispute, the construction is still for the court. But . . . „ . _ , where the extrinsic facts are unconceded and rest upon conflicting testimony from which different inferences might be drawn, it is for the triers of the facts to draw the inferences and say what the parties meant by the contract.- Mathews v. [27] Danahy, 26 Mo. App. 660; Enterprise Soap Works v. Sayers, 55 Mo. App. 16. These principles obtain and must be applied in the discussion and disposition of the remaining assignment.

Free access — add to your briefcase to read the full text and ask questions with AI

Thorn & Hunkins Lime & Cement Co. v. St. Louis Expanded Metal Fire Proofing Co., 77 Mo. App. 21, 1898 Mo. App. LEXIS 490 (Mo. Ct. App. 1898).

77 Mo. App. 21 (Thorn & Hunkins Lime & Cement Co. v. St. Louis Expanded Metal Fire Proofing Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Brooks v. J. R. Watkins Medical Co.
1921 OK 109 (Supreme Court of Oklahoma, 1921)