Thormahlen v. Citizens Savings and Loan

698 P.2d 512, 73 Or. App. 230
CourtCourt of Appeals of Oregon
DecidedApril 17, 1985
Docket81-2560-J-3; CA A28839
StatusPublished
Cited by4 cases

This text of 698 P.2d 512 (Thormahlen v. Citizens Savings and Loan) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thormahlen v. Citizens Savings and Loan, 698 P.2d 512, 73 Or. App. 230 (Or. Ct. App. 1985).

Opinion

*232 BUTTLER, P. J.

Plaintiffs brought this action for damages against defendant, their construction lender, contending that defendant breached its contractual and common-law duties to them by disbursing construction loan funds in excess of the percentage of completion of a project known as the Ravenwood Condominiums. They also sought rescission of two deeds of trust given to defendant to secure additional financing of the project. Defendant counterclaimed for foreclosure of the trust deeds. 1 At the close of plaintiffs’ case, the trial court granted defendant’s motion to dismiss plaintiffs’ seven claims for relief. 2 After trial, the court entered judgment for defendant on plaintiffs’ second amended complaint and, on defendant’s counterclaims, entered a decree foreclosing the two trust deeds.

On appeal, plaintiffs contend that the trial court erred in dismissing their first two claims for relief and in refusing to admit certain testimony. 3 The underlying issue is whether defendant owed plaintiffs either a contractual or common-law duty to monitor the progress of the project and to limit its disbursement of the loan proceeds to the percentage of completion of construction. On the contract claim, both parties contended in argument on defendant’s motion to dismiss that the meaning of the contract was for the court, and we cannot say that the court erred in deciding the question as so posed. On plaintiffs’ common law duty claim, we conclude that defendant had no such duty. Accordingly, we affirm.

In 1979, plaintiffs began planning for the development of a 24-unit condominium project on real property they owned in Ashland. They sought financing for the project from defendant, located in Medford. Plaintiffs anticipated a sales *233 price for the project, to be known as the Ravenwood Condominiums, of approximately 1.4 million dollars and sought financing in the amount of $849,000. Defendant agreed to lend $800,000, with $400,000 to be disbursed for each phase. Plaintiffs requested defendant to lend $542,600 on the first phase, and the balance on the second phase.

Defendant agreed, and on July 13, 1979, the parties executed a commitment letter, by which defendant agreed to lend a total of $800,000, to be disbursed during the two phases as requested by plaintiffs. That letter also stated, in part, that defendant’s commitment to make the loan was subject to the following:

“2A. Satisfactory periodic inspections of subject property during the construction process prior to each disbursement of loan funds. Inspections to be done by representatives of the mortgagee. * * * *
“3F. Signators to documents as set forth by mortgagee shall be Philip A. Thormahlen, Sharon C. Thormahlen, and Donald E.G. Gorman.”

On August 27, 1979, plaintiffs and their contractor executed a form of construction loan agreement provided by defendant. That agreement provided, in pertinent part:

“The undersigned expressly covenants with CITIZENS SAVINGS AND LOAN ASSOCIATION
hereinafter referred to as ‘the Association,’ and agrees in consideration of the granting of a loan by the Association, to do and perform the following acts and things: <<* * * * *
“SECTION 2.
“It is further understood:
“1. That the Association is authorized to disburse funds under its control in said construction loan account, together with the net proceeds of the loan, only in proportion to its inspector’s report of progress, or by Architect’s or Superintendent’s Certificate accompanied by a proper affidavit from the contractor. * * * *
“3. That the Association may, at any time, without consent of the undersigned, if in its opinion it becomes necessary *234 so to do, pay bills and/or complete said building or buildings in accordance with plans and specifications, etc., on file with it, using for such purposes, including therein the unexpended net proceeds of this loan, upon which funds the Association shall have a first lien for any one or more such purposes, but nothing herein contained shall be in any way construed as a covenant on the Association’s part to so pay or complete. * * * *
“6. The owner has accepted, and hereby accepts the sole responsibility for the selection of his own contractor and contractors, all materials, supplies and equipment to be used in the construction, and the Association assumes no responsibility for the completion of said building, or buildings, according to the plans and specifications and for the contract price. In the event that the funds on hand are found to be insufficient to erect the building and complete the same in accordance with the plans and specifications and any agreed extras, the owner shall place and hereby agrees to place such additional funds in his construction loan account as may be necessary to complete the building or buildings, according to such plans and specifications, plus any extras authorized by him.
“The above promises and agreements are made for the purpose of inducing CITIZEN SAVINGS AND LOAN ASSOCIATION of Medford, Oregon, to make a loan upon the following described property and improvements to be constructed thereon, to-wit: Ravenwood Condominiums, Ash-land, Oregon.”

A few days before the execution of the construction loan agreement, various other documents were also signed, including a note secured by a trust deed covering the real property to be developed.

From September through December, 1979, Teresa O’Connor, vice-president of defendant, was the person responsible for making project inspections. Although O’Con-nor had several years of banking experience, she had no experience in construction or in administering construction loans. The normal procedure was for plaintiff Sharon Thormahlen to submit a disbursement request to defendant, for defendant to issue a check as requested and for Mrs. Thormahlen to pay the amounts shown on the disbursement request.

*235 Construction on the project began in the fall of 1979, and the first disbursement was made in September. Written reports were prepared for inspections of the project on September 20 and October 9, although no percentage of completion was calculated at that time. Approximately $65,700 was disbursed in October, and $90,000 in November. Sometime during the fall, defendant became aware of cost overruns on the project. O’Connor testified that she had several conversations with plaintiff Sharon Thormahlen in which Mrs. Thormahlen demanded that construction loan funds be disbursed to satisfy cost increases. Despite its position that the requests were unreasonable, defendant acquiesced in those demands. In early November, O’Connor met with plaintiffs’ contractor to discuss cost overruns on the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blais v. Warren Five Cents Savings Bank
1993 Mass. App. Div. 213 (Mass. Dist. Ct., App. Div., 1993)
Parker v. Columbia Bank
604 A.2d 521 (Court of Special Appeals of Maryland, 1992)
Federal Deposit Insurance v. Fordham (In Re Fordham)
130 B.R. 632 (D. Massachusetts, 1991)
Seymour v. New Hampshire Savings Bank
561 A.2d 1053 (Supreme Court of New Hampshire, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
698 P.2d 512, 73 Or. App. 230, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thormahlen-v-citizens-savings-and-loan-orctapp-1985.