Thompson v. Loring Oil Co.

50 F. Supp. 213, 1943 U.S. Dist. LEXIS 2603
CourtDistrict Court, W.D. Louisiana
DecidedMay 6, 1943
Docket649
StatusPublished
Cited by17 cases

This text of 50 F. Supp. 213 (Thompson v. Loring Oil Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thompson v. Loring Oil Co., 50 F. Supp. 213, 1943 U.S. Dist. LEXIS 2603 (W.D. La. 1943).

Opinion

DAWKINS, District Judge.

This suit was filed in the state court for the Parish of Sabine and removed here on the ground of diverse citizenship. It demands the sum of $4,196.30 as overtime and penalties for labor alleged to have been performed as an oil pumper. The petition alleges that the plaintiff was entitled to pay for 12 hours a day 7 days a week for the period from March 1, 1941, until December 27 of that year; that he was paid for 35 hours a week, while he worked 84; that his base pay was 71‡ per hour and for the first 40 hours he was entitled to receive $28.40, but for the additional 44 hours he should have received pay for 1% times the regular rate or $1.065 per hour in addition to $48.86 per week; that after deducting what he actually received at 7l<jt an hour for 35 hours a week, there remained due to him the sum of $2,021.47, and that under the “Fair Labor Standard Act” of 1938, 29 U.S.C.A. § 201 et seq. he was entitled to recover the same amount additional, thus making the total the sum sued for.

Defendant answered that it had paid plaintiff at the rate of 7If, an hour for a work week of 35 hours, and for all overtime “in excess of 35 hours of work per week, plaintiff was paid on the basis of $1.065 an hour which included all that was due him”.

The evidence shows that the duties of plaintiff required him to visit and look after some six pumping wells. “Two of the wells were about a mile and a quarter north of where plaintiff lived, there was another well about a mile and a quarter east of him, there was another well about three miles south of him, and another well about a mile and ouc-half or two miles west, and still another well, called the Martinas Well, approximately seven miles west of where-he lived”.

Formerly there had been three persons employed to perform this service, but be *214 ginning March 1, 1941, they were reduced to two. Plaintiff would take over at 12 o’clock midnight and the other man would relieve him at noon midday. When plaintiff went on duty he would first take the other pumper to his home, a distance of approximately a mile and a half and “go back by two wells that was north of me”. If any trouble was found he would either go on to the others and back later, or would correct it at that time, if he could. Where the trouble was such as with spark plugs, magneto, or a belt had slipped, he would" repair it, but if more serious, he would “report it to the office before 7 o’clock in the morning.” He serviced five of the wells once a day and the sixth once a week, the- latter being the Martinas Well, which was some 7 miles distant.

He further testified that the wells were equipped with a device called a “barker”, fastened on the exhaust pipe of the engine, the sound of which, as to the wells near his home would wake him up if anything went wrong. If all the wells were working smoothly he could make the rounds in an hour, but if not, it took longer, the average being from one to three hours. After making his rounds, shortly after going on duty, he would go to his home and go to bed, but had to report at the office about 7 o’clock A. M. After that, until 12 o’clock noon, he was subject to call. If he worked after mid-day he was paid at the same rate of 710 an hour. He was credited on the payroll with 35 hours a week or 5 hours per day for 7 days, and such additional time as, according to the defendant’s contention, he actually worked. Plaintiff signed the payrolls, received his checks, and made no protest about being paid for five hours a day.

Plaintiff called as a witness in his own behalf one John Strong, who filled in for plaintiff a week while the latter was off duty. Strong testified that the truck would be turned over to him at 12 midnight. At about 4 A.M. he would make the rounds but because of his unfamiliarity with the situation, it would take him until about 7 o’clock to get back, and “if everything was running good I went back to the house and stayed until about 11 o’clock, and then made the two wells close to where I lived and turned the truck over to Mr. Barr (the other pumper) around 11:30 or 12:00 o’clock”.

Plaintiff’s wife was also called and testified that he took over the car at 12 o’clock, and in response to plaintiff’s counsel, gave answers as follows:

“Q. During that period of time, what time of night or day did he go to work? A. Well, did you just want me to tell the hours? He went to work at —he took over the car at twelve o’clock at night.

“Q. How long would it be before he would come back to the house when everything was going well? A. I couldn’t tell you every time, but sometimes it was several hours and he would come in and maybe sleep awhile and then get up. He always ate breakfast between six and six-thirty, and went up to the office by seven. But of course I couldn’t tell you every time because I don’t know.

“Q. Would you know that he was called away from the house at all hours? A. I didn’t get that.

“Q. Was he called to go to the lease-at all hours of the night? A. Yes, sir, from twelve at night to twelve next day.”

Emmett Remedis, called on behalf of plaintiff, testified simply as to the character of the roads over which plaintiff had to travel, and that he (Thompson) came back home each day about 12 o’clock noon.

In addition to the above, plaintiff called on cross examination Nolan Winn, who was one of the superintendents during the time plaintiff worked for defendant, and who testified that plaintiff worked as a rule five hours a day 7 days a week, but when asked if plaintiff worked from 7 in the morning until noon, answered, “No sir, I do not think so”. He said that the five-hours with which plaintiff was credited was. not for the period from 7 to 12 A. M. but “covered five hours, no matter what time he might put in”. Finally the witness explained :

“Pie was required to put in five hours a day from 12_ midnight to 12 noon; anytime-during that time”.

J. M. Blair, another superintendent for the defendant, was also called on cross examination. He had worked for the defendant up to April 1, 1941 (one month after-plaintiff started on the two day shift), and. both he and Winn were working for a “connected company” at the time they testified and Blair has been in Illinois since April 1, 1941. He said that plaintiff was not required to stay on the job the whole 12 hours, and his pay was “for the five hours he put in, sometime during that period”. Asked if plaintiff “was told to quit after he worked five hours” Blair replied, “I do not remember”. Plaintiff was paid overtime or- *215 given time off the next day in case he did work over five hours during one day. When three pumpers were used they were each subject to call for 8 hour shifts but they did not work 8 hours and were also credited with five hours a day whether they worked that much or not. The witness kept the time while he was with defendant and “was supposed to know” how long plaintiff worked. The roustabouts worked six hours a day but only six days a week. Everyone then worked 35 hours a week. He testified that the payroll sheets showing time plaintiff worked were correct. The witness lived at the warehouse, about three miles from plaintiffs residence, and also made the rounds of the wells every day himself.

Plaintiff finally called J. T.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Allen Parish Police Jury
526 So. 2d 1190 (Louisiana Court of Appeal, 1988)
Goff v. City of Airway Heights
730 P.2d 691 (Court of Appeals of Washington, 1986)
Bernardi v. Village of North Pekin
482 N.E.2d 101 (Appellate Court of Illinois, 1985)
John A. Allen v. Atlantic Richfield Co.
724 F.2d 1131 (Fifth Circuit, 1984)
Hogan v. Kansas City
516 S.W.2d 805 (Missouri Court of Appeals, 1974)
Pilkenton v. Appalachian Regional Hospitals, Inc.
336 F. Supp. 334 (W.D. Virginia, 1971)
Hofler v. Spearin, Preston & Burrows, Inc.
51 Misc. 2d 758 (Civil Court of the City of New York, 1966)
Deyá v. Otis Elevator Co.
91 P.R. 649 (Supreme Court of Puerto Rico, 1965)
Guillermo Deyá v. Tribunal Superior de Puerto Rico
91 P.R. Dec. 669 (Supreme Court of Puerto Rico, 1965)
Cochrun v. County of San Bernardino
229 Cal. App. 2d 362 (California Court of Appeal, 1964)
Blakeley v. Fresno Oil Co.
208 S.W.2d 902 (Court of Appeals of Texas, 1948)
Electron Corp. v. Wilkins
189 P.2d 142 (Supreme Court of Colorado, 1947)
Straughn v. Schlumberger Well Surveying Corp.
72 F. Supp. 511 (S.D. Texas, 1946)
Bohn v. B & B Ice & Coal Co.
63 F. Supp. 1020 (W.D. Kentucky, 1946)
Davies v. Onyx Oils & Resins, Inc.
63 F. Supp. 777 (D. New Jersey, 1946)
Skelly Oil Co. v. Jackson
1944 OK 179 (Supreme Court of Oklahoma, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
50 F. Supp. 213, 1943 U.S. Dist. LEXIS 2603, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thompson-v-loring-oil-co-lawd-1943.