Thompson Tree and Spraying Service, Inc. v. City of McComb, Mississippi

271 So. 3d 623
CourtCourt of Appeals of Mississippi
DecidedNovember 20, 2018
DocketNO. 2017-CA-00640-COA
StatusPublished
Cited by1 cases

This text of 271 So. 3d 623 (Thompson Tree and Spraying Service, Inc. v. City of McComb, Mississippi) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thompson Tree and Spraying Service, Inc. v. City of McComb, Mississippi, 271 So. 3d 623 (Mich. Ct. App. 2018).

Opinion

FAIR, J., FOR THE COURT:

¶ 1. In this contract case, Thompson Tree and Spraying Service Inc., doing business as Live Oak Construction ("Live Oak"), appeals a judgment rendered by the Pike County Circuit Court in favor of Live Oak on some claims but not all. The trial court awarded Live Oak a total of $7,016.75 against the City of McComb. Live Oak now appeals.

FACTS

¶ 2. Following the statutory process for bidding requirements, 1 the City advertised for bids to construct three buildings at the McComb Sports Park, a center for baseball and softball fields for the City. Live Oak was the lowest bidder at $252,000 and was awarded the contract. Steve Cox, a McComb architect, drafted the plans for the City and supervised the work through completion. Cox was named as a defendant but was dismissed from the lawsuit on motion for summary judgment.

¶ 3. On completion of the project by Live Oak, the City paid the contract price, along with an additional sum of $1,941.60 reflected in a written construction contract change, 2 (change order) agreed upon by Live Oak, Cox, and the City. The contract called for completion of construction 120 days after the "Notice to Proceed"-given by Cox on January 20, 2014-on penalty of $250 per day in liquidated damages if it took longer. Substantial completion occurred on September 19, 2014. The term of construction lasted for eight months rather than four as outlined in the contract. The City did not seek liquidated damages. Live Oak submitted that the City is to blame for the entire 120-day delay and sought related damages in the amount of $135,760.73 above the paid contract price.

¶ 4. After a bench trial, the trial court found for Live Oak on some of the claimed contract breaches and awarded a judgment against the City for $4,876.75. Live Oak filed motions under Mississippi Rules of Civil Procedure 52(b) and 59(e) to amend the trial court's finding of facts and final judgment. Subsequently, the order was amended, and a total judgment of $7,016.75 was awarded to Live Oak. On appeal, Live Oak claims that the trial court committed manifest error in not finding the City wholly liable for the breaches it asserted caused the delay and argues that the evidence presented at trial was unrebutted. Further, Live Oak argues the trial court erred in awarding Live Oak an arbitrary amount of damages for the City's liability. For the following reasons, we affirm.

DISCUSSION

¶ 5. Live Oak contends that it is entitled to damages above the contract price in light of the delay caused by the City. It specifically highlights the costs and overhead associated with the following: (1) lack of power to the job site; (2) moving the press box from its original location; (3) extra dirt work not originally agreed upon; (4) lintels that were not specified on the architect's plan; and (5) overall delay.

¶ 6. "The applicable standard of review will not permit that the finding of the trier of fact be disturbed on appeal if there is substantial supporting evidence even if under the same proof we might have found otherwise. The finding of fact may not be set aside unless manifestly wrong." Bailey v. Worton , 752 So.2d 470 , 474 (¶ 9) (Miss. Ct. App. 1999). Where a circuit judge sits without a jury, the deference given is that which is given to a chancellor's findings. Sweet Home Water & Sewer Ass'n v. Lexington Estates Ltd. , 613 So.2d 864 , 872 (Miss. 1993). "Findings of fact made by a chancellor which are supported by credible evidence[ ] may not be set aside on appeal." Bailey , 752 So.2d at 474 (¶ 9).

It is settled law that the chancellor is the judge of the weight and worth of the testimony and the court's decree based upon the evidence will not be disturbed unless manifestly wrong. Therefore, when the chancellor is confronted with conflicting testimonies, he determines which has more credibility. Even if this Court disagreed with the lower court on the finding of fact and might have arrived at a different conclusion, we are still bound by the chancellor's findings unless manifestly wrong.

Reed v. Weathers Refrigeration & Air Conditioning Inc. , 759 So.2d 521 , 524 (¶ 10) (Miss. Ct. App. 2000) (citation and internal quotation marks omitted). "Additionally, where the chancellor has made no specific findings, we will proceed on the assumption that he resolved all such fact issues in favor of the appellee."

Lee v. S. Miss. Elec. Power Ass'n , 17 So.3d 597 , 599 (¶ 7) (Miss. Ct. App. 2009).

¶ 7. Live Oak points to various contract provisions to support its claim for damages associated with the delay. We highlight the applicable sections:

ARTICLE 10 CHANGES IN THE WORK
§ 10.1 The Owner, without invalidating the Contract, may order changes in the Work within the general scope of the Contract consisting of additions, deletions or other revisions, the Contract Sum and Contract Time being adjusted accordingly in writing. If the Owner and Contractor can not agree to a change in the Contract Sum, the Owner shall pay the Contractor its actual costs plus reasonable overhead and profit.
....
§ 10.3 If concealed or unknown physical conditions are encountered at the site that differ materially from those indicated in the Contract Document or from those conditions ordinarily found to exist, the Contract Sum and Contract Time shall be subject to equitable adjustment.
ARTICLE 11 TIME
§ 11.2 If the Contractor is delayed at any time in progress of the Work by changes ordered in the Work, or by labor disputes, fires, unusual delay of deliveries, unavoidable casualties or other causes beyond the Contractor's control, the contract time shall be subject to equitable adjustment.

A. Lack of Power

¶ 8. Live Oak contends that it was not given power to the construction site for a period of three months, which was guaranteed by the City and then was forced to rent generators. Live Oak claims the rental caused delay and out-of-pocket expenses that were not foreseen when the bid was made. The City claims that it never guaranteed power and merely offered to make a phone call to Entergy to ask for power.

¶ 9. The record indicates that the specifications state that the "[o]wner will provide ... electrical services to all buildings" but make no mention about providing power to the construction site prior to erecting the buildings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
271 So. 3d 623, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thompson-tree-and-spraying-service-inc-v-city-of-mccomb-mississippi-missctapp-2018.