Thompson Thrift Contruction, Inc. v. Modus Studio, Pllc

2025 Ark. App. 193, 709 S.W.3d 898
CourtCourt of Appeals of Arkansas
DecidedApril 2, 2025
StatusPublished

This text of 2025 Ark. App. 193 (Thompson Thrift Contruction, Inc. v. Modus Studio, Pllc) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thompson Thrift Contruction, Inc. v. Modus Studio, Pllc, 2025 Ark. App. 193, 709 S.W.3d 898 (Ark. Ct. App. 2025).

Opinion

Cite as 2025 Ark. App. 193 ARKANSAS COURT OF APPEALS DIVISION III No. CV-23-673

THOMPSON THRIFT Opinion Delivered April 2, 2025 CONSTRUCTION, INC. APPELLANT APPEAL FROM THE WASHINGTON COUNTY CIRCUIT COURT [NO. 72CV-21-2676] V.

HONORABLE BETH STOREY MODUS STUDIO, PLLC; CENTER BRYAN, JUDGE POINT CONTRACTORS, INC.; ICRETE TECHNOLOGIES, LLC; PRESTIGE CONSTRUCTION & DEVELOPMENT, LLC; ROOFING SYSTEMS, INC.; AND U.S. FRAMING, INC. REVERSED APPELLEES

BRANDON J. HARRISON, Judge

The Pantheon in Rome has stood for more than 1,900 years. If it collapsed

tomorrow, the claim-accrual and statute-of-limitations principles that apply in Arkansas to

ordinary negligence claims would give an injured person three additional years to sue those

who were alleged to have negligently designed or constructed it.1 That’s a long time to stay

on the legal hook. So in the 1960s, like legislatures in a number of other states, the Arkansas

General Assembly changed the accrual and limitations principles that apply to tort or

contract claims for damages “caused by any deficiency in the design, planning, supervision,

1 We would take the defense side of that case. or observation of construction or the construction and repairing of any improvement to real

property” against a person “performing or furnishing the design, planning, supervision, or

observation of construction or the construction and repair of the improvement.” Ark. Code

Ann. § 16-56-112(a) & (b) (Repl. 2005). With a few express exceptions, for those

architectural or construction-type claims “[n]o action . . . shall be brought” more than five

years from the date of substantial completion of the improvement, even if the limitation

period for that kind of claim has not run—and even if no claim exists yet because no damage

or injury has yet occurred. Section 112 has been called Arkansas’s only statute of repose. 2

David Newbern, John Watkins & D.P. Marshall Jr., Arkansas Civil Practice & Procedure § 5:11

(5th ed. 2010).

This appeal presents an issue of first impression in Arkansas: may a party who timely

filed claims that are covered by the statute of repose (section 112) refile them under the

savings statute (Ark. Code Ann. § 16-56-126 (Repl. 2005)) within one year of a dismissal

without prejudice, even if the repose period in section 112 has ended before the one-year

savings statute period had run? Put another way, does the statute of repose trump, toll, or

defeat (different words, same end) the savings statute? The circuit court ruled that the

savings statute did not take pride of place and therefore dismissed Thompson Thrift

Construction, Inc.’s (Thompson’s) refiled claims against Modus Studio, PLLC (Modus) with

prejudice. We respectfully disagree and reverse.

The lead up to this appeal includes three lawsuits in Washington County Circuit

Court and one arbitration. West Center Partners, LLC (WCP) filed the first lawsuit in July

2019 alleging that Thompson was responsible as prime contractor for undetermined

2 construction defects in a Fayetteville student housing project WCP owned. Before filing

an answer, Thompson and its surety Fidelity and Deposit Company of Maryland

(collectively “Thompson”) filed a third-party complaint against eight third-party defendants,

including Modus, the project’s architect. Thompson alleged that to the extent it was liable

to WCP, the third-party defendants “each are or may be liable to [Thompson] for their

respective breaches of contract with [Thompson], breaches of applicable implied and express

warranty, contribution and indemnification.” Thompson included claims for negligence,

contribution, breach of contract, breach of implied warranties, and indemnity.

The repose periods in section 112(a) & (b) run from the date an improvement to real

property is substantially complete. The parties agree that date was 14 August 2014.

Thompson filed its third-party complaint on 14 August 2019—within five years. But WCP

nonsuited its complaint to pursue its claims in arbitration. The circuit court found this

“render[ed] moot the claims and causes of action” in Thompson’s third-party complaint and

dismissed it without prejudice on 2 December 2020. Thompson opposed the dismissal but

did not appeal.

Thompson moved the arbitrator to join five subcontractors in the arbitration. The

arbitrator allowed it. Four subcontractors sued to stop that. The circuit court entered a

declaratory judgment compelling WCP and Thompson not to arbitrate with them in May

2022. WCP went on to win a $13,529,726 award in arbitration against Thompson alone.

Thompson paid it. So Thompson is left holding the bag, so to speak, unless it can recover

in this action, filed 364 days after the court dismissed its third-party complaint (savings statute

3 ✔)—but more than seven years after the construction project was substantially complete

(repose statute ❌).

All defendants naturally argued that section 112 barred Thompson’s refiled claims.

The circuit court uniformly ruled the savings statute did not toll the repose periods in section

112. But Modus was the only party dismissed from the case as a result, because contractual-

indemnity claims Thompson pleaded against the other defendants are not subject to section

112.2

To save the effort and expense of holding a two-week trial without Modus—and

doing it over, with Modus, if we reversed the repose ruling later—the circuit court certified

the order granting Modus summary judgment for immediate appeal. Ark. R. Civ. P. 54(b).

The court made detailed findings about the waste of resources that would result if an appeal

were postponed. It observed that Thompson’s dismissed claims (against all defendants) and

those set for trial (against all but Modus) “all arise from the same construction project” of

which Modus was architect. Resolving them would “necessarily require an allocation of

fault (if any) among all of these defendants[,]” so Modus would be “entitled to relitigate

virtually all issues raised in the first trial” if we reversed the repose ruling later. Further, the

result of an immediate appeal “could impact the previously dismissed claims against the rest

of the defendants for negligence, breach of contract, breach of warranty, and contribution.”

Thompson filed a timely notice of appeal.

2 Ray & Sons Masonry Contractors, Inc. v. U.S. Fid. & Guar. Co., 353 Ark. 201, 114 S.W.3d 189 (2003). Thompson did not dispute that section 112 applied to its other claims but contended it could refile them under the savings statute.

4 We begin with the text of the savings statute, emphasizing five words that are chiefly

in contention:

(a)(1) If any action is commenced within the time respectively prescribed in this act, in §§ 16-116-101 [to] 16-116-107, in §§ 16-114-201 [to] 16-114- 209, or in any other act, and the plaintiff therein suffers a nonsuit, . . . , the plaintiff may commence a new action within one (1) year after the nonsuit suffered or judgment arrested or reversed.

Ark. Code Ann. § 16-56-126(a)(1) (emphasis added).

Thompson sees an easy analysis: (1) Act 42 of 1967, codified at section 16-56-112(a),

was an “other act”; (2) it prescribed “the time” within which an action must commence;

(3) Thompson brought its claims in time; and (4) they were dismissed without prejudice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCastlain v. Elmore
10 S.W.3d 835 (Supreme Court of Arkansas, 2000)
Summerville v. Thrower
253 S.W.3d 415 (Supreme Court of Arkansas, 2007)
Matter of Adoption of Martindale
940 S.W.2d 491 (Supreme Court of Arkansas, 1997)
Forrest City MacHine Works, Inc. v. Lyons
866 S.W.2d 372 (Supreme Court of Arkansas, 1993)
Carter v. Hartenstein
455 S.W.2d 918 (Supreme Court of Arkansas, 1970)
Casey v. Burdine
217 S.W.2d 613 (Supreme Court of Arkansas, 1949)
Yates v. Phillips
22 S.W.2d 559 (Supreme Court of Arkansas, 1929)
Screeton v. Crumpler
617 S.W.2d 847 (Supreme Court of Arkansas, 1981)
East Poinsett County School District No. 14 v. Union Standard Insurance
800 S.W.2d 415 (Supreme Court of Arkansas, 1990)
David Thomas and Cynthia Parker v. Adam Gray Amanda Cox And Dominique Belles
2023 Ark. App. 281 (Court of Appeals of Arkansas, 2023)
Scott White and Jamie White v. Hunter Owen and John Does 1-3
2021 Ark. 31 (Supreme Court of Arkansas, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2025 Ark. App. 193, 709 S.W.3d 898, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thompson-thrift-contruction-inc-v-modus-studio-pllc-arkctapp-2025.